G.R. No. 12283. July 25, 1918
ARTHUR F. ALLEN, PLAINTIFF AND APPELLEE, VS. THE PROVINCE OF TAYABAS, DEFENDANT AND APPELLANT.
MALCOLM, J.:
Public Works, and Arthur F. Allen, contractor, entered into a contract whereby
the contractor agreed to construct five reenforced concrete bridges for P39,200.
This contract was in the usual form. One provision was that the bridges were to
be constructed “in accordance with the said advertisements, instructions to
bidders, general conditions, plans, specifications, proposal, and this
agreement.” Other paragraphs of the contract concerned the method and rate of
payment for extras.
Four of the bridges were accepted by the Government and paid for. The dispute
between the parties arose as to the fifth bridge, No. 53.3 and as to certain
extras. As to this bridge, the Province of Tayabas paid to the contractor P4,360
on account of the contract price thereof, but refused to pay the balance of
P2,840, because plaintiff had deviated from the specifications and because the
work was defective. The province further refused to pay for certain extras. To
recover the balance upon the contract was the purpose of the contractor in
bringing action for ^9,685 (amended complaint), alleged to be due him by the
Province of Tayabas. The common averments of the six causes of action were: (1)
Residence; (2) the contract; (3) the faithful compliance “with all the terms and
conditions of the said contract” on the part of the contractor, and completion
and delivery of the bridges in question; (4) refusal of defendant to pay
plaintiff the balance due for bridge No. 53.3, for certain extras, and as
damages, although frequently requested to do so. Defendant demurred to the
complaint on the ground that it did not state facts sufficient to constitute a
cause of action, because: (a) The approval of the Governor-General to the
contract had not been given as contemplated by section 2 of the Provincial
Government Act (No. 83) ; and (b) the certificate for payment had not been
accomplished by the Director of Public Works or the district engineer as
provided by section 6, of Act No. 1401, as amended. The demurrer was overruled.
Thereupon defendant answered, renewing as a special defense the grounds of the
demurrer, alleging defective work on the part of the plaintiff, and admitting a
total of P2,454.78, the amount certified by the Director of Public Works and the
district engineer, as due the plaintiff. The trial court gave judgment for the
plaintiff-contractor for P4,905, with legal interest from July 14, 1914, and
costs. Defendant moved for a new trial, which was denied, duly excepted, and
perfected a bill of exceptions to this court.
Appellant’s assignments of error relate to the findings of fact and two main
issues of law. We pass the facts for the moment, to discuss the legal
questions.
The first contention of appellant is that the Province of Tayabas is not
obligated to pay the contractor anything because the contract was not approved
by the Governor-General. This position is absolutely untenable. The law in force
when the contract was entered into and when the action was tried, section 2, Act
No. 83, as amended by Act No. 1600, made the approval of the Governor-General a
prerequisite only to the purchase and conveyance of real estate by a province.
The grammatical construction of the English text, which is controlling, makes
this perfectly clear. Moreover, the law now in force (Administrative Code of
1917, section 2068) has removed any possibility of doubt and has at the same
time revealed legislative intention, by placing the requirement for the
Governor-General’s approval of transfers of real estate by provinces in a
section separate and distinct from the section of the Code giving the corporate
powers of provinces.
The remaining legal issud merits more extended consideration. Appellant’s
contention is that the certificate by the district engineer and the Director of
Public Works must be obtained before suit can be brought on a contract; that the
findings of these officials are conclusive; and that the complaint must contain
an averment to this effect. Appellee’s reply is that neither the law nor the
contract requires the submission to arbitration of disputes between the
Government and the contractor, and that a mere administrative procedure incident
to payment has been established.
Act No. 1401, as amended by Act No. 1752, was in force when this action was
instituted. The same provisions are now found in slightly altered phraseology in
sections 1917-1923 of the Administrative Code of 1917. The law gives a district
engineer supervision over all contracts connected with public works, which
exceed the estimated cost of 1*500. Section 6 of Act No. 1401, as amended by
section 3 of Act No. 1752, reads:
“No payments, partial or final, shall be made on any public works without a
certificate on the vouchers therefor to the effect that the work for which
payment is contemplated has been accomplished, inspected, and accepted. Such
certificate for work under the supervision of the district engineer shall be
signed by him or his duly authorized representative. For work not under his
supervision such certificate shall be signed by the provincial treasurer.”
