G.R. No. 83138. October 17, 1989
AMALIO L. SARMIENTO, DOING BUSINESS UNDER THE NAME OF A.L. SARMIENTO CONSTRUCTION, PETITIONER, VS. HONORABLE COURT OF APPEALS AND HERCON, INC., RESPONDENTS.
PARAS, J.:
These are two petitions for review on certiorari seeking
to set aside portions of the decision of the Court of Appeals in CA-G.R. CV
No. 12060 which modified the decision of the Regional Trial Court of Makati, Branch CL in Civil Case No. 1476 for a Sum of Money
and Damages: (1) in G.R. No. 83138 filed by Amalio L. Sarmiento, insofar as
it awarded price escalation payment to Hercon, Inc.
and insofar as it disallowed payment of moral and exemplary damages and
attorney’s fees to Sarmiento; and (2) in G.R. No.
85220 filed by Hercon, Inc., insofar as it awarded
actual damages to Sarmiento.
These cases arising from the same suit filed in the Regional
Trial Court of Makati were consolidated by this Court
in the Resolution of April 5, 1989
(G.R. No. 85220 p. 102, Rollo).
The undisputed facts of the case are as follows:
On February 13, 1980,
Mass Integrated Group entered into a contract with the Ministry of Public Works
and Highways (MPWH, for brevity) for the construction of the Mangahan Floodway Project (Phase B). As representative of Mass Integrated Group, Sarmiento engaged the services of several subcontractors, one
of which was Hercon, Inc., to construct the said
project.
Sometime in December, 1980, Sarmiento
agreed with Leonard Earl Pitcock, the president of Hercon, Inc. that the latter “will participate in 70% of
all collections (of Sarmiento) from MPWH including
escalation on earthworks and as to dredging works therein, it shall receive as
compensation P5.00 per cubic meter of dredge
excavation plus 40% of any price escalation payments made by MPWH.” (Exh. “A”)
Hercon, Inc., together with the other
subcontractors, proceeded to work on the project, submitting their respective
periodic billings and work accomplishment reports to the MPWH, which in turn,
made payments to Sarmiento on the basis of the
same. (Decision, Court
of Appeals, p. 3).
Conflict arose when on September
19, 1982, Hercon, Inc. stopped working on the project. It claimed that Sarmiento
failed to pay its progress billings and its share in the price escalation costs
paid by the MPWH.
On January 10, 1983, Hercon, Inc. filed
a complaint against Sarmiento, praying for “the
sum of P3,846,075.86 representing money collected by
defendant A.L. Sarmiento from the MPWH between
February 5, 1981 to May 22, 1981 for the balance of plaintiff’s dredging
accomplishments and contract price escalation on its dredging works and
earthworks’ as well as the sum of P2,301,027.83 representing contract price
adjustment on plaintiff’s dredging works from May 23, 1981 to June 22,
1982.” (Decision, Court of Appeals, p. 5).
In his Answer, Sarmiento claimed: that Hercon, Inc.
breached their contract by abandoning the project; that he had paid all of the
billings of Hercon, Inc.; that Hercon,
Inc. is not entitled to the
entire escalation amount paid by MPWH but merely participates proportionately
with the other subcontractors; and that the latter refuses to have a conference
with Sarmiento for a joint survey of their
accounts. Sarmiento
set up a counterclaim for actual, moral and exemplary damages as well as
attorney’s fees as a consequence of the abandonment of the project by Hercon, Inc. and the malicious filing of its baseless
suit. (Decision,
Regional Trial Court, p. 4).
After trial, the trial court rendered a decision in favor of Sarmiento, the dispositive
portion of which reads:
“WHEREFORE, judgment is hereby rendered:
1.- ordering plaintiff to pay or reimburse the
defendant Amalio L. Sarmiento
the amount of P7,370,450.31 representing the cost of the defective works of
plaintiff as evidenced by Exhibit ’13’
which was remedied by defendant at his expense together with the operational
costs incurred by said defendant as evidenced by Exhibits ’10’ to ’10-K’ and
’11’;
2.- ordering plaintiff to pay defendant Amalio L. Sarmiento the amount of
P500,000.00 for moral damages and the sum of P200,000.00 as exemplary damages;
3.- directing the plaintiff to pay defendant Amalio L. Sarmiento attorney’s
fees in the amount of P300,000.00;
4.- ordering the plaintiff to pay the cost of this
suit; and
5.- ordering the dismissal of other claims and
counterclaims which the parties may have against each other in this case.
“SO ORDERED.” (P. 508, RTC Rollo)
(Decision, Regional Trial Court, p. 13)
Hercon, Inc. appealed from the
aforesaid decision. The factual findings
of the trial court were adopted by the Court of Appeals, quoting portions
thereof in its decision, thus –
“At the outset, it must be stated that, as evidenced by
plaintiff’s periodic billings (Exhs. D to P) and
defendant’s money advances and disbursements (Exhs.
