EL BANCO ESPAÑOL FILIPINO, PLAINTIFF AND APPELLEE, VS. DONALDSON SIM & CO. ET AL., DEFENDANTS AND APPELLANTS.
Listen, read along, or open presentation mode.
El Banco Español Filipino versus Donaldson Sim and Company
The Case
This is a civil action for the collection of a debt. The Banco Español Filipino lent a large sum to the mercantile firm of Donaldson Sim and Company, and when the loan fell due unpaid, the bank sued not only the principal debtor but also the parties who had bound themselves for its payment: James H. Threw, who pledged three vessels as security, and the firm of J. M. Tuason and Company, which constituted itself joint surety. The case matters because it is a compact lesson on the law of suretyship: on when a surety is released, on whether mere delay by the creditor amounts to an extension of the obligation, and on the limits of a surety's right to set up defenses belonging to another party. It is an early decision of the Supreme Court applying the Civil Code and the Code of Civil Procedure.
Procedural History
The bank filed its action in the Court of First Instance of Manila. Judgment by default was pronounced against the principal firm, Donaldson Sim and Company, and a separate judgment by default was rendered against James H. Threw, ordering the sale at public auction of the three pledged vessels and the application of the proceeds to the debt. The vessels were thereafter sold at public auction, and the net proceeds were paid to the bank. The remaining question of law, whether the joint surety J. M. Tuason and Company was liable for the unpaid balance, was submitted by the parties to the trial court. That court held the surety responsible and sentenced it to pay the unpaid balance of the debt. The surety appealed, assigning errors of law, and the case came to the Supreme Court by bill of exceptions.
Facts
On the ninth of May, 1901, the Banco Español Filipino lent the firm of Donaldson Sim and Company 110,000 pesos for a term of six months, with interest at eight per cent per annum, payable at the end of each quarter. The contract of loan was embodied in a public instrument. In that same instrument, James H. Threw bound himself jointly with the principal debtor and pledged three ships that he owned, the Chow Phya, the Hercules, and the Hebe, to guarantee payment of the principal, the proper interest, and whatever other obligations the firm might contract. By a further clause, the firm of J. M. Tuason and Company, represented by a partner, constituted itself joint surety of Donaldson Sim and Company for the sum which that firm should be found to owe after partial payment of the loan from the proceeds of the sale of the steamers, or for the total of the obligation if the security of the steamers should disappear before partial settlement.
The obligation fell due on the ninth of November, 1901, but the bank did not then demand payment from the principal debtor, nor did it file an action. It continued to draw the stipulated interest until March 1902. This was done without the express consent of the surety. When the bank finally sued, judgment by default was entered against the principal firm for 115,894 pesos and 41 centavos, Philippine currency, representing the principal plus stipulated interest. The sheriff returned the writ of execution unsatisfied, as there was no property of the firm that could be attached. Judgment by default was also entered against James H. Threw, ordering the sale of the three vessels.
The vessels were sold at public auction after the required advertisement and compliance with the formalities of the Code of Civil Procedure. The Hercules and the Hebe realized 1,250 pesos, and the Chow Phya, also called Aparri, realized 3,440 pesos, Philippine currency. After deduction of the sheriff's fees, these sums were paid to the bank. The parties agreed that when the launches were sold at public auction, no price was fixed, but they were adjudged to the highest bidder, and the proceeds represented the real value of the launches in the condition in which they were at the dates of the respective sales. The surety resisted liability on two grounds: that the obligation had been tacitly extended without its consent, and that the bank should have subjected itself to the prices fixed for the sale in the eighth clause of the instrument.
Issues
- Whether or not the surety, J. M. Tuason and Company, was released from its obligation because the creditor delayed in demanding payment and continued to receive interest after the debt fell due, which the surety claims was a tacit extension of the obligation granted without its consent.
- Whether or not the bank violated the contract by selling the pledged launches at public auction without fixing the prices stipulated in the eighth clause of the instrument, thereby releasing the surety.
- Whether or not the surety may set up, as a defense, an objection pertaining to the owner of the pledged vessels rather than to the principal debtor.
Applicable Provisions
Article 1851 of the Civil Code provides:
The extension granted to the debtor by the creditor, without the consent of the surety, extinguishes the security.
This is the provision on which the surety rests its claim of release, and the Court must decide whether the creditor's conduct amounted to such an extension.
Article 1847 of the Civil Code provides:
The obligation of the surety extinguishes at the same time as that of the debtor, and for the same causes as the other obligations.