Section 1922 of the Administrative Code of 1917, reads:
“No payment, partial or final, shall be made on any public work of
construction or repair without a certificate on the voucher therefor to the
effect that the work for which payment is contemplated has been accomplished in
accordance with the terms of the contract and has been duly inspected and
accepted. Such certificate shall be signed by a duly authorized representative
of the Director of Public Works having full knowledge of the facts in the
case.”
Contractors are of Course bound to take notice of ‘the provisions of the law
relating to contracts. Statutory requirements cannot be departed from for the
accommodation of either party to a contract. As a matter of fact, in the present
instance, this obligation is intensified in so far as the contractor is
concerned for the instructions to bidders contains this clause: “The contractor
shall comply with all existing or future laws, the municipal or provincial
building ordinances and regulations in so far as the same are binding upon or
affect the parties hereto, the work, or those engaged thereon.” (No. 23).
The instructions to bidders, a part of the contract, under the heading of
“Payments,” also contains the following:
“51. Payments will be made monthly, based upon the estimates of work
satisfactorily completed and accepted by the Director during the preceding
month. Upon such estimates the Province of Tayabas, P. I., shall pay to the
contractor a sum equal to ninety (90) per cent thereof up to and until such time
as the total work shall have been completed or the contract canceled, as herein
provided.
“52. The acceptance of the work from time to time for the purpose of making
partial payments, shall not be considered as a final acceptance of the work in
question.
“53. Whenever this contract, in the opinion of the Director, shall be
completely performed on the part of the contractor, the Director shall proceed
promptly to measure the work and shall make out and certify the final estimates
and acceptance for the same. The province shall then, excepting for cause herein
specified, pay to the contractor promptly after the execution of said
certificate the remainder which shall be found due, excepting therefrom such sum
or sums as may be lawfully retained under any of the provisions of this
contract: Provided, That nothing herein contained shall be construed to
waive the right of the Director, hereby reserved, to reject the whole or any
portion of the aforesaid work should the same be found to have been constructed
in violation of any of the conditions or covenants of this contract.”
Both the law and the contract provide in mandatory language for a certificate
of acceptance by the Director of Public Works or his representative before any
payment small be made on any public work for the Government.
Contracts of this character, giving into the hands of a third person or of
the purchaser the power of acceptance or nonacceptance, are not unusual. Courts
have frequently upheld them. The law regards the parties as competent to
contract in this manner. Municipal and provincial contracts, being on the same
footing as those of natural persons, may not be breached with impunity. That
mutuality exists is undoubted. The party who deliberately enters into such an
agreement, whether wisely or unwisely, must abide by it. The public corporation,
in the absence of a showing of fraud or concealment, is estopped by the approval
of its officer who is authorized to accept the work, from contesting the
contractor’s right to the contract price. (City of Omaha vs. Hammond
[1876], 94 U. S., 98; City Street Improvement Co. vs. City of
Marysville, [1909], 155 Cal., 419.) Likewise, the contractor must not only
deliver a product with which the party of the second part ought to be satisfied,
but with which he must be satisfied, or he is not bound to accept it. The rule
is well settled that in the absence of fraud or of such gross mistake as would
necessarily imply bad faith, contractors with public corporations are concluded
by the decisions of engineers or like officers where the contract contains such
a stipulation. The public corporation can rely on the provision in a contract
that performance by the other party shall be approved by or satisfactory to it,
or a particular officer, board or committee. (Second Nat Bank vs.
Pan-American Bridge Co. [1910], 183 Fed., 391, reviewing Federal decisions;
Silsby Manufg Co. vs. Town of Chico [1885], 24 Fed., 893; 23 L. R. A.
[1910], 322, Notes.)
A leading example is the case of Sweeney vs. United States ([1883],
109 U. S., 618), in which a contractor sought to recover from the United States
the price of a wall built by him around the National Cemetery. The contract
provided that the wall shall be received and become the property of the United
States after the officer or civil engineer, to be designated by the Government
to inspect the work, should certify that it was in all respects such as the
contractor agreed to construct. The officer designated for that purpose refused
to so certify on the ground that neither the material nor the workmanship was
such as the contract required. As the officer exercised an honest judgment in
making his inspection and as there was on his part neither fraud nor such grave
mistake as implied bad faith, it was adjudged that the contractor had no cause
of action on the contract against the United States.
