Mecaydor versus Saekyung Realty

The Case

This is a labor case about who is the real employer. A group of construction workers — foremen, masons, carpenters, steel men, painters, helpers, and laborers — sued Saekyung Realty Corporation and its president for illegal dismissal and for unpaid salaries, overtime pay, holiday pay, and thirteenth month pay. Saekyung insisted that it never hired them; it said they were the employees of MPY Construction, an independent contractor to which it had farmed out the construction work. The workers answered that MPY was a mere labor-only contractor, a shell that supplied bodies while Saekyung kept control. The case matters because it fixes the burden of proof in contracting arrangements and reminds us that a contractor's failure to register with the Department of Labor and Employment raises a legal presumption of labor-only contracting.

Procedural History

The workers filed their complaints before the Labor Arbiter. The Labor Arbiter dismissed the consolidated cases, holding that no employer-employee relationship existed between the workers and Saekyung, and that MPY was their employer under the four-fold test. The workers appealed to the National Labor Relations Commission. The Commission reversed the Labor Arbiter and declared Saekyung the actual employer, ordering reinstatement and the payment of backwages, wage differentials, service incentive leave pay, and attorney's fees. On Saekyung's motion for reconsideration, however, the Commission vacated its own decision and dismissed the case, this time giving weight to additional documents Saekyung submitted. The workers' motion for reconsideration was denied. The workers then filed a petition for certiorari with the Court of Appeals, which dismissed the petition and affirmed the Commission. The Court of Appeals denied reconsideration, so the workers came to the Supreme Court by petition for review.

Facts

Saekyung Realty Corporation, incorporated in August 2010, is engaged in real estate development, particularly condominium projects in Cebu. For its first three buildings it entered into a Contractor Agreement with MPY Construction, covering specific work, a number of laborers, and a rate per laborer. MPY hired the workers on different dates and detailed them to Saekyung as project employees. The workers claimed that Saekyung's president directly supervised their work, and that a Saekyung employee monitored their time-ins and time-outs and prepared their weekly payroll reports.

On September 28, 2013, a foreman was told that his group's employment would end at five o'clock that afternoon. Saekyung then hired new workers. In January 2014, MPY informed Saekyung that the workers had abandoned their jobs; Saekyung did nothing, thinking the matter was MPY's concern, and was surprised when the complaints were filed.

Before the tribunals, the workers stressed that MPY was not registered as a legitimate labor contractor with the Department of Labor and Employment, and was not accredited by the Philippine Contractors Accreditation Board. Saekyung, for its part, submitted a Contractor Agreement, business registrations, billings, and later, on reconsideration, an audited financial statement and a letter from the Land Transportation Office listing vehicles registered to MPY and its proprietor.

Issues

  • Whether or not MPY Construction is a labor-only contractor, such that the workers are the regular employees of Saekyung Realty Corporation.
  • Whether or not the workers were illegally dismissed and entitled to reinstatement, backwages, and monetary awards.

Applicable Provisions

Article 106 of the Labor Code provides:

There is labor-only contracting where the person supplying workers to an employer does not have substantial capital or investment in the form of tools, equipment, machineries, work premises, among others, and the workers recruited and placed by such person are performing activities which are directly related to the principal business of such employer. In such cases, the person or intermediary shall be considered merely as an agent of the employer who shall be responsible to the workers in the same manner and extent as if the latter were directly employed by him.

This is the core test: absent substantial capital and investment, and with work directly related to the principal's business, the intermediary is a mere agent and the principal is the true employer.

Section 11 of Department Order Number 18, Series of 2002, provides:

Failure to register shall give rise to the presumption that the contractor is engaged in labor-only contracting.

This presumption is decisive here, because Saekyung never presented MPY's certificate of registration.

Ruling

The Court granted the petition. It first addressed the procedural objection that factual findings are not reviewable, and held that the Court of Appeals overlooked relevant facts that would justify a different conclusion, which is a recognized exception. It then restated the burden of proof: the general presumption is that a contractor is engaged in labor-only contracting unless the contractor proves otherwise, and that burden shifts to the principal when the principal claims the contractor's legitimacy. The Labor Arbiter erred in placing that burden on the workers.

On the first issue, the Court held that MPY is a labor-only contractor. Saekyung failed to present MPY's certificate of registration, so the legal presumption of labor-only contracting arose and stood unrebutted. The Court also found no reliable proof of capitalization: the audited financial statement was prepared by a person who turned out to be non-existent upon verification with the Professional Regulation Commission, and the vehicles listed in the Land Transportation Office letter were not shown to have been actually and directly used in the contracted work. The tools and materials were supplied by Saekyung. The Court added that the parties cannot dictate the character of their business by a unilateral declaration in a contract, so reliance on the Contractor Agreement was misplaced.

On the second issue, the Court held that as regular employees of Saekyung, the workers were entitled to both substantive and procedural due process, and none was observed. They were therefore illegally dismissed and entitled to reinstatement without loss of seniority rights, full backwages, and other benefits, plus attorney's fees equivalent to ten percent of the total monetary award, with legal interest at six percent per annum from finality until full payment.

Doctrine

First, labor-only contracting is presumed; the contractor must prove substantial capital or investment actually and directly used in the contracted work, and the principal bears that burden when it asserts the contractor's legitimacy. Second, failure to register with the Department of Labor and Employment raises the presumption of labor-only contracting, and registration, while not conclusive, prevents that presumption from arising. Third, the totality of facts, not the labels in a contract, determines the true relationship. Fourth, where labor-only contracting exists, the workers are regular employees of the principal, who must observe due process in any dismissal.

Disposition

The petition was granted; the Court of Appeals decision and resolution were reversed and set aside, the Commission's May 2016 decision was reinstated, and Saekyung was ordered to reinstate the workers, except Apollo Tura, and to pay them backwages, wage differentials, service incentive leave pay, and attorney's fees totaling twelve million seven hundred seventy-seven thousand ninety-five pesos and twenty centavos, with six percent legal interest from finality.

Remember This

Memorize this line: failure to register with the Department of Labor and Employment raises the presumption of labor-only contracting, and the principal who claims otherwise carries the burden. Examiners use this case to test the burden of proof in job contracting and the effect of a missing certificate of registration.