LIBRADO C. NAVARRO, PETITIONER, VS. COMMISSION ON AUDIT, DIRECTOR ROLAND A. REY, REGIONAL DIRECTOR, COMMISSION ON AUDIT, REGIONAL OFFICE NO. XIII, CARAGA REGION, BUTUAN CITY, RE…

G.R. No. 240632. August 22, 2023 August 22, 2023

← Read the full text of the decision

Listen, read along, or open presentation mode.

Navarro versus Commission on Audit

The Case

This is a petition for certiorari under Rule 64 in relation to Rule 65 of the Rules of Court, brought by Mayor Librado C. Navarro and the members of the Bids and Awards Committee and the Technical Working Group of the City Government of Bislig, Surigao del Sur, against the Commission on Audit, its Director Roland A. Rey, and its Regional Director for the Caraga Region. The petitioners ask the Supreme Court to reverse the Commission on Audit Proper, which affirmed a notice of disallowance and later increased it to the full purchase price of a hydraulic excavator bought by the city. The case matters because it fixes the narrow gate through which a disallowance may be struck down, and because it shows how the Court reads the post-qualification stage of Republic Act Number 9184, the Government Procurement Reform Act, when the audit body and the procuring entity disagree on whether a bid was responsive.

Procedural History

The city auditors issued a notice of disallowance against the petitioners. They appealed to the Commission on Audit Regional Office for the Caraga Region, which denied the appeal and affirmed the disallowance. They then filed a petition for review before the Commission on Audit Proper, which dismissed the petition as filed out of time and declared the regional decision final and executory. On motion for reconsideration, the Commission Proper gave due course to the motion and resolved the case on its merits. Because the inspection reports conflicted, the Commission Proper ordered a re-inspection by a reconstituted regional technical audit team. On the merits, the Commission Proper denied the motion and affirmed the disallowance, but modified it upward to the full contract price. The petitioners then filed separate petitions for certiorari before the Supreme Court, which were consolidated. They later asked the Court to consider a decision of the Sandiganbayan acquitting them of charges under the Anti-Graft and Corrupt Practices Act in connection with the same procurement.

Facts

In September 2011, the City Government of Bislig, with an approved budget of 15,000,000 pesos, sought to buy a brand-new crawler type hydraulic excavator to fast-track its infrastructure projects. Through its Bids and Awards Committee, it advertised an Invitation to Bid requiring, among other specifications, a bucket capacity of 1 to 1.5 cubic meters. Two bidders responded: RDAK Transport Equipment, Incorporated, offering the Komatsu Hydraulic Excavator, and JVF Commercial, offering the Kobelco Hydraulic Excavator. JVF was declared the bidder with the Lowest Calculated Bid, but after post-qualification it was post-disqualified for failing the six-cylinder engine requirement and the bucket digging force requirement. The committee then evaluated RDAK, found its bid responsive, and recommended the award. The mayor approved the recommendation, issued a Notice of Award, and executed a purchase order for 14,750,000 pesos. RDAK delivered the unit in December 2011 and was paid the same day, and the unit was inspected and declared compliant.

In February 2012, the city's General Services Office asked the state auditor to inspect the excavator. One inspection report found it conformed with the purchase order specifications. A later evaluation report by the regional technical audit team, however, concluded that the Kobelco unit was superior and that the Komatsu unit failed the bucket capacity requirement, and that both bidders should have been declared non-responsive. Relying on page six of the Komatsu Manual, which states a heaped bucket capacity of 0.80 cubic meter, the auditors disallowed 4,214,000 pesos, the price variance between the two units.

On appeal, the regional office affirmed the disallowance. The Commission Proper dismissed the petition for being filed out of time, then on reconsideration resolved the case on the merits. A reconstituted audit team re-inspected the unit and reported that it conformed with the specifications except for the bucket, which had an actual capacity of 0.80 cubic meter, though it could excavate an additional thirty percent if the material were not scraped level. The Commission Proper then denied the motion, held that the bid should have been disqualified and a failure of bidding declared, and increased the disallowance to the full contract price of 14,750,000 pesos.

Issues

  • Whether or not the Commission on Audit Proper committed grave abuse of discretion amounting to lack or excess of jurisdiction in affirming the disallowance relative to the procurement of the Komatsu Hydraulic Excavator.
  • Whether or not the Commission on Audit Proper gravely abused its discretion in ruling that RDAK should have been post-disqualified for failing to meet the required bucket capacity specification.

