G.R. No. 220500. February 08, 2023

CRISTINA AMPOSTA-MORTEL, PETITIONER, VS. PEOPLE OF THE PHILIPPINES, RESPONDENT.

Decisions / Signed Resolutions February 8, 2023 SECOND DIVISION LOPEZ, J., J.:


LOPEZ, J., J.:


Assailed in these consolidated Petitions for Review[1] under Rule 45 of the Revised Rules of Court are the Decision[2] and the Joint Resolution[3] rendered by the Sandiganbayan. The dispositive portion of the assailed Decision reads:

WHEREFORE, premises considered, the Court renders judgment as follows:

1. Accused Manuel Beriña, Jr., Jaime Millan, Bernardo Viray,
Theron Victor Lacson, Raphael Pocholo Zorilla, Cristina Amposta-Mortel,
Frisco Francisco San Juan, Carmelita De Leon-Chan, Daniel Dayan,
Salvador Malbarosa, Leo Padilla, Elpidio Damaso and Jesusita Legaspi are
found GUILTY BEYOND REASONABLE DOUBT of violating Sec.
3(e) of R.A. No. 3019. They are each sentenced to the indeterminate
penalty of imprisonment of Six (6) years and One (1) month, as minimum,
to Eight (8) years, as maximum, with perpetual disqualification from
holding public office. They are ordered to jointly and severally
reimburse the government the cost of the improper contract price
adjustment and the cost for the Seaside Drive Extension totaling One
Hundred Million Sixteen Thousand Seven Hundred Ninety-Four Pesos and
Seventy-Four Centavos (P100,016,794.74), with interest until fully paid, as civil liability.

2. Accused Ernest Frederick Villareal, Joemari Gerochi,
Angelito Villanueva, Martin Sanciego, Jr., Rodolfo Tuazon, Manuela Dela
Paz, Arturo Layug, Benilda Mendoza, Epifanio Pureza, Jose Capistrano,
and Ma. Cecilia Dela Rama are found NOT GUILTY, the
Prosecution being unable to prove beyond reasonable doubt that they
acted with manifest partiality, evident bad faith, or gross inexcusable
negligence and were involved in a conspiracy, as charged in the
Information.

No civil liability is adjudged against accused Villareal,
Gerochi, Villanueva, Sanciego, Jr., Tuazon, Dela Paz, Layug, Mendoza,
Pureza, Capistrano, and Dela Rama considering that no act or omission on
which any civil liability can be based exists. Their bail bonds are
deemed CANCELLED and ORDERED RELEASED. The hold-departure orders issued against them are ordered LIFTED and SET ASIDE.

3. The case against accused Carlos Doble is hereby ARCHIVED
until the Prosecution or the counsel of said accused presents a
certified true copy of his Death Certificate from the Philippine
Statistics Authority.

SO ORDERED.[4] (Emphasis in the original)

The dispositive portion of the assailed Joint Resolution reads as follows:

WHEREFORE, the Court resolves as follows:

1. Accused Beriña, Jr., et al.’s motion to be allowed to present evidence in support of their motion for reconsideration, is DENIED, for lack of merit.

2. [T]he separate motions for reconsideration of accused Beriña,
Jr., Millan, Viray, Lacson, Zorilla, De Leon-Chan, Damaso, Dayan,
Malbarosa, Padilla, San Juan, Legaspi, and Mortel are DENIED, except on the matter of accused Legaspi’s civil liability over the contract price adjustment of P42,418,493.64,
which should be deducted from the amount the latter was ordered to
reimburse the government. This reduces accused Legaspi’s total civil
liability to P57,598,301.10.

3. The prosecution’s Motion for Partial Reconsideration (On the Civil Aspect), dated February 20, 2015, is hereby PARTIALLY GRANTED.

In addition to the civil liability of P100,016,794.74,
accused Beriña, Jr., Millan, Viray, Lacson, Zorilla, Amposta-Mortel,
San Juan, De Leon-Chan, Dayan, Malbarosa, Padilla and Damaso are ordered
to jointly and severally reimburse the government the amount of P73,424,079.46, representing the overruns/underruns for Variation Order No. 1 (P67,982,609.07) and the Inland Channel Bridge under Variation Order No. 2 (P5,441,470.39). Their total civil liability is hereby increased to P173,440,874.20.

SO ORDERED.[5] (Emphasis in the original)

Facts

The factual findings of the Sandiganbayan[6] indicate that on September 24, 1998, Public Estates Authority (PEA) Deputy General Manager Manuel Beriña, Jr. (Beriña, Jr.) and PEA General Manager Carlos Doble (Doble)
submitted a Memorandum to the PEA Board regarding the construction of
the Central Boulevard Road Project. It is a highway traversing the
reclaimed area from Buendia Avenue to Pacific Avenue at Asiaworld City,
spanning 5.1234 kilometers and was to have three bridges to cross over
the drainage channels separating the islands. This project was pursuant
to Administrative Order No. 176[7] issued by former President Fidel Ramos (President Ramos) that created the Presidential Task Force Boulevard 2000 and former President Joseph Ejercito Estrada’s (President Estrada)
Memorandum dated October 16, 1998, ordering the PEA to develop and
construct the said highway. PEA estimated the cost of the construction
of the entire stretch to be at PHP 731,443,700.00, which already
included a 15% price escalation.[8]

As the project was implemented, it appeared that some stretches of the
highway were already covered by undertakings of PEA’s Joint Venture
partners. These other portions are covered by development agreements by
PEA with SM, Inc., as well as with R1 Consortium/D.M. Wenceslao, Inc.[9]

On September 28, 1998, the PEA Board of Directors (Old Board) approved, in principle, the Proposed Action Plan for the construction of the Central Boulevard Project (later renamed to President Diosdado Macapagal Boulevard or PDMB)
where PEA will borrow PHP 1 billion from various financial institutions
to finance the project.[10] The members of the PEA Board of Directors
during this time were the following:

Frisco San Juan – Chairman
Carlos Doble – General Manager
Carmelita de Leon-Chan – Member
Elpidio Damaso – Member
Daniel Dayan – Member
Salvador Malbarosa – Member
Leo Padilla – Member[11]

On April 22, 1999, San Juan updated the Office of then President Estrada, through Executive Secretary Ronaldo Zamora (Executive Secretary Zamora),
of the steps taken by PEA regarding the construction of the PDMB
project. Because of the importance of the project, San Juan requested
for authority to bid and award contract packages relative to the PDMB
through simplified public bidding. PEA was then authorized, by a
Memorandum issued by then Executive Secretary Zamora dated July 2, 1999,
to bid and award contracts for the PDMB project through simplified
public bidding. On April 22, 1999, Doble likewise issued Office Order
No. 070, series of 1999, where an Ad Hoc Committee was constituted to fast track the implementation of the Ombudsman Building and the Central Boulevard Road Project[12] or the PDMB Project. The members of the Committee were:

Manuel Beriña, Jr. – Chairman
Theron Lacson – Member
Bernardo Viray – Member
Ernesto Enriquez – Member[13]

On May 11, 1999, Beriña, Jr., as Chairman of the Ad Hoc Committee, wrote to the Project Director of the Department of Public Works and Highways (DPWH), Engr. Arturo M. Santos (Engr. Santos),
requesting for a list of contractors who have inter-agency
classification of large “B” and contractor’s license classification of
triple “AAA” with proven track records in implementing DPWH’s major
roads/bridges projects. On May 19, 1999, Engr. Santos replied and gave
the names of 10 contractors with the foregoing qualifications. These
contractors were W. Red Construction and Development Corp. (W. Red), JD Legaspi Construction (JD Legaspi), D.L. Cervantes Construction (D.L. Cervantes), Egapol Construction (Egapol), Tokwing Construction (Tokwing),
Atlantic Erector’s, Inc., Emerald Construction and Development Corp.,
D.M. Consunji Inc., Bandila Construction and Development Corp., and High
Peak Construction and Development Corp.[14]

On July 8, 1999, Beriña, Jr. sent invitations for prequalification
and to bid to W. Red, JD Legaspi, D.L. Cervantes, Egapol, and Tokwing.
This was because the PEA Ad Hoc Committee decided to divide the
10 contractors equally for Package 1 and Package 2. Prequalification
documents were received until July 19, 1999. After evaluation, all
contractors qualified for Package 1, with satisfactory performance and
compliant with the minimum equipment requirement. Beriña, Jr. then
informed the five prequalified bidders who were asked to submit their
respective bids on July 26, 1999, with the pre-bid conference set on
September 10, 1999. The bids were opened in the presence of the bidders,
Ad Hoc Committee members, and a Commission on Audit (COA) representative on September 16, 1999.[15]

The bids of the five construction companies were all considered
responsive, with the following respective bids and a summary of the
agency estimates set by PEA:

Bidders
 
Bid Amount
 
1. Egapol Construction P656,373,738.03
2. JD Legaspi Construction P584,365,885.05
3. D.L. Cervantes Construction P631,588,119.00
4. W. Red Construction and Development Corporation P652,999,429.18
5. Tokwing Construction P642,404,794.129
   
Approved Agency Estimate (AAE) P549,713,194.00
Higher Limit (120% of AAE) P659,655,832.80
Lower Limit (60% of AAE) P329,827,916.40
Allowable Government Estimate (AGE) P591,629,793.55
Lower Limit of AGE (70% of AGE) P414,140,855.48[16]