The Court uses this to show that the surety's obligation follows the principal debt, and that mere delay in demanding payment is not among the causes that extinguish it.
Number 4 of article 1843 of the Civil Code provides:
In accordance with the provisions of number 4 of article 1843, the surety, even before payment, may proceed against the principal debtor when the debt has become demandable because the term in which it should have been paid has expired.
This shows that the law gives the surety a remedy against the principal debtor once the debt is demandable, so that the creditor's delay does not leave the surety defenseless.
Article 1853 of the Civil Code provides:
The surety, J. M. Tuason and Company, had the right to set up all the exceptions pertaining to the principal debtor and inherent in the debt (article 1853) but not those pertaining to the other surety.
This limits the defenses a surety may raise to those pertaining to the principal debtor and inherent in the debt, and not those belonging to another surety such as the owner of the pledged vessels.
Ruling
On the first issue, the Court held that the surety was not released. The mere fact that the creditor does not demand compliance immediately upon the obligation becoming due, and delays its action more or less, does not mean or reveal an intention to grant an extension to the debtor. Deferring the filing of the action does not change the efficacy of the contract or create liability on the part of the debtor. It is merely respite, waiting, courtesy, leniency, passivity, inaction. It does not constitute novation, because novation must be express. Nor does it engender liability on the part of the creditor, which can arise only from delay, and for that class of delay interpellation by the party who considers himself injured is necessary. The Court also held that the receipt of interest stipulated in the same contract after the obligation became due does not constitute novation; it is merely a compliance with the obligation itself. It extends the time for fulfillment or payment, but not the term of the obligation. The Court added that even if the delay were an express extension, the surety could not consider itself relieved, because the surety was a party to the contract, and the fourth clause provided:
The term of duration of this contract is six months, beginning with this date, and may be extended at the will of the creditor.
Having consented to that clause, the surety ought to have been prepared for any delay.
On the second issue, the Court held that no law or contract was violated. The eighth clause, which fixed the values of the vessels and declared that those values shall be the prices for the sale, took the place of a formality prescribed by the Code of Civil Procedure then in force, which the parties sought to avoid by using the right granted by the same article. That formality having been repealed by the present Code of Civil Procedure, the sale had to be adjusted to the present law, and it took place in the manner ordered by the judge and prescribed by law, without the sentence ordering the sale having been objected to. Besides, the creditor did not bind himself in the contract not to request a sale except under a fixed price. Even if he had so bound himself, it was not his fault that the sale was carried out differently, since it was made in accordance with existing legal procedure. The Court stressed that forms of legal procedure are of a public nature and interest and cannot be repealed, altered, or modified by private citizens by means of contracts.
On the third issue, the Court held that any objection to the manner of the sale would at all events have to be made by the owner of the launches who gave them as security. The surety, J. M. Tuason and Company, had the right to set up all the exceptions pertaining to the principal debtor and inherent in the debt, but not those pertaining to the other surety. The Court also noted that the proceeds of the sales represented the real value of the launches, so it would have been useless to fix a minimum price. Under the seventh clause, the surety responded for the sum which Donaldson Sim and Company should be found to owe after partial payment from the proceeds of the sale of the steamers, and that is the case explicitly mentioned in the contract which had occurred.
Doctrine
A surety is not released by the creditor's mere delay in demanding payment. Under article 1851, only an extension granted to the debtor without the consent of the surety extinguishes the security, and mere inaction, courtesy, or leniency is not such an extension. Novation must be express, and the receipt of interest already due is not novation but compliance with the obligation itself. The surety's obligation extinguishes at the same time and for the same causes as that of the debtor under article 1847, and the surety is protected by the preventive action under number 4 of article 1843, which allows the surety, even before payment, to proceed against the principal debtor once the debt has become demandable. Where the surety has consented in the contract to an extension at the will of the creditor, the surety cannot complain of delay. Finally, under article 1853, a surety may set up only the exceptions pertaining to the principal debtor and inherent in the debt, not those pertaining to another surety. And forms of legal procedure, being of public nature and interest, cannot be altered by private contract.
Disposition
The Supreme Court affirmed the sentence appealed from in all its parts, with costs against the appellant, and ordered the case returned to the court below for execution.
Remember This
The single line worth memorizing is that mere delay by the creditor in demanding payment is not the extension that extinguishes the surety's security under article 1851, for novation must be express. Examiners like to use this case to test the distinction between delay and extension, the effect of receiving interest after maturity, and the rule that a surety may raise only the defenses of the principal debtor and not those of another surety.