4-D to 4-M), plaintiff does not disagree to the following findings and conclusions of the lower court:
“Plaintiff’s Exhibit ‘Q’ which is its own summary of its
periodic billings (Exhs. ‘D’ to ‘P’) on its work
accomplishment in the Mangahan Floodway Project,
plaintiff himself stated that most of his work accomplishments evidenced by
Exhibits ‘D’ to ‘P’ had been paid by Sarmiento
‘excluding the escalation price; there is, however, no clear or direct evidence
to show just how plaintiff is entitled to
escalation price; neither is there evidence on how this claim could be computed and segregated from the various
collections of defendant from the MPWH although there appears on Exhibit ‘Q’ the figures ‘P6,147,103.70’ marked as Exhibit ‘Q-1’, there is no
showing as to how plaintiff arrived at
this figure as allegedly representing ‘escalation money due Hercon
from May 22, 1981 to June 22,
1982’; this computation, Exhibit ‘Q-1’, is self-serving and without any basis; assuming, plaintiff is
entitled to escalation money from defendant, its evidence on this point is so
hazy, self-serving and inconclusive; while it appears that defendant had been
able to collect escalation price and the cost of work accomplishments (Exh. ‘JJ’) from the MPWH, there is absolutely no evidence
adduced which part or portion of these amounts collected by defendant pertains
to the plaintiff; x x x x x x
was incumbent upon plaintiff to specify and particularize the amount it is
entitled to from these amounts collected by defendant from the MPWH considering
these sums represent work accomplishment and for escalation prices for the
entire Mangahan Floodway (Phase B) Project, over which several subcontractors,
plaintiff being only one
of them, that participates/participated
(70%) in the said construction
project x x x
“It has not been seriously denied or rebutted by plaintiff
that the defendant had disbursed or given money to plaintiff as payments or
advances for the works
subcontracted to be accomplished by the latter; x x x hence, the need of a final reconciliation between Sarmiento of the partial payments or advances he made in
relation to the accomplishments of any particular subcontractor after the MPWH shall have finally approved the completion
of the project in accordance with the plans and specifications xxx it is
unfortunate that plaintiff has refused
a conference with the defendant (Exh.
‘6’) for the purpose of reconciliation or payments and accomplishments
of the former; according to survey, (Exh. ‘7’) of plaintiff’s
work on the project, several defects were found thereon (Exh.
‘8’) which constrained the defendant to remedy at his expense in the amount of
P5,399,614.40 (Exh. ’12’)
and the sum of P1,970,835.91 (Exhs. ’10’ to ’10-K’ & ’11’). x x x
On defendant’s counterclaim, plaintiff maintains that it did not
abandon the project. In support of its argument, it emphasized that its dredger
remains in the jobsite. xxx
At any rate, on two (2) counts, plaintiff has impliedly admitted
stopping the dredgers from working on the job site. Plaintiff said that he stopped the dredging work for two (2) reasons: (1) the two (2) checks of defendant had
bounced; and (2) defendant has failed or refused to pay the amounts due
plaintiff. Anent the first reason, the
checks were issued long after the stoppage of work. The plaintiff stopped the dredging work on September 19, 1982, while the checks were both dated December, 1982.
Anent the second reason, as earlier presented, documentary evidence
proves payment by defendant of plaintiff’s work on the floodway. The last periodic billing of plaintiff, Exhibit P, is dated September
20, 1982 while
plaintiff stopped the dredging work on September 19, 1982. x x x (Decision, Court of
Appeals, pp. 5-8)
The Court of Appeals, however, radically modified the dispositive
portion of the decision, as follows:
On the prayers for recovery of damages and attorney’s fees, We find that both parties have violated their contract on
the Mangahan floodway project.
The appealed judgment awarded defendant the sums of P7,370,450.31 as actual damages, P500,000.00 as moral damages,
P200,000.00 as exemplary damages and the sum of P300,000.00 as attorney’s
fees. We uphold the actual damages, but
disallow the moral and exemplary damages and attorney’s fees in the total sum
of P1,000,000.00, thereby leaving a balance of P7,370,450.31 due defendant by way
of actual damages occasioned by the damages he had suffered due to the
abandonment by plaintiff of its dredging job and the defects and deficiencies
in the works of plaintiff.
On the price escalation due plaintiff, We find that defendant is
indebted in the total sum of P6,147,103.70.
WHEREFORE, the decision a quo is modified; as We hold
that defendant is liable to plaintiff for price escalation in the amount of P6,147,103.70; while plaintiff is liable to defendant for
actual damages in the amount of P7,370,450.31; hence offsetting both
accountabilities from each other, the only amount due defendant from plaintiff
is the sum of P1,223,346.61, without interest.
No special pronouncement as to costs.
SO ORDERED.
(Decision, Court of
Appeals, p. 11)
Unsatisfied, both parties filed their respective petitions for
review with this Court.
From the petitions, submitted for resolution are the following
issues:
WHETHER OR NOT HERCON,
INC. BREACHED ITS CONTRACT WITH SARMIENTO WITH RESPECT TO THE MANGAHAN FLOODWAY
PROJECT (PHASE B);
WHETHER OR NOT SARMIENTO
IS ENTITLED TO THE DAMAGES AWARDED BY THE TRIAL COURT;
WHETHER OR NOT HERCON,
INC. IS ENTITLED TO THE PAYMENT
OF PRICE ESCALATION COSTS IN THE AMOUNT
OF P6,147,103.70.