From the submissions of the contractors, it was determined that JD Legaspi was the lowest complying bidder. The Ad Hoc
Committee thereafter recommended that the project be awarded to JD
Legaspi. The Bid Evaluation was prepared by Project Management Officer
Jose Morales, Jr., and checked by Raphael Pocholo Zorilla (Zorilla), while Bernardo Viray (Viray), Atty. Ernesto Enriquez (Atty. Enriquez), Theron Victor Lacson (Lacson)
and Beriña, Jr. recommended the approval thereof. Doble approved the
same Bid Evaluation Report, which was forwarded to the PEA Board of
Directors. In turn, the Board of Directors approved the awarding of the
contract to JD Legaspi during its Board Meeting held on November 3,
1999.[17] Resolution No. 2032, series of 1999 states:

RESOLVED, that the award of contract for the construction
of the proposed Central Boulevard Road Project (Package 1) to JD
Legaspi Construction and the appropriation of the amount of Five Hundred
Eighty[­ ]Four Million Three Hundred Sixty[-]Five Thousand Eight
Hundred Eighty[-]Five and 05/100 Peso[s] (584,365,885.05), chargeable against the proceeds
of the One Billion Peso loan from Land Bank of the Philippines/All Asia
Capital, is hereby approved, subject to pertinent accounting and
auditing rules and regulations.[18] (Emphasis supplied)

Pursuant to the above action of the Board of Directors, a
Construction Agreement was drawn up and signed by Doble and Legaspi. It
was later presented to the Board of Directors, which approved the same
on December 15, 1999. The Board of Directors’ approval was for the
Construction Agreement for Package 1 of the Central Boulevard Road
Project executed between the PEA and JD Legaspi.[19]

Upon review of the Office of the President, then Executive Secretary Zamora issued a Memorandum[20] dated January 29, 2000 addressed to San Juan, which provides:

The request for approval by the PEA of its Construction
Agreement with JD Legaspi Construction for the construction of the
Central Boulevard Road Project in the amount of five hundred
eighty[-]four million three hundred sixty[-]five thousand eight hundred
eighty[-]five pesos and 05/100 (P584,365,885.05) is hereby granted
subject to the following conditions:

a.)
The PEA Accountant should sign as a witness to the Agreement
   
b.)
The following provisions must be added to the Agreement:
     
(i)
All the extra works and price adjustments should first be submitted to the President for approval.
     
(ii)
The fifteen percent (15%) advance
payment to cover the mobilization expenses of the Contractor should be
given to the latter at two staggered payments of seven and a half
percent (7.5%) each, in compliance with CI 4 of the Implementing Rules
and Regulations of P.D. 1594 and DPWH Ministry Order No. 42, Series of
1984.
   
c.)
Additional credit line in
the amount of eight million four hundred thirty[-]six thousand five
hundred eighty[-]eight pesos and 50/100 (P8,436,588.50) must be opened.
   
d.)
Final approval and actual release of the loan proceeds from the Land Bank of the Philippines/ All Asia Capital must be secured.

After the compliance with the foregoing, the PEA is directed to
issue the written Notice to Proceed. This must specifically require the
Contractor to complete the project within three hundred sixty (360) days
from receipt of said Notice.

Please submit to the Office of the President, through the PMS, a
report on the results of the transaction within thirty (30) days from
receipt by the Contractor of the Notice to Proceed, a statement of
commitment concerning the additional credit line opened with the bank
concerned, a copy of the certificate of final approval and actual
release of the loan proceeds from the Land Bank of the Philippines/All
Asia Capital and a copy of the signed Construction Agreement, duly
notarized, with accompanying annexes.[21]

Pursuant to this Memorandum, several changes were incorporated to the agreement signed beforehand by Doble and Legaspi.[22] Another Construction Agreement (Agreement) was signed on April 10, 2000.[23]
As per the Agreement, the project was for PHP 584,365,885.05 inclusive
of value added tax, fees and taxes for obtaining the necessary licenses
and clearances from various government agencies. Other notable
provisions of the Agreement were the following:

Article 4

4.5 Price Escalation: Adjustment of contract price due to
escalation shall be effected in accordance with P.D. 1594 and its IRR,
upon written agreement of the parties and subject to availability of
funds.

Article 8 Change Order and/or Additional Work

8.1 The PEA, may at any time, by written order,
make changes in the schedule and work required under this Agreement. If
any such change/s causes an increase or decrease in the work or the
time required for performing the work, an equitable adjustment shall be
made of the contract price and completion date upon mutual agreement of
the parties reflecting such adjustments by way of written order subject
to the provisions of the IRR of P.D. 1594, as last amended and the
approval of the President.

8.2 Should the PEA find it necessary to have
any additional work carried out for the purposes of the Project in
addition to the contracted work, such additional work will be carried
out immediately by the CONTRACTOR upon receiving
written approval from the President, provided that the amount of the
change order is within the limitations and in accordance with conditions
set forth in P.D. 1594 and its IRR.[24] (Emphasis in the original)

The Agreement also explicitly states that the Contractor “shall
commence prosecution of the Project within 10 calendar days from receipt
of the Written Notice to Proceed from the PEA, and shall finish and
complete the construction of the entire Project to PEA’s satisfaction
within 360 calendar days.”[25]
The 15% advance payment provision, as stated in the Memorandum of the
Executive Secretary, was likewise included. The Agreement also has a
notation on Page II thereof, which states “Funds Available in the amount
of PHP 300 million for Phase I only.”[26]

Thereafter, PEA issued the Notice to Proceed dated April 10, 2000,
giving JD Legaspi 360 calendar days for the entire project, that was to
commence seven calendar days from receipt thereof. Said Notice to
Proceed was stamped “Received” on April 11, 2000.[27] At this point, PEA had only received PHP 300 Million from Land Bank of the Philippines (LandBank)
as loan proceeds, as evidenced by the Comptroller’s note on the signed
Construction Agreement. The PEA Board of Directors also approved a loan
from the Government Service Insurance System (GSIS) for PHP 600 million.[28]

Several Variation Orders followed the signing of the Agreement. The first of these Variation Orders (later renamed as Variation Order No. 2)
was for the construction of the Seaside Drive Extension and Inland
Channel to facilitate the flow of traffic at the Seaside Drive
Extension, submitted by Beriña, Jr. for consideration of the Board of
Directors on June 27, 2000. The total amount of the Variation Order as
presented to the Board was PHP 117,454,756.71. Beriña, Jr. explained
that the bridge must be constructed to avoid the gap between Central
Business Park II and Central Business Park I B & C. The Memorandum
likewise stated that the bridge was originally included in the proposed
bidding of Package 2, which did not materialize because R1 Consortium
merely indicated its willingness to construct the Central Boulevard at
Central Business Park I B & C under their Joint Venture Agreement,
but not the bridge. He thus recommended that the additional works be
awarded to the contractor of Package 1, subject to fulfillment of
certain conditions.[29] This Variation Order was approved by the Board of Directors on July 5, 2000, subject to the conditions set forth by Beriña, Jr.[30]

Another Variation Order (Variation Order No. 1)
was approved by the Board on January 29, 2001. It involved the
realignment of certain items of work with no additional cost and
additional time. Variation Order No. 1 was deemed necessary because of
the changes in the original plans and in order to suit the actual field
conditions. The changes were mainly on the thickness of pavement
structures, number of layers of geotextile/geogrid materials, and the
type of drainage system (from reinforced concrete pipe culvert to
reinforced concrete box culvert). The effect of the Variation Order was
considered reasonable by the COA after review, as shown by the Review
Report later that same year.[31]

Then on March 21, 2001, Beriña, Jr. requested for approval of the
revised cost of Variation Order No. 2 based on the detailed plans in the
total amount of PHP 126,440,810.20 which includes the following works:[32]

1.
Design and Construction of
Bridge across the 42 m. inland channel between Central Business Park 1, B
& C (CBP-1 B&C) and Central Business Park 2 (CBP-II) including
the design and construction of containment walls at the approaches of
the proposed bridge and the design and construction of the bridge
approaches. The construction of the bridge is necessary to connect the
Central Boulevard of CBP-1 B&C and CBP-II so that the Central
Boulevard can be fully utilized from Buendia Extension to Asiaworld
Property before the end of 2001.
2.
Design and construction of the Seaside
Drive extension that will serve as an access to Roxas Boulevard and
Seaside Drive going to the National Airport (NAIA).[33]

The additional quantities for earthwork excavation, embankment,
disposal of unsuitable materials and geotextile/geogrid materials, which
resulted to the increase in the amount for Variation Order No. 2, was
approved by the Board of Directors on June 29, 2001. Nevertheless, it
was already on July 19, 2002 when PEA issued the Notice to Proceed for
Variation Order No. 2.[34]

It would appear that on April 3, 2001, Jaime R. Millan (Millan)
recommended the grant of time extension to JD Legaspi until the balance
of the PHP 1 billion loan was secured. This was on account of JD
Legaspi’s letter to PEA on January 16, 2001, which was received on March
12, 2001, requesting for a time suspension effective January 15, 2001
due to unavailability of funds. The same time suspension was lifted
effective June 14, 2002.[35]

In the meantime, there were substantial changes in the composition of
the Board of Directors of PEA. Between March and July 2001, new members
of the board came in, giving rise to a different set of directors. From
thereon, the Board of Directors consisted of the following:

Ernest F.O. Villareal -Chairman
Benjamin Cariño -General Manager
Joemari Gerochi -Member
Sulficio Tagud, Jr. -Member
Angelito Villanueva -Member
Rodolfo Tuazon -Member
Martin Sarciego, Jr. -Member[36]