Applicable Provisions

Section 34 of Republic Act Number 9184, the Government Procurement Reform Act, provides:

Section 34. Objective and Process of Post-qualification. Post-qualification is the stage where the bidder with the Lowest Calculated Bid, in the case of Goods and Infrastructure Projects, or the Highest Rated Bid, in the case of Consulting Services, undergoes verification and validation whether he has passed all the requirements and conditions as specified in the Bidding Documents. If the bidder with the Lowest Calculated Bid or Highest Rated Bid passes all the criteria for post-qualification, his Bid shall be considered the Lowest Calculated Responsive Bid, in the case of Goods and Infrastructure or the Highest Rated Responsive Bid, in the case of Consulting Services. However, if a bidder fails to meet any of the requirements or conditions, he shall be post-disqualified and the Bids and Awards Committee shall conduct the post-qualification on the bidder with the second Lowest Calculated Bid or Highest Rated Bid. If the bidder with the second Lowest Calculated Bid or Highest Rated Bid is post-disqualified, the same procedure shall be repeated until the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid is finally determined. In all cases, the contract shall be awarded only to the bidder with the Lowest Calculated Responsive Bid or Highest Rated Responsive Bid.

This provision supplies the test for the case: the question is whether RDAK passed all the requirements and conditions in the bidding documents, including the bucket capacity specification.

Ruling

On the first issue, the Court acknowledged the constitutional role of the Commission on Audit as guardian of government funds and the respect ordinarily owed to its factual findings. But it held that those findings bind only to the extent they rest on substantial evidence, and that certiorari lies where the Commission acts without or in excess of jurisdiction or with grave abuse of discretion. The Court defined grave abuse of discretion in the words it had used in Fernandez versus Commission on Audit:

By grave abuse of discretion is meant such capricious and whimsical exercise of judgment as is equivalent to lack of jurisdiction. The abuse of discretion must be grave as where the power is exercised in an arbitrary or despotic manner by reason of passion or personal hostility; it must be so patent and gross as to amount to an evasion of positive duty or to a virtual refusal to perform the duty enjoined by or to act at all in contemplation of law. The burden lies on the petitioner to prove not merely reversible error, but grave abuse of discretion amounting to lack or excess of jurisdiction on the part of the public respondent issuing the impugned order.

On the second issue, the Court found a palpable misapprehension of facts. The Commission had relied on page six of the Komatsu Manual, but page seven of the same manual, under the heading for backhoe bucket, arm, and boom combination, lists bucket capacities including 1.05 cubic meters and 1.17 cubic meters, both within the required range of 1.00 to 1.50 cubic meters. The figure on page six, the Court explained, is only an estimate used to illustrate approximate operating weight, while page seven states the accurate bucket specifications. The Court also distinguished struck capacity from heaped capacity, and held that the thirty percent additional load shown in actual testing confirmed compliance. It concluded that the Technical Working Group and the Bids and Awards Committee correctly found RDAK's bid responsive, and that the Commission Proper gravely abused its discretion in upholding the disallowance.

Doctrine

First, the factual findings of the Commission on Audit are generally accorded utmost respect, but only to the extent that they are supported by substantial evidence; where they are not, or where the Commission acts capriciously, certiorari under Rule 64 lies. Second, grave abuse of discretion means capricious and whimsical exercise of judgment equivalent to lack of jurisdiction, and the burden is on the petitioner to prove it. Third, under Section 34 of Republic Act Number 9184, a bid is post-qualified by verifying whether it passed all the requirements and conditions in the bidding documents; a bidder who passes is declared to have submitted the Lowest Calculated Responsive Bid, and only such a bidder may be awarded the contract. Fourth, in determining compliance with technical specifications, the audit body must read the bid documents as a whole and apply the correct technical measure, here the heaped bucket capacity stated in the proper section of the manufacturer's manual.

Disposition

The Court granted the petitions, set aside the Commission on Audit Proper decision and resolution, and lifted the notice of disallowance against the petitioners.

Remember This

The one line to memorize: audit findings command respect only when supported by substantial evidence, and grave abuse of discretion means capricious and whimsical judgment equivalent to lack of jurisdiction. Examiners use this case to test the standard of review over the Commission on Audit and the post-qualification rules under Section 34 of the Government Procurement Reform Act.