The old common law rule required a strict or literal performance of
contracts. The modern rule sanctions a substantial performance of contractual
relations. The law now looks to the spirit of the contract and not to its
letter. Even though a plaintiff is not entirely free from fault or omission, the
courts will not turn him away if he has in good faith made substantial
performance. Of course the terms of the contract may be such that the contractor
has agreed that another shall have the absolute and unreviewable right to reject
the article or work if not satisfied with it; in such case the contractor shall
abide by his word. But when the terms, or the nature of the contract, or the
circumstances are such as to make it doubtful, whether the contractor has made
any such unwise agreement, the courts will ordinarily construe the contract as
an “agreement to do the thing in such way as reasonably ought to satisfy the
defendant.” (Parlin & Orendorff Co. vs. City of Greenville [1904],
127 Fed., 55; Swain vs. Seamens [1870], 9 Wall., 254.) Thus, it has been held
that the provision of a contract to perform work for the city requiring the
contractor to obtain the certificate of the city engineer that the work has been
done in accordance with the contract and the approval of such work by certain
boards or committees, before he is entitled to payment therefor, does not
deprive him of the right to recover for the work, if it has been done in
substantial conformity to the contract, because the city’s officers arbitrarily
or unreasonably refuse the certificate and approval called for. (City of
Elizabeth vs. Fitzgerald [1902], 114 Fed., 547.)
Substantial performance and the unfounded refusal of the certificate of
approval can be proved in various ways. Thus, acceptance and occupancy of the
building by the owner amounts to an acknowledgement that the work has been
performed substantially as required by the contract. (Campbell and Go-Tauco
vs. Behn, Meyer & Co. [1904], 3 Phil., 590, affirmed on appeal to
the United States Supreme Courts [1905], 200 U. S., 611.) Other circumstances,
as partial payment, also show acquiescence on the part of the purchaser.
Appellee speaks of the provisions of the law and the portions of the contract
in questions as possibly constituting an arbitration agreement. We deem these
provisions to be more correctly labeled a condition precedent .to the
contractor’s right to obtain payment; the condition is for the satisfaction of
the Government. Nevertheless, considered as a species of arbitration, it was a
convenient and proper method, duly agreed upon between the parties, to determine
questions that would necessarily arise in the performance of the contract, about
which men might honestly differ. It would be highly improper, for courts out of
untoward jealousy to annul laws or agreements which seek to oust the courts of
their jurisdiction. The New York theory of refusal to uphold such agreements,
because of the opinion that they violate the spirit of the laws creating the
courts, is hardly agreed to by more progressive jurisdictions. (See U. S.
Asphalt Refining Co. vs. Trinidad Lake Petroleum Co. [1915], 222 Fed.,
1006.) Unless the agreement is such as absolutely to close the doors of the
courts against the parties, which agreement would be void (Wahl and Wahl
vs. Donaldson, Sims & Co. [1903], 2 Phil., 301), courts will look
with favor upon such amicable arrangements and will only with great reluctance
interfere to anticipate or nullify the action of the arbitrator. For instance, a
policy of fire insurance, contained a clause providing that in the event of a
loss under the policy, unless the company shall deny all liability, as a
condition precedent to the bringing of any suit by the insured upon the policy,
the latter should first submit the question of liability and indemnity to
arbitration. Such a condition, the Supreme Court of the Philippines held in
Chang vs. Royal Exchange Assurance Corporation of London ([1907], 8
Phil., 399), is a valid one in law, and unless it be first complied with, no
action can be brought.
What then are the remedies of the contractor? In the first place he has his
administrative remedy, which is to complete the work substantially according to
the contract and ask for the approval of the proper official. If such officer
refuse or culpably neglect to perform a ministerial duty, such as making out the
warrant, it is possible that mandamus will lie to coerce the officer. A
stipulation requiring the approval of some one as a condition to a recovery by
the contractor would not bar the party of his remedies by action at law. The
right to redress in the courts where substantial compliance with the terms of a
contract are set forth, and where the proof discloses the withholding of the
certificate by an officer for insufficient reasons, should not be taken away by
inference or anything short of a distinct agreement to waive it. (Aetna
Indemnity Co. vs. Waters [1909], 110 Md., 673.) As a condition
precedent to action by the courts, fraud or bad faith on the part of the
responsible Government official, or arbitrary or unreasonable refusal of the
certificate or approval must be alleged and proved.