Then, on July 24, 2001, JD Legaspi requested for a price adjustment based on Section Instruction to Bidders (IB) 10.10 of the Implementing Rules and Regulation[37] (IRR) of Presidential Decree (P.D.) No. 1594[38],
amounting to PHP 45,811,510.32. The request sent by JD Legaspi was
forwarded by Millan to Cariño for the latter’s consideration on August
24, 2001. The Internal Memo was noted by Cariño “Ask for COA approval of
the adjusted unit prices prior to payment.” The said request was
endorsed to the Board of Directors by Beriña, Jr. through a Memorandum
dated October 24, 2001.[39]

During the meeting of the Board of Directors held on November 6,
2001, they approved the request of JD Legaspi but lowered the contract
price adjustment to PHP 42,418,493.64, which was 7.26% of the contract
amount. Then, during the December 5, 2001 meeting of the Board of
Directors, Tagud questioned the authority of PEA Management to approve
the price adjustment. The PEA Management was then directed to verify if
the subject contract price adjustment was within the approval limits of
management. In the following Board Meeting on December 14, 2001, Beriña,
Jr. explained the process of dealing with price adjustments and
escalations, with the former taking effect if the Notice to Proceed was
issued after 120 calendar days from the bidding date. The Board
eventually decided to defer discussion on the matter until justification
was forwarded to them.[40]

The matter was not brought up until Beriña, Jr. sent a Memorandum dated
April 16, 2002 to the Board, requesting for confirmation of the
contract price adjustment. In its Price Adjustment Review Report, the
COA deemed the price adjustment reasonable. The COA Report was
eventually relayed to PEA by De la Paz and the price adjustment was
finally approved on April 19, 2002, through Resolution No. 3203, series
of 2002, which also provides that the same is chargeable to the proceeds
of the PHP 1 billion loan with the GSIS, and will only be due and
demandable when the loan proceeds are released to PEA.[41]

Near the tail end of the project, Beriña, Jr. requested the Board of
Directors to confirm Variation Order Nos. 3, 4 and 5 for the President
Diosdado Macapagal Boulevard, to be chargeable against the GSIS loan
secured for the purpose. Variation Order No. 3 is for landscaping works
of the Central Boulevard amounting to PHP 13,357,005.00, No. 4 is for
additional items of work amounting to PHP 4,759,630.80, and No. 5 is for
landscaping work of the Seaside Drive amounting to PHP 1,244,949.00.[42]

Finally, Beriña, Jr. requested confirmation and appropriation of funds
from the Board of Directors for the Overrun/Underrun quantities or
costs of Items of work of the PDMB Road Project Package 1 due to the
disparity between the Bid Plans (preconstruction plans) and the
approved construction plans, and actual works accomplished to suit
actual field conditions. The Memorandum signed by Beriña, Jr. includes
the following table summarizing the amounts of overruns:[43]

Description
Original Amount
Overrun/
Underrun
Revised Amount
% Increase
1. Variation Order No. 1 (Original Contract)
P584,365,885.05
P67,982,609.07
P652,348,494.12
11.6336
2. Variation Order No. 2
a. Seaside Drive Extension
b. Bridge at 42-m Inland Channel
 
P51,689,856.48
P74,750,953.72
 
P5,908,444.62
P5,441,470.39
 
P57,598,301.10
P80,192,424.11
 
11.4306
7.2795
TOTAL
P710,806,695.25
P79,332,524.08
P790,139,219.33
11.1609[44]

The same Memorandum contained a request to enter into a
Supplemental Agreement with JD Legaspi on the Overrun/Underrun
quantities that exceeded 25% of the original contract quantities/costs
per items of work, amounting to PHP 57,031,012.96.[45]

On August 13, 2002, the Board of Directors confirmed and approved
Variation Order No. 4 and the Final Bill of Quantities
(Overruns/Underruns) in the amount of PHP 4,759,630.80 and the amount of
PHP 79,332,524.08 through Resolution No. 3272, series of 2002. The
Resolution also authorized PEA Management to enter into a Supplemental
Agreement with JD Legaspi for quantities exceeding 25% of the original
contract quantities or costs per items of work. On August 22, 2002, a
Supplemental Agreement was then entered into by PEA, then represented by
Cariño and JD Legaspi, where PEA agreed to pay JD Legaspi for the
faithful and satisfactory performance of the additional works stipulated
in Variation Order No. 1 and the works required to complete the Seaside
Drive Extension and the bridge at the 42-meter Inland Channel. The
contract was priced at PHP 57,031,012.96.[46]

These Internal Memoranda requesting approvals for Variation Orders were
sent to the General Manager (Cariño in most cases, since these were
made in the implementation stage of the Agreement) by Millan, with
Beriña, Jr. recommending the approval thereof.[47]

The PDMB was inaugurated on April 5, 2002 and was eventually opened to the public on July 15, 2002.[48]

In 2003, a Subsoil Assessment Report was commissioned by the Senate of
the Philippines. It was found that the subsoil was characterized by fill
materials predominantly consisting of sands with silts and clays and
with traces of gravels, but the same was based on subsurface
investigation data from the four boreholes and the four test pits only.
The body that conducted the assessment also commented that the soil
stratification on other locations along the alignment may differ from
those mentioned in the report. Further tests were conducted later that
year, and it was concluded that additional borehole drilling results
were consistent with the initial findings, that is, materials were
considered suitable fill materials and that the in-place embankment
materials of the reclaimed site were suitable based on provisions of
the DPWH Standard Specifications for Highways and Bridges.[49]

The issue of overpricing on the PDMB project eventually broke
out and a Senate investigation was commenced. Because of this, PEA
denied the request of JD Legaspi for payment on October 13, 2003 and
October 11, 2004. Thereafter, JD Legaspi was compelled to file a case
for Specific Performance, which was decided in its favor on January 10,
2007. On December 5, 2007, PEA, now Philippine Reclamation Authority (PRA) entered into a Compromise Agreement with JD Legaspi for the payment of the 13th
Progress Billing for the PDMB in the amount of PHP 27,471,322.84,
attorney’s fees of PHP 100,000.00, and interest of PHP 4,593,117.48. The
said Compromise Agreement was approved by Branch 148 of the Regional
Trial Court of Makati City, where JD Legaspi filed the case demanding
payment for the unpaid portion of the Progress Billings submitted to
PEA.[50]

All in all,
the total amount received by JD Legaspi was PHP 839,312,471.47. The
total amount of the variation orders amounted to PHP 145,802,395.00 or
24.95% of the total contract amount. The amounts received by JD Legaspi
are broken down as follows:[51]

Original contract P584,365,885.05
Contract Price Adjustment P42,418,493.64
Overrun/Underrun P79,332,524.08
Variation Order No. 2 P126,440,810.20
Variation Order No. 4 P4,759,630.80
   
Total P837,317,343.77
Interest and Attorney’s Fees P1,995,127.70
Overall Total P839,312,471.47[52]

On June 6, 2003, an Information[53] was filed with the Sandiganbayan charging inter alia,
the members of the Old PEA Board, the members of the new PEA Board, the
PEA Management, JD Legaspi, and auditors of the COA for violation of
Section 3(e) of Republic Act (R.A.) No. 3019,[54] allegedly committed as follows:

That in or about the period from April 1999 to August 2002, in
Metro Manila, Philippines, and within the jurisdiction of this Honorable
Court, accused public officials of the Public Estates Authority (PEA),
namely: CARLOS P. DOBLE, former General Manager (with Salary Grade 30)
and ex-oficio member of the PEA Board, BENJAMIN V. CARIÑO, PEA General Manager (with Salary Grade 30) and ex-oficio
member of the Board, and other responsible public officials of PEA,
namely: FRISCO FRANSICO SAN JUAN, former Chairman of the Board,
CARMELITA DE LEON-CHAN, DANIEL T. DAYAN, SALVADOR P. MALBAROSA, LEO V.
PADILLA and ELPIDIO G. DAMASO, all former members of the Board, ERNEST
FREDERICK O. VILLAREAL, Chairman of the Board, and JOEMARI D. GEROCHI,
ANGELITO M. VILLANUEVA, MARTIN S. SANCIEGO, JR., and RODOLFO T. TUAZON,
all Board members, JAIME R. MILLAN, Assistant General Manager, MANUEL R.
BERIÑA, JR., Deputy General Manager for Operations & Technical
Services and Chairman of the Ad Hoc Committee responsible for the
bidding and award of the construction contract for the President
Diosdado Macapagal Boulevard Project, THERON VICTOR V. LACSON, Deputy
General Manager for Finance, Legal and Administration and member of the Ad Hoc Committee, BERNARDO T. VIRAY, Manager for Technical Services Department and member of the Ad Hoc Committee, RAPHAEL POCHOLO A. ZORILLA, Project Management Officer, ERNESTO L. ENRIQUEZ, Senior Corporate Attorney and member of the Ad Hoc Committee,
and CRISTINA AMPOSTA-MORTEL, Department Manager, Legal Department, and
other responsible public officials of the Commission on Audit (COA),
namely: MANUELA E. DELA PAZ, State Auditor V, ARTURO S. LAYUG, State
Auditor V and Chief of Technical Services Audit Division A, Technical
Services Offices, BENILDA E. MENDOZA, Supervising Technical Audit,
EPIFANIO L. PUREZA, Assistant Chief of the Technical Services Audit
Division A, JOSE G. CAPISTRANO, Technical Audit Specialist II, and MA.
CECILIA A. DELA RAMA, Technical Audit Specialist I, all of whom were
public officials during the times material to the subject offense, while
said public officials were occupying their respective positions as just
stated, acting in such capacity and committing the subject offense in
relation to office and while in the performance of their functions and
duties, with manifest partiality and evident bad faith (or at the very
least, gross inexcusable negligence), conspiring and confederating
with accused JESUSITO D. LEGASPI, a private contractor doing business
under the name of JD Legaspi Construction, did then and there,
willfully, unlawfully and criminally give unwarranted benefits,
advantage and preference to accused JESUSITO D. LEGASPI, through the
commission of numerous illegal related acts all pertaining to the
President Diosdado Macapagal Boulevard Project, such as (but not limited
to) the bidding out of the said project and illegally awarding the same
to accused JESUSITO D. LEGASPI’s JD Legaspi Construction and approving
the award of the project to, as well as the Construction Agreement
with, JD Legaspi Construction despite the lack of compliance with the
mandatory requirements and procedure for bidding, even if no funds are
yet available to finance the project, without the requisite certificate
of availability of funds and without complying with the mandatory
conditions imposed by the Office of the President for the approval
thereof, per Memorandum dated 29 January 2000 from the Office of the
Executive Secretary, Malacañang, and approving/allowing several improper
variation/change orders and overruns to be implemented without the
requisite presidential approval and the appropriate funds, recognizing,
affirming and causing the implementation of the just-mentioned void
contract, allowing and paying or causing the allowance and payment of
several claims of accused JESUSITO D. LEGASPI for initial contract
price, contract price adjustment, variation orders, overruns and other
claims even when the same were clearly improper, illegal and without the
requisite presidential approval, thereby paving the way for accused
JESUSITO D. LEGASPI to claim and receive undue payments from the
Government totalling millions of pesos in improper overprice, thereby
causing undue injury and grave damage to the government in the aggregate
amount of at least FIVE HUNDRED THIRTY TWO MILLION NINE HUNDRED TWENTY-SIX THOUSAND FOUR HUNDRED TWENTY AND 39/100 PESOS (P532,926,420.39), more or less, constituting the total illegal overprice paid to accused JESUSITO D. LEGASPI for the subject Project.