We
find merit in the
petition of Sarmiento.
The Court of Appeals committed reversible error in eliminating
the damages awarded by the trial court
to Sarmiento and in holding the latter liable for
price escalation costs to Hercon, Inc. despite its own finding that the latter
abandoned the project and that there were defects and deficiencies in its works in the project.
The contractual breach of Hercon, Inc.
was tainted with bad faith. Hercon, Inc. tried to justify its work stoppage due to the
alleged failure of Sarmiento to pay his obligations
and the latter’s issuance of two bouncing checks.
As found by the trial court and the Court of Appeals, however,
the documentary evidence on record proves that Sarmiento
was up to date in paying all of Hercon’s
billings. The checks adverted to were
postdated checks for December 1982, or long
after the stoppage of work on September, 1982.
Said checks were issued in advance to induce Hercon,
Inc. to resume work on the project but when the latter refused, Sarmiento ordered the bank to stop payment (TSN, Feb. 17,
1986, pp. 41-42). Records also show that
Hercon, Inc. ignored numerous conferences requested
by Sarmiento for a reconciliation of accounts. The same could have resolved the issue on payment with which Hercon, Inc. tried to justify its refusal to continue the
project.
Clearly, there is basis not only for awarding actual damages but
moral and exemplary damages as well as attorney’s fees to Sarmiento
whose contract for the entire project with the MPWH was abruptly terminated due
to the malicious and unjustified abandonment by Hercon,
Inc. of its undertaking in the project.
The amounts awarded by the trial court for moral and exemplary
damages and attorney’s fees to Sarmiento are
reasonable, considering his reputation as a contractor and the painful ordeal
he has gone through.
At the trial, he testified:
“Atty. Sunga
“Q – When you received the complaint in this case, were you affected by
this case?
A – Yes,
sir.
Q – What
is the effect on you?
A – I
was affected tremendously, projects
with the Ministry
of Public Works and Highways were not done.
We always complete our projects ahead of time, this time, because of
this case, our reputation was clearly affected
and even our standing with the banks
has been affected very much and
also with my fellow contractors, I feel
that we were affected so much to
the point that there were some nights
when I lost sleep.
Q – Was
this Mangahan B project completed by Mass Integrated
Group?
A – No,
sir, as a matter of fact, because of this inability
of Hercon to complete or
to resume the work, we were constrained
or we were forced to request for the termination of the project and
this request for termination of the project
was approved by the Ministry of Public Works and Highways.
Q – Was
this project delayed as a consequence
of the abandonment of the work?
A – Yes,
very much.“ (tsn., Sarmiento, February
17, 1986, pp. 51-52)
Hercon, Inc.
failed to introduce any evidence to controvert, much less rebut the same.
The Court of Appeals failed to state any satisfactory reason why
it awarded Hercon, Inc. price escalation costs. It simply stated that according to Exh. Q and the testimony of the plaintiff, Hercon, Inc. is entitled to price escalation costs in the
total sum of P6,147,103.70. (Decision, Court of Appeals,
p. 11).
A mere summary of claims does not suffice. It is precisely the basis of these claims
that is being questioned. Hercon, Inc. failed to introduce any evidence that will
enable the court to determine its claims.
Such factual finding by the trial court was adopted by the Court of Appeals
in its decision. There is, therefore, no
basis for a different conclusion.
It is fundamental that judgments must conform to both the
pleadings and the proof and must be in accordance with the theory of the action
upon which the pleadings were framed and the case was tried. (Lazo vs. Republic
Surety & Insurance Co., Inc., 31 SCRA 329)
Finally, well settled is the rule that the factual findings of
the trial court are entitled to
great weight and respect on appeal and We find no
cogent reasons to disturb the same.
WHEREFORE, the decision of the trial court is hereby
reinstated as follows: (1) ordering
HERCON Inc. to pay or reimburse Amalio L. Sarmiento the amount of P7,370,450.31 representing the cost
of the defective works of the former as evidenced by Exhibit ’13’ which was
remedied by the latter at his expense together with the operational costs
incurred by said Sarmiento as evidenced by Exhibits
’10’ to ’10-K’ and ’11’; (2) ordering HERCON Inc. to pay Amalio
L. Sarmiento the amount of P500,000.00 for moral
damages and the sum of P200,000.00 as exemplary damages; (3) directing HERCON
Inc. to pay Amalio L. Sarmiento attorney’s fees in the
amount of P300,000.00; (4) ordering HERCON Inc. to pay the cost of this suit;
and (5) ordering the dismissal
of other claims and counterclaims which the parties may have against each other
in this case. The decision of the Court
of Appeals is hereby SET ASIDE.
SO ORDERED.
Melencio-Herrera, (Chairman),
Padilla, Sarmiento, and
Regalado, JJ., concur.