To concentrate our facts and legal principles—we find the contractor
supported by one expert insisting that the work and the materials actually
conform to the specifications; and we have this as resolutely denied by
competent Government engineers. We find substantial performance of the contract
not proved to the satisfaction of the Government’s technical adviser, but proved
to the satisfaction of the trial court. Ordinarily, we would not review the
facts unless the findings of the trial court are plainly and manifestly contrary
to the proof. But here it was incumbent on the trial court to take about the
same view of the findings of the Government’s engineers as the appellate court
would take of the findings of the trial court, or that any court would take of
the findings of customs boards, assessors, and the like. In order to set aside
the action of the Director of Public Works or his authorized representative,
fraud or bad faith on the part of these engineers must be established. Has this
been proved? The judge in the course of his decision incidentally remarked: “It
may as well be said here that there appears to have been a great deal of
ill-feeling between plaintiff and the engineer in charge of this construction.”
Is this observation in connection with the testimony of the plaintiff and of one
engineer sufficient to demonstrate fraud or bad faith? We think not. In other
Words we believe that the contractor cannot maintain an action for the
stipulated price when the engineer has in good faith, in pursuance of the
contract, withheld his certificate. The decision of the responsible engineer
cannot be subjected to the revisory power of the courts without doing violence
to the terms of the contract and the law.
The Province of Tayabas, having accepted bridge No. 53.3, should of course
pay the balance due, or P2,840. It should not be permitted to deduct the cost of
the test of the bridge, P900.12, for this is a legal question for resolution by
the courts, and the contract contains no such stipulation. (See Ripley
vs. U. S. [1912], 223 U. S., 695.) But the findings of the Government
engineers on all the other points covered by causes of action 2, 3, 4, 5, and 6
are deemed to be conclusive, fraud or bad faith not having been proved. Thus, we
have P2,840, plus P269.10, plus P214.80, plus P6, plus P25, or P3,354.90 due
plaintiff.
One point made by appellant is that the demurrer to the complaint was
improperly overruled. An elementary principle of pleading heretofore approved by
this court in Government of Philippine Islands vs. Inchausti & Co.
([1913], 24 Phil., 315) is brought to our notice, namely; “If the plaintiff’s
right of action depends upon a condition precedent he must allege and prove the
fulfilment of the condition or a legal excuse for its nonfulfilment. And if he
omits such allegation, his declaration, complaint, or petition, will be bad on
demurrer.” Undoubtedly, the complaint should have alleged either the performance
of the condition precedent, approval by the Director of Public Works or the
District Engineer, or a good and sufficient excuse for not obtaining it. It is
possible that if sitting in first instance, we would so hold with defendant, but
on appeal such a backward sweep would avail nothing but delay. Moreover, the
complaint contains the general averment that the plaintiff fully and faithfully
complied with all the terms and conditions of the said contract, while some
months subsequent to the filing of the complaint but previous to the trial, the
defendant accepted the bridge. A failure to allege a condition precedent or a
legal reason for dispensing with it may be cured by the issues tendered by the
answer and the proof. (Donegan vs. Houston [1907], 5 Cal. App.,
626.)
To summarize, we are of opinion and so hold that the law makes the approval
of the Governor-General a prerequisite only to the purchase or conveyance of
real property by a province: that the provisions of the law and the form of the
contract, usually followed in this jurisdiction, providing for the certificate
of approval by the Director of Public Works or his representative, are in the
nature of a condition precedent, which must be alleged and proved, and that this
certificate is conclusive in the absence of a showing of fraud or bad faith.
Judgment shall be modified so that the plaintiff shall recover from the
defendant P3,354.90 with Jegal interest thereon from July 14, 1914, until paid,
without special finding as to costs in either instance. So ordered.
Torres, Johnson, and Fisher, JJ., concur.
Carson and Street, JJ., concur in the result.