CONTRARY TO LAW.[55] (Emphasis in the original)

Consequently, warrants of arrest were issued against the accused
on June 27, 2003. Villareal, San Juan, and Doble filed their cash bonds
with the Sandiganbayan while Zorilla, Lacson, Viray, Beriña Jr., and
Millan posted their surety bonds. After their respective Motion for
Reduction of Bail was granted, Pureza, Capistrano, De la Rama, Mendoza,
and De la Paz likewise posted their cash bonds with the Sandiganbayan.[56]

The accused were arraigned on various dates and entered their
respective pleas. On July 24, 2003, Villanueva was arraigned and he
entered a plea of not guilty. Then, on January 21, 2005, Malbarosa, San
Juan, Tuazon, Chan, Damaso, Legaspi, Dayan, Beriña, Jr., Millan,
Zorilla, Viray, Gerochi, Cariño, and Amposta-Mortel refused to enter a
plea. On February 15, 2005, Villareal, Padilla, and Lacson refused to
enter a plea. On February 24, 2005, Doble did not enter a plea. Lastly,
on March 10, 2005, Layug, Pureza and Capistrano refused to enter a plea.
Consequently, this Court entered a plea of not guilty for those who
refused to enter a plea.[57]

After due proceedings, the Sandiganbayan rendered the assailed Decision dated February 5, 2015.

Sandiganbayan Decision

In convicting petitioners for violation of Section 3(e) of R.A. No.
3019, the Sandiganbayan found that the procedures for simplified bidding
of a flagship project were not followed. Under IB 10.4.2.5, IRR of P.D.
No. 1594, as amended, the participants for such project must be limited
to bona fide contractors duly accredited and classified for
the project category and size, and who are included in a separate
masterlist to be prepared by the Philippine Contractors Accreditation
Board (PCAB).[58]
However, instead of complying with this requirement, PEA elected to
limit its shortlisted bidders to only 10 contractors who were listed in
the roster prepared by the DPWH. PEA did this in spite of the fact that
the “Invitation to Contractors” clearly stated that PEA invited bids
from contractors who were included in the PCAB masterlist.[59]
JD Legaspi, it appears, had a PCAB license as a Large “B” contractor.
The records and evidence however, do not show that the other nine
contractors in the DPWH list had valid PCAB licenses at the time of the
bidding.[60]

Likewise, PEA divided the PDMB project into Package 1 and
Package 2, for purposes of the simplified bidding without rational
basis, as it merely chose the first five contractors in the DPWH list
for the Package 1 bidding and the other half for Package 2. Package 1
covered the PDMB project consisting of that portion awarded to JD
Legaspi. Package 2 consisted of the portion of the Central Boulevard in
which PEA had a prior joint venture agreement with SM and R1 Consortium
wherein the latter two developers had the option to construct, in
exchange for land or bonds, their respective portions. Thus, those
contractors for the Package 2 bidding were, from the start,
disadvantaged on account of the great possibility that Package 2 could
not be bid out because of the option given to SM and R1 Consortium. In
turn, those contractors that were assigned for Package 1 were favored by
PEA’s arbitrary decision. This is because by just being listed ahead in
the DPWH list, they were certain to be able to bid and, in the case of
JD Legaspi, win the award for Package 1. This alone gave undue advantage
to the first set of contractors and prejudiced the second set.[61]
JD Legaspi, which was second on the DPWH list, therefore gained an
advantage or benefit, as it was able to bid and win Package 1, to the
disadvantage of those contractors in the second set of the DPWH list and
also those PCAB-accredited contractors in the latter’s masterlist, who
were not included in the DPWH list.[62]

The Sandiganbayan likewise found the lack of detailed engineering
requirements, which must be submitted before any bidding. While Beriña,
Jr. and Millan claimed that the project awarded to JD Legaspi was a
design and build contract, the approved agency estimate did not include
the design cost, which was pegged by PEA at PHP 13.5 million. Thus, the
design plans should have been done before any bidding in order to arrive
at an approved agency estimate. As part of the detailed engineering
requirement, there should have been definitive soil foundation and
investigation results for purposes of bidding. Furthermore, design was
not mentioned in the scope of works in the Construction Agreement and
Invitation to Bid in the award of the project to JD Legaspi. This was
what PEA did with respect to its contract with R1 Consortium in
connection with the Roxas Canal West Bridge, which is part of the
Central Boulevard project. This was not however present in the contract
with JD Legaspi.[63]

The Sandiganbayan also cited the Government Auditing Code that
proscribes the making of any contract involving the expenditure of
public funds unless there is an appropriation therefor.[64]
In this case, PEA, at the time when the PDMB project was bid out, only
provided a Board Resolution identifying the source of the fund. PEA
hoped to secure loans in the amount of PHP 1 billion to finance the
project. When the PEA Board approved the award of the contract to JD
Legaspi on November 3, 1999, it identified the source of the PHP
584,365,885.05 cost of the project to be the PHP 1 billion loan facility
from the Landbank/All Asia Capital group. However, the said loan was
yet inexistent as it was still under negotiation at the time.[65]
Further, at the time the JD Legaspi contract was signed, dated and
notarized on April 10, 2000, only the amount of PHP 300 million was
actually released and available from the proceeds of the Landbank loan.
This was found to be in open defiance of one of the conditions imposed
by the Office of the President that approval of the JD Legaspi contract
should be preceded by “final approval and release of the loan proceeds
from the Landbank and All Asia Capital.”[66]
The PEA Management even divided the contract into two phases: Phase I
for works corresponding to the PHP 300 million available funds and Phase
II covering the remaining works of the entire project. In the executed
contract, however, it was clear that Phase II could be undertaken only
if and when funds are made available again. This explicitly recognized
and admitted that PEA did not have enough funds to finance the JD
Legaspi contract at the time of its execution.[67]

The result was that PEA ran out of funds and could not pursue, as
scheduled, the remaining works left to be funded. The PHP 300 million
initial funds were depleted by October 15, 2000. Naturally, JD Legaspi
filed a notice of suspension of work as his claims for payment could not
be funded. PEA, thus, issued a Suspension of Work Order effective
January 15, 2001, which was only lifted on June 14, 2002.[68]

Moreover, despite only having PHP 300 million initial funds for Phase I
of the project, Beriña, Jr. recommended as early as July 5, 2000, or
barely three months after the notice to proceed was issued to JD
Legaspi, that the PEA Board approve Variation Order No. 2 consisting of
the construction of the Inland Channel Bridge and the Seaside Drive
Extension with a final cost of around PHP 126 million. These additional
works were not part of JD Legaspi’s original contract.[69]

PEA also violated the requirement that all extra works and price
adjustments should be first submitted to the President for approval.[70]
While PEA contended that this requirement only applied to extra work
and not works for variation orders, the Sandiganbayan found that the
requirement covered any kind of price adjustment, and not only those
related to variation orders. This is because a variation order for
additional work necessarily carries with it a price adjustment, and
presidential approval of the Variation Order will implicitly carry
approval of the price adjustment.[71]
JD Legaspi was thereafter paid the amount of PHP 42,418,493.64 because
of a contract price adjustment due to the late issuance of the Notice to
Proceed, after the date of bidding. The Sandiganbayan found that no
presidential approval was secured for this price adjustment, with PEA
contending that only price adjustments arising from change orders had to
be priorly approved.[72] By
the terms of the Construction Agreement, however, PEA had to secure the
OP’s approval for any Variation/Change Order. As the Sandiganbayan
declared, the contract was the law between the parties, binding on both
of them.[73]

Further,
the Seaside Drive Extension under Variation Order No. 2 cannot legally
qualify to be covered by a variation order because it was a road outside
of the PDMB project and nowhere along the original PDMB roadway plan.
It was, in fact, a roadway connecting PDMB and Roxas Boulevard.[74]
As it was not part of the PDMB project, it could not legally be a
variation order or a change order. PEA should have taken steps to
include this road in the bidding for the PDMB project. As such, the
Seaside Drive Extension that entailed a total cost of PHP 57,598,301.10
should have been bid out.[75]

Overall, the Sandiganbayan found the JD Legaspi contract to be
overpriced. It held that overpricing should not be hinged on whether the
cost of materials and labor, on a unit price basis, greatly exceeded
the total contract price of PHP 584 million. Overpricing may also come
into play when payments to a contractor are made beyond the total
contract price arising out of irregular or unauthorized contract price
adjustments and variation/change orders.[76]
The overpriced amount, which comprised the adjustments in the amount of
PHP 42,418,493.64 and the cost of the Seaside Drive Extension in the
adjusted amount of PHP 57,598,301.10, total to PHP 100,016,794.74 that
were paid to JD Legaspi.[77]

The liability of the petitioners was then described as follows:

Liability of Beriña, Jr., Lacson, Millan, Viray and Zorilla (Members of PEA Management)

Through their various positions, Millan and Beriña[, Jr.] and the other members of the Ad Hoc
Committee, Lacson and Viray, clearly had the duty to be involved in the
planning and execution of all PEA Projects, including the PDMB project
and to ensure that the same complied with the law . . . their actions
[however caused] damage to the government by awarding the PDMB project
to Legaspi and paving the way for the approval of the price adjustment,
variation orders and final bill of quantities despite the legal
infirmities of the same.[78] Accused Zorilla, despite not being [a , member of the Ad Hoc
Committee, cannot be said to be without fault.] He prepared the
Approved Agency Estimate for the PDMB project despite the lack of a
detailed engineering . . . As per the law and common sense, a detailed
engineering is a crucial part of formulating an Approved Agency
Estimate.[79] (Emphasis in the original)

Liability of Amposta-Mortel

Amposta-Mortel . . . was the Department Manager of the Legal Department of PEA[80]
. . . and was to act as the legal adviser and therefore render advisory
or legal opinion. It is incumbent upon her to recommend, draft and
approve legal instruments involving PEA.[81]
. . . [S]he herself was aware that there were not enough funds to cover
the transaction. [T]hough she allegedly went over the initial
Construction Agreement, as shown by her signature, her findings on the
legality of its provisions or the compliance of PEA with the conditions
imposed by the Office of the President were conspicuously absent, which
only goes to show that either she purposely failed to do her job to
review the contract, or she was negligent in her duties. Her argument
that she only reviews matters which are brought to her attention showed
her lackadaisical attitude towards her duties as Manager of the Legal
Department.[82]

Liability of San Juan, Chan, Dayan, Malbarosa, Padilla, and Damaso (Members of the Old Board of Directors)

All the members of the Old Board are liable for the following:

1.
Resolution No. 2032 dated
November 3, 1999, approving the award of the contract to [JD] Legaspi,
despite the absence of any appropriation or actual loan proceeds from
Landbank/All Asia Capital.
   
2.
Resolution No. 2057 dated December 15,
1999, covering the approval of the construction agreement despite
insufficient funding. This resulted in PEA’s inability to issue a notice
to proceed within 120 days from bidding date, thus, enabling [JD]
Legaspi to claim the contract price adjustment of over [PHP] 42 million.
   
3.
Resolution No. 3017 dated July 5, 2000,
approval of Variation Order No. 1 (later renumbered as Variation Order
No. 2 under Resolution No. 3102), for lack of bidding on the Seaside
Drive Extension which cannot be considered germane to the JD Legaspi
agreement, the same not being part and parcel of the original Package 1
project.
   
4.
Resolution No. 3102 dated April 26,
2001, in relation to Resolution No. 3017, allowing an increase on the
cost of Variation Order No. 2, which included the Seaside Drive
Extension.[83]

As to Villareal, Gerochi, Villanueva, Sanciego, Jr., and Tuazon
(members of the new Board of Directors), they assumed their duties
between March and July 2001 when the PDMB project was already under
construction.[84] Unlike the
Old Board, the new Board no longer had the opportunity to question the
award and approval of the Construction Agreement with JD Legaspi.[85]
While the contract price adjustment of more than PHP 42 million was
irregular, the new Board’s confirmation of the same cannot be taken as a
conspiratorial act on their part. The claim of Legaspi was an offshoot
of the belated issuance of the Notice to Proceed which was partly caused
by PEA’s inability to secure total funding for the PDMB project. Thus,
the new Board had nothing to do with these deficiencies.[86]

With respect to Dela Paz, Layug, Mendoza, Pureza, Capistrano, and
De la Rama (officers of the COA), their roles were limited to
post-audit.[87] Moreover, the
findings of COA officials that the total project cost, including the
price adjustments, was reasonable and not overpriced were affirmed by
subsequent COA Special Audit Report.[88]
De la Paz failed to consider that even as an observer, she should have
noted and included in her report that the contract for the project was
awarded to JD Legaspi even before the funds for the project was
available. Nevertheless, such negligence, by itself, does not prove
conspiracy with JD Legaspi. Given that she referred the contract and
variation orders to the Technical Services Office and gathered positive
findings from the same, it can be said that she fulfilled her duties
albeit to a less than ideal degree.[89]

As to JD Legaspi, the Sandiganbayan found no conspiracy in the award of the PDMB Project.[90]
However, as to the contract for the Seaside Drive Extension, it found
that Legaspi pushed for the variation order, which was not part of the
original contract and claimed for overruns that resulted into the final
bill for the project that is 43% higher than the original contract
price. PEA Management would not have presented the same to the Old Board
had JD Legaspi not submitted documents pertaining to the possibility of
constructing the same as a change order to the original Construction
Agreement, thereby violating all the public bidding rules already in
place.[91]

Further, the
Construction Agreement obligated JD Legaspi to carry out additional
work only upon receiving written approval from the President. However,
despite the lack of this written approval, JD Legaspi started and
finished Variation Order No. 2. The Notice to Proceed for Variation
Order No. 2 was issued only on July 19, 2002 but the project was
allegedly finished sometime in July 2002 and was opened to the public on
July 15, 2002.[92]

Those found liable for violation of R.A. No. 3019 were also found civilly liable for the amount of PHP 100,016,794.74.[93]

Several motions for reconsideration were filed, which were resolved by the Sandiganbayan in its Joint Resolution[94]
dated September 16, 2015. In this Resolution, the Sandiganbayan
maintained its findings of criminal liability but increased the civil
liability of the members of the Old Board and PEA Management to include
the overruns of Variation Order No. 1 amounting to PHP 67,982,609.07,[95]
involving changes mainly on the thickness of pavement structures,
number of layers of geotextile/geogrid materials, and the type of
drainage system (from reinforced concrete pipe culvert to reinforced
concrete box culvert).[96] The
Sandiganbayan also included the overruns for the Inland Channel Bridge
under Variation Order No. 2 in the amount of PHP 5,441,470.39.[97] There was thus an additional civil liability in the amount of PHP 73,424,079.46[98] and the total civil liability was increased to PHP 173,440,874.20.[99]

These were included because the extra quantities claimed by JD Legaspi
as overruns were actually foreseeable and determinable had there been a
detailed engineering before the PDMB project was bid out. Part of the
detailed engineering activities is soil and foundation investigation.[100] They are not in the nature of conditions that are not known or cannot be predicted at the time the quantities are prepared.[101]
The additional amount cannot however be charged against JD Legaspi
since detailed engineering is a requirement prior to bidding. The guilt
of JD Legaspi was limited only to the Seaside Drive Extension where this
Court found an implied conspiracy.[102]

On the other hand, the Inland Channel Bridge is differently situated
from the Seaside Drive Extension, although both were claimed by JD
Legaspi and approved by the Board under Variation Order No. 2. The
Inland Channel Bridge was necessary because without it, the PDMB Project
would be useless as there would be a gap between the segment built by
JD Legaspi and R1 Consortium unlike the Seaside Drive Extension that was
outside the PDMB project.[103] The civil liability of JD Legaspi was then limited to the Seaside Drive Extension in the amount of PHP 57,598,301.10.[104]

Hence, the instant Petition.

Issues

The common issues brought forth by petitioners are as follows:

I.

Whether the Sandiganbayan erred in finding petitioners guilty
beyond reasonable doubt for violation of Section 3(e) of R.A. No. 3019

II.

Whether Amposta-Mortel and the members of the Old Board of PEA
and the PEA management should be held civilly liable in the amount of
PHP 173,440,874.20 for the irregularities that accompanied the
construction of the PDMB Project

III.

Whether JD Legaspi should be held civilly liable
to pay the amount of PHP 57,598,301.10 for the construction of the
Seaside Drive Extension under Variation Order No. 2

Pertinent arguments raised by petitioners are as follows:

G.R. No. 220500

Amposta-Mortel argues that while one of her functions is to direct the
preparation and review of all contracts and other legal instruments to
which PEA is a party, there are some unwritten rules and policies that
her office has been practicing even before her assumption to office as
Head of Legal Department. She explained that the General Manager of PEA
is clothed with power and prerogatives to decide and appoint individuals
to whom he would like to assist him with the projects. Thus, he created
an Ad Hoc Committee for this particular project.[105]

In turn, the actions of the Ad Hoc
Committee were submitted to the PEA General Manager and approved by the
Governing Board and the Office of the President. Amposta-Mortel claimed
that there was no directive on the part of the lawyer assigned in the Ad Hoc
Committee, Atty. Enriquez, to submit the contract to the Legal
Department, which she heads, for her review before it was made part of
the bid documents and before it was approved by the Board.[106]

Moreover, at the time when Amposta-Mortel was called upon to review the
written contract, the PDMB project was already a done deal. The
contract has been previously signed by Doble, in his capacity as the
General Manager of PEA, and Jesusito Legaspi, as owner of JD Legaspi,
the winning contractor, albeit it was submitted for review to the Office
of the President and the Office Government Corporate Counsel (OGCC).[107]

With respect to the availability of funds, Amposta-Mortel argued that
she relied on Board Resolution No. 2032, series of 1999, which stated
that the contract amount needed for the project is chargeable against
the proceeds of the PHP 1 billion loan from LandBank/All Asia Capital.
However, she was not aware how much was the actual available funds for
the project at the time she affixed her initials in the contract.[108]

As to the variation orders and other requests for payments that were
submitted and approved after the execution of the contract and during
the implementation of the project, it was only Variation Order No. 1,
which entailed additional works to the Central Boulevard at no
additional costs, that was referred to her for review. Even then, she
gave her legal opinion that Variation Order No. 1, even if it does not
entail additional costs, would have to be submitted for approval to the
Office of the President pursuant to the conditions imposed by the said
Office.[109]

Amposta-Mortel insists that she is not a member of the Ad Hoc Committee tasked to implement the project and did not have a hand in its creation. All actions of the Ad Hoc
Committee were submitted to the General Manager without having been
referred to her for legal opinion. Moreover, she reviewed the
Construction Agreement after the same had undergone separate reviews by
the OGCC and the Office of the President, and only after the General
Manager asked her to do so before the parties signed the same anew.[110]
She also cited the Decision dated May 30, 2008 rendered by the Office
of the Ombudsman, where she was absolved from administrative liability
based on the same allegations in the criminal complaint subject of the
instant petition.[111]

G.R. No. 220504

On the part of Lacson, he argues that in rendering its Decision, the
Sandiganbayan relied heavily on the pieces of evidence presented by the
prosecution and thereafter found him guilty because he was a member of
the Ad Hoc Committee, which recommended the award of the project to JD Legaspi after a series of due diligence all in pursuance to law.[112]

Lacson claims that he did not participate in the preparation of the
minutes or the deliberation on the approval of various resolutions.
Further, the prosecution’s witness, Atty. Karen Villamil,[113]
stressed on re-cross examination that Lacson, who is part of
management, has not signed any memoranda directing the Board to act on
anything or to issue a resolution.[114]

Lacson argues that he simply performed his duties as a member of the Ad Hoc
Committee. He signed the Abstract of Bids attesting to the results of
the bidding, which was likewise signed by the COA representative. Also,
he signed the Bid Evaluation Report that described the bidding process;
the request to the DPWH for a list of qualified contractors for roads
and bridges with large “B” and triple “AAA” license category; the pre-
and post-qualification evaluation report of bidders; and the
recommendation to award the PDMB Project to JD Legaspi as the lowest
complying bid pursuant to P.D. No. 1594 and its IRR. The recommendation
was approved by the General Manager, and attached it to a memorandum to
the Board, which likewise approved the same. After all of the foregoing
and at that point in time, the functions and responsibilities of Lacson
in the Ad Hoc Committee have ceased to exist.[115]

Lacson further explained that in compliance with the requirement to
source participants in a “simplified public bidding” from the separate
masterlist to be prepared by the PCAB, Atty. Enriquez, a member of the Ad Hoc
Committee, reported that this “separate masterlist” was not yet
available then. Instead, he was furnished with a copy of a general
masterlist of PCAB in the NCR containing hundreds of listed contractors
with their respective PCAB category/license.[116]
The problem then was how to narrow down the list of pre-qualified
bidders to achieve the objective of conducting a “simplified public
bidding” as approved by the Office of the President. To use the general
masterlist obtained by Atty. Enriquez could be unwieldy and militate
against the presidential instructions to immediately have the PDMB
Project available to the public. Hence, the Chairman of the Ad Hoc
Committee decided to seek the help of the DPWH for a list of PCAB
contractors with large “B,” triple “AAA” category/license for roads and
bridges since this is the nature of the PDMB Project.[117]

Moreover, the COA gave its clearance to the PDMB original contract
price of PHP 584 million, and considered it reasonable. This means that
the approved agency estimate, which was derived from the bid plans,
including the detailed engineering component, was quite reasonable and
accurate. One cannot have an acceptable approved agency estimate without
a sufficiently detailed engineering. Furthermore, the clustering of the
five responsive bids within the allowable thresholds or range of values
prescribed in the implementing rules of P.D. No. 1594 shows that the
requirement of detailed engineering was substantially complied with.[118]

With respect to the issue of funding, Lacson argues that the provisions
of P.D. No. 1594 and its IRR state that in the process of bidding and
recommending award for the project, it is merely required to pinpoint
the source of funding. This was complied with under Board Resolution No.
1895, series of September 28, 1998 approving the PDMB project and
pinpointing its source of funding, i.e., PHP 1 billion loan from
financial institutions, which the General Manager was authorized to
negotiate. This was followed by Board Resolution No. 1959, series of
1999 when the Board approved the terms and conditions of the above
loan/security from, LandBank/ All Asia Capital as Financial Advisor and
Arranger on April 5, 1999. The above documents were already in existence
before the creation of the Ad Hoc Committee in April 1999.[119]

Lacson further claims that he has nothing to do with Variation Order
No. 2. There is no evidence, either testimonial or documentary
presented, wherein he participated, discussed, endorsed or even
initialed or signed any notes or memorandum recommending the approval of
Variation Order No. 2 to the Board. All the prosecution witnesses, as
well as the defense witnesses, including their respective documents have
never even hinted of Lacson’s involvement in such matters as price
adjustment, Variation Order Nos. 1 to 5, price escalation, extra works,
charge orders, bill of quantities, overruns/underruns, etc. After all,
Lacson is a non-technical or non-engineering person who does not possess
the expertise or training in infrastructure contract implementation.
Most important, the Ad Hoc Committee ceased to exist after
the recommendation was made. Variation Order No. 2 was agreed when
Lacson’s participation in the PDMB Project became nil.[120]

G.R. Nos. 220505, 220552, 220568, 220580 & 220592

As to the liability of the members of the Old PEA Board, the
Sandiganbayan found them criminally liable for violation of Section 3(e)
of R.A. No. 3019, holding that their acts constitute gross negligence,
characterized by the want of even slight care, in reference to passing
the following Board Resolutions:

a. Resolution No. 2032 dated 3 November 1999, approving the award of the contract to [JD] Legaspi Construction;

b. Resolution No. 2057 dated 15 December 1999, covering the approval of the construction agreement;

c. Resolution No. 3017 dated 5 July 2000, approving Variation
Order No. l (later renumbered as Variation Order No. 2 under Resolution
No. 3102); and

d. Resolution No. 3102 dated 26 April 2001, approving the increase in the cost of Variation Order No. 2.[121]

The members of the Old PEA Board argue that preceding the
approval of Resolution No. 2032 dated November 3, 1999 is no less than
two Administrative Orders (Nos. 176 and 224) and a Presidential
Memorandum dated October 16, 1998 on prioritizing Boulevard 2000 as a
flagship project. They claim that as far back as September 28, 1998,
they simply directed the PEA Management to seek financing for the road
construction project; and on April 22, 1999, to request the Office of
the President for authority to conduct simplified public bidding, which
request was found meritorious and thus granted by the said Office.[122]

Even before the questioned award of the contract to JD Legaspi under
Board Resolution No. 2032 was passed, the members of the Old PEA Board,
under Resolution No. 2017 series of 1999, already approved a PHP 1
billion loan facility from LandBank/All Asia Capital. This was no more
and no less than an actual credit facility from LandBank set in place by
the members of the Old PEA Board for the funding of the PDMB Project,
among others, pursuant to the previous PEA Board’s own directive to PEA
Management to seek such financing as of one year before.[123]

Thus, they argue that when the PEA Management subsequently recommended
in its Memorandum dated October 21, 1999 containing the approval of the
award of the construction contract to JD Legaspi as the lowest complying
bidder under the simplified bidding process, there was no legal
obstacle to the transaction, especially considering that PEA had already
appropriated the contract amount against the LandBank loan of PHP 1
billion for the purpose of seeing the project through. Hence, the
members of the Old PEA Board believed in all good faith that the
necessary measures and requirements were in place and complied with, and
nothing criminal whatsoever attended their acts.[124]

With respect to Resolution No. 2057 dated December 15, 1999, the
approval of the construction agreement between PEA and JD Legaspi, as
the records would bear out, was based on the PEA Management Memorandum
dated December 14, 1999 recommending Board Approval of the contract.
Relying on good faith on this recommendation, the Old PEA Board approved
the proposed corporate measure. Subsequently, it likewise approved the
bridge financing of PHP 300 million under Board Resolution No. 2060,
series of 2000 as part of the PHP 1 billion loan package from LandBank.
As before, these were straightforward business decisions made by the Old
PEA Board as a policy-making body based on the facts laid out before it
by the PEA Management.[125]

As to Resolution No. 3017 dated July 5, 2000 approving Variation Order
No. 1 (later renumbered to Variation Order No. 2), the decision of the
Old PEA Board to pass the same was based on information provided by PEA
Management. As stated in the PEA Management’s Memorandum dated June 27,
2000, the Seaside Drive Extension and proposed bridge connecting Central
Business Park (CBP) II and CBP I B and C were necessary
components to complete the road construction project. The approval, as
contained in the Board Resolution, was also made expressly “subject to
existing accounting auditing rules and regulations and to the following
conditions, to wit:

a. Payment will be made only on actual quantities completed
based on the approved detailed plans and applicable unit bid prices and
agreement prices (on new items of work)

b. No time extensions will be associated on these additional works

c. Final approval of the Office of the President

d. Actual release of the loan proceeds from Land Bank.”[126]

As to Resolution No. 3102 dated April 26, 2001 on the updated
costs of the works covered by the original Variation No. 1 (renumbered
as Variation Order No. 2) based on the detailed plans in the total
amount of PHP 124,440,810.20, the same was also the subject of PEA
Management Memorandum dated March 21, 2001, recommending approval of the
updated costs. In approving the said Variation Order, the Old PEA
Board, in addition to the previous conditions it imposed under Board
Resolution No. 3017, further required that the implementation of
Variation Order No. 2 be made subject to the provisions of P.D. No.
1594, while the appropriation of the difference resulting from the
updated cost thereof must be made subject to existing accounting and
auditing rules and regulations.[127]

The members of the Old PEA Board further maintain that Section 86 of P.D. No. 1445[128]
merely requires that the certification as to availability of funds must
state that “the amount necessary to cover the proposed contract for the
current year is available for expenditure.” It does not require the
certification to state that funds are available for the entire project
when the same will encompass more than one fiscal year. They cite
Department of Justice Opinion No. 174, series of 1989, which states:

However, in cases where the term of the contract extends beyond
the year of its execution, such certification shall cover only the
portion pertaining to the current year. Stated differently, the law lose
(sic) not require in a multi-year contract that the certification of
available funds should likewise cover the period exceeding the year the
contract was executed.[129]

In the case at bar, the subject Construction Agreement, although
fixed for a period of 360 days, straddles two fiscal years, the contract
having been executed on April 10, 2000. The Certificate of Availability
of Funds in the amount of PHP 300 million was thus compliant with the
law and rules as the expected expenditures for the current fiscal year
at the time the contract was executed was not expected to exceed said
amount.[130]

Further,
while the introduction of works for the Seaside Drive Extension was not
included in the original contract, its addition was within the general
scope of the PDMB Project as bid and awarded. Said provision merely
requires that the scope of works in the proposed variation order must be
related to the same general scope of works in the original project as
bid and awarded. The scope of works in the construction of the Seaside
Drive Extension is similar to the works undertaken in the original
contract.[131]

Furthermore, they argue that payments were made after the approval of
National Economic and Development Authority, which was approved during
the term of the New PEA Board, and not of the Old PEA Board. Yet, the
Old PEA Board was held liable for the payment on costs which its members
had no knowledge of, had not reviewed and approved, and had absolutely
no control over.[132]

G.R. No. 220532

In their Petition, Beriña, Jr., Millan, Viray, and Zori1la averred that
the list of contractors submitted by the DPWH are contractors with
Inter-Agency classification of large “B” and license classification of
triple “AAA.” As such, they are necessarily accredited by the PCAB
because it is the body that accredits and classifies the licenses of
contractors.[133] By securing
the list of contractors from the DPWH for purposes of simplified public
bidding, PEA was assured that the contractors participating in the
simplified public bidding would be qualified and competent to undertake
the PDMB Project.[134]
Moreover, the splitting of the ten contractors for Package 1 and Package
2 of the PDMB Project is no proof that they were ill-motivated as they
did so precisely to avoid a single contractor winning both packages.[135]

Further, they explained that all the requirements for the detailed
engineering were done first hand, except for soils and foundation
investigation which were based on existing data from comparative areas,
particularly the SM segment, R1 Consortium segment, and actual test
conducted along Uniwide Coastal Mall.[136]
They also claimed that the bid document furnished to all prospective
bidders contained preliminary designs and studies based on comparative
data available for bidding purposes, hence, the need for the winning
bidder to validate said data.[137]

They add that PEA is a government-owned and controlled corporation that
generates its own funds from its operations, and is not dependent upon
Congress for funds. In the case of the PDMB Project, its funding was
made available through loans obtained by PEA for that purpose, which
incidentally have already been fully paid years ago. Thus, there was no
risk that PDMB Project would not be completed as a consequence of the
phasing of the project because PEA had its own assets, revenues, and
other sources of funding to pay, as it did, for the construction of the
project.[138]

Further,
P.D. No. 1594 does not limit the subject of a variation order only to
items that are included in the original contract as awarded. It allows a
contractor to be awarded a variation order in the form of an extra work
order for introducing work items that are not included in the original
contract, so long as the works are merely for the completion of the
project and the aggregate amount thereof does not exceed 25% of the
escalated original price.[139]
P.D. No. 1594 also allows a negotiated contract where a variation order
is adjacent or contiguous to an ongoing project and could be
economically prosecuted by the same contractor. From the ground and
aerial sketches, the Integrated Framework Plan and the present Google
image of the President Diosdado Macapagal Boulevard, the Seaside Drive
Extension as well as the Inland Channel Bridge are adjacent and/or
contiguous to JD Legaspi’s PDMB Project.[140]

They also argue that the acts found by the Sandiganbayan were merely
recommendatory in nature and subject to the approval of the PEA General
Manager and the Board of Directors. Thus, all the functions of the Ad Hoc
Committee, of which Beriña, Jr. and Viray were members; of the Planning
Task Force, of which Viray was Chairman with Zorilla and two other
engineers as members; and of the Construction Task Force of which Millan
was Project Director, Viray as Project Manager, Zorilla as Resident
Engineer and two other engineers as members — all involved in submitting
proposals and recommendations for the approval of the PEA General
Manager and Board of Directors.[141]

G.R. No. 220587

In his Petition, Legaspi argues that the Sandiganbayan arrived at a
conclusion of his overt act in the implied conspiracy for violation of
Section 3(e) of R.A. No. 3019 for suggesting, proposing, pushing for,
and submitting documents pertaining to the construction of the Seaside
Drive Extension as a Change Order based on the Sworn Affidavit dated
September 23, 2002 attached to Tuazon’s counter-affidavit, which the
Sandiganbayan took judicial notice of.[142]

Legaspi however claims that the Sandiganbayan contravened law and
jurisprudence in concluding that the aforesaid Sworn Affidavit was
admissible and may be taken judicial notice of considering that (i) it
was not formally offered by the prosecution or the defense; (ii) there
was no prior motion and hearing for its admission or judicial notice;
(iii) the affiant was never presented in court; and (iv) the Sworn
Affidavit is immaterial to the charges against him as it actually
pertained to the Bay Boulevard, a project unrelated, and different from,
the Seaside Drive Extension.[143]
Paragraph 4 of the Sworn Affidavit expressly states that it refers to
the “Bay Boulevard Project” and not to the Seaside Drive Extension
project, to wit:[144]

4. On 3 May 2001, JDLC submitted to PEA a proposal to do the Bay
Boulevard Project which is adjacent/contiguous to the Central Boulevard
Project and which is intended to connect Central Boulevard with Roxas
Boulevard. The PEA Management recommended to the PEA Board the approval
of this proposal sometime at the end of May 2001.[145]

The differences between these projects were further outlined by Legaspi as follows:[146]

Disparities
Subject of Conviction
Subject of Sworn Affidavit
Names
Seaside Drive Extension
Bay Boulevard
Locations
Connects to NAIA Road
Connects to Buendia Avenue (now Gil Puyat Ave.), 3,820 meters from the Seaside Drive Extension
Contract Costs
P57,598,301.10
P281,703,812.93
Date of Proposal
PEA Management Memorandum to the
Board, recommended approval of Seaside Drive Extension on June 27, 2000;
PEA Board approved the Seaside Drive Extension on July 5, 2000, via
Board Resolution No. 3017
According to paragraph 4 of the Sworn Affidavit:

Alleged proposal was submitted on May 3, 2001, about a year after the Seaside Drive Extension was already approved.[147]

Legaspi likewise argues that the proposal, which he allegedly made,
was neither charged in the Information nor put in issue during trial.
Otherwise, Legaspi or the other accused would have been given the
opportunity to present evidence to the contrary. He cited that Beriña,
Jr. admitted in his Memorandum dated June 27, 2000 that he was the one
who requested for the approval of the Seaside Drive Extension, as it
would “facilitate the flow of traffic at the Seaside Drive Extension,”
and that “it is deemed necessary to complete the construction of the
proposed Seaside Drive Extension (connecting Roxas [Boulevard] and
Central [Boulevard])…” This was never rebutted by the prosecution.[148]
Furthermore, Millan himself admitted that while JD Legaspi’s firm was
in the process of designing the PDMB Project, there was also an
instruction from the PEA Management to include the Seaside Drive
Extension and the bridge.[149]

Legaspi added that it was then President Estrada himself who
directed that the “road project including appurtenances be completed on
or before April 2001.”[150]
This was stated in the letter dated May 3, 2000 of Carlos P. Doble, as
former PEA General Manager, to Legaspi. Pursuant to then President
Estrada’s directive, PEA requested the submission of quotations for, inter alia,
the construction of the Seaside Drive Extension and the Bay, Boulevard.
Clearly, it was PEA Management, through Doble, which initiated and
pushed for the construction of the Seaside Drive Extension.[151]

Legaspi further claimed that in the subject criminal information, he
and the other accused were charged with “approving/allowing several
improper variation/change orders and overruns to be implemented without
the requisite presidential approval and the appropriate funds” and
“allowing and paying or causing the allowance and payment of several
claims of Legaspi for variation orders, overruns, and other claims even
when the same were clearly improper, illegal and without the requisite
presidential approval, thereby paving the way for Legaspi to claim and
receive undue payments from the Government totaling millions of pesos in
overprice.”[152] However, he
was convicted for pushing, suggesting, and proposing the award and
implementation of the Seaside Drive Extension, which was void for not
being part of the original project as bid and awarded to him, and not
for implementing the Seaside Drive Extension despite the lack of a
Notice to Proceed and Office of the President’s approval, and for
submitting the Variation Order for the Seaside Drive Extension to the
Board a mere 78 days after the Construction Agreement was signed.[153] He then cited the case of Burgos v. Sandiganbayan,
where there was a stark variance between the allegation in the
information and proof adduced during trial with respect to the means of
committing violation of Section 3(e) of R.A. No. 3019, as in this case,
that Legaspi spearheaded the implementation of the Seaside Drive
Extension, and that said road cannot be awarded through a variation
order. However, Legaspi was charged in the Information with implementing
the variation orders and overruns despite lack of approval from the
Office of the President.[154]

Legaspi adds that it was pursuant to Memorandum Circular No. 25 issued
on February 10, 1999, which served as a basis for the requirement of
presidential approval, and prompted then Executive Secretary Zamora to
require all extra works and price adjustments to be submitted to the
president. It requires that the project must have been awarded and
approved by the head of the agency. Thus, the approval of the president
will only be sought after the Head of the Procuring Entity, which is the
PEA Board, has signed its approval for the project. Beriña, Jr. and
Millan were thus not required by law or by the terms of the contract to
await prior presidential approval before recommending the award of the
Seaside Drive Extension to Legaspi.[155]

He adds that no presidential approval was required for the
implementation of the works under Variation Order No. 2 because
Executive Order No. 109, issued on May 27, 2002, removed the requirement
of presidential approval when it expressly repealed Memorandum Circular
No. 25. Due to the express repeal of Memorandum Circular No. 25, the
approval of the Variation Orders shall be governed by the provisions of
P.D. No. 1594. Section 1, CI-3, Chapter III thereof provides that “Under
no circumstances shall a contractor proceed to commence work under any
Change Order, Extra Work Order or Supplemental Agreement unless it has
been approved by the Secretary or his duly authorized representative.”
Thus, he argues that upon the effectivity of Executive Order No. 109 on
May 27, 2002, the approval of the President was no longer necessary for
the implementation of Variation Order No. 2.[156]

Consolidated Comment

In its Consolidated Comment[157]
dated June 15, 2017, the Office of the Special Prosecutor argued that
the petitions filed by Lacson and the members of the Old PEA Board
failed to indicate the material dates of their receipt of the notice of
the assailed February 5, 2015 Decision in violation of Sections 4(b) and
5 of Rule 45 of the Revised Rules of Court.[158] They also argue that the petitioners’ call for the re-examination of the factual findings of the court a quo are thus improper in an appeal by certiorari under Rule 45 of the Rules of Court.[159]

They add that the pre-requisite presidential approval was expressly
mentioned in the Memorandum dated January 29, 2000 issued by then
Executive Secretary Zamora and was expressly carried over to the
Construction Agreement signed on April 10, 2000 which contained
provisions embodying the conditions that “adjustment of contract price
due to escalation shall be effected in accordance with P.D. No. 1594 and
its IRR, upon written agreement of the parties and subject to
availability of funds” and “changes in the schedule and work required
shall be made…upon the written consent of the parties… and approval
of the President.” In this case, the variations and changes have all
reached the implementation stage albeit the absence of such presidential
approval.[160]

While Executive Order No. 109 expressly repealed Memorandum
Circular No. 25, the required presidential approval, did not do away
with the necessary clearance from the president for the following
reasons: (a) Executive Order No. 109 speaks of government contracts, not
contract price adjustments; (6) Variation Order No. 2 was processed for
approval even before Executive Order No. 109 came into effect. The PDMB
was inaugurated on April 5, 2002 whereas Executive Order No. 109 was
issued only on May 27, 2002; (c) The Office of the President’s
Memorandum dated January 29, 2000, which approved the Construction
Agreement, subject to certain conditions, expressly states that all
extra works and price adjustments should first be submitted to the
president for approval; and (d) Article 8 of the Construction Agreement,
which is the law between the parties, expressly requires presidential
approval for any change order and/or additional work.[161]

They also argue that simplified public bidding dispenses only with the
requirements of publication/advertisement and posting. It does not
include an authority for the Bids and Awards Committee or any Ad Hoc
Committee for that matter to secure the list of qualified
contractor-bidders from other organizations, or any other government
agency. Thus, when PEA’s Ad Hoc Committee, of which petitioners
are members, obtained the list from DPWH Special Buildings Project
Management Office, whose area of responsibility was vertical
construction buildings, it blatantly violated the law.[162]

Further, the members of the Ad Hoc
Committee doubly violated the rules of procurement when they
arbitrarily divided the list of accredited contractor-bidders into two
groups, one group to bid in Package 1, and another to bid in Package 2.
This situation resulted in the award of the project to JD Legaspi, to
the disadvantage of contractors in the second set of the DPWH list and
those contractors who are PCAB-accredited but were not included in the
DPWH list.[163]

There was also no actual soil boring test conducted on the
site to be developed. As a result, the estimates in the detailed
engineering was not based on the actual conditions of the site to be
developed but was drawn from an assumption of available data from the
adjacent areas.[164]

The Bid Plans and even the approved agency estimate, by themselves, do
not prove that a detailed engineering and survey had been conducted. The
prosecution has shown that no other documentation of the alleged ‘ I
engineering plan exists so much so that the said bid plans and agency
estimates become questionable for having no basis at all.[165]

Further, there were no sufficient funds when the project was bid out and awarded to JD Legaspi.[166]
The best evidence of the sufficiency of funds for the project would
have been a document or testimony from the Landbank/All Asia Capital,
confirming the approval of the PHP 1 billion loan facility. However, the
best that they could muster was a Certification dated May 3, 2000
issued by LandBank’s Assistant Vice President, confirming that the PEA
had a PHP 300 million short term loan line facility.[167]

The Office of the Special Prosecutor maintains that the construction of
the Seaside Drive Extension was illegal. Geographically, the Seaside
Drive Extension is located outside the roadway plan for the PDMB
project. On the other hand, the Inland Channel Bridge is located along
the stretch of the project and necessary to connect two segments of the
road separated by a creek. These additional works are both the subject
of Variation Order No. 2[168] which was approved despite the illegality of the construction of the Seaside Drive Extension.

Petitioners thereafter filed their corresponding Reply,[169] reiterating their positions.

This Court’s Ruling

We shall first address the procedural issues raised by the Office of the Special Prosecutor.

Contrary to its claim that the members of the Old PEA Board failed to
indicate the date of receipt of the assailed Decision, a reading of the
Joint Petition would show that they made an allegation that the
Sandiganbayan read the dispositive portion of the assailed Decision in
open court.[170] Necessarily,
the date when the Sandiganbayan read the dispositive portion of its
Decision that was promulgated on February 5, 2015, is also the date when
they received the aforesaid decision. They thereafter filed a motion
for reconsideration within the 15-day period, and stated in their Joint
Petition the date when they respectively received the Joint Resolution
denying their motion for reconsideration. As alleged:

11.1 On 28 September 2015, Petitioners Padilla and Dayan were
separately served copies of the Joint Resolution through their
respective counsels.

11.2 On 30 September 2015, Petitioners Chan, Damaso and San Juan were separately served copies of the Joint Resolution through their respective counsels.[171] (Emphasis in the original)

Lacson, also made the following narration:

From the date of receipt by petitioner of the Joint Resolution
on September 28, 2015 denying his motion for reconsideration, he filed a
Motion for Extension of Time to file a Petition for Review on [Certiorari] seeking for a Thirty (30) days on October 9, 2015, or up to and until November 12, 2015.[172] (Emphasis supplied)

It must be remembered that the purpose of requiring the date of
receipt of the assailed decision and resolution in a petition is to
determine its timeliness. In this case, the dates described by
petitioners were sufficient for this Court to determine that the
petition was indeed filed on time.

The Office of the Special
Prosecutor also assails the allegations of petitioners claiming that
they failed to comply with the requirement under Rule 45 of the Rules of
Court for which only questions of law may be raised.

A question
of law arises when there is doubt as to what the law is on a certain
state of facts, while there is a question of fact when the doubt arises
as to the truth or falsity of the alleged facts.[173]
In this case, the actions taken by petitioners and how the PDMB Project
was awarded to JD Legaspi was no longer disputed. Rather, it is the
applicability of the provisions of the law that were cited by the
Sandiganbayan, ultimately concluding a violation of Section 3(e) of R.A.
No. 3019, upon which the issues raised by petitioners revolved.

Further, as a rule, findings of fact of the Sandiganbayan, as a trial
court, are accorded great weight and respect. However, in cases where
there is a misappreciation of facts, this Court will not hesitate to
reverse the conclusions reached by the trial court. At all times, this
Court must be satisfied that in convicting the accused, the factual
findings and conclusions of the trial court meet the exacting standard
of proof beyond reasonable doubt. Otherwise, the presumption of
innocence must be favored, and exoneration must be granted as a matter
of right.[174] As such, the
instant case must be carefully scrutinized to ensure that indeed, the
exacting standard of proof beyond reasonable doubt has been met.

Now on the merits.

The Sandiganbayan summarized its basis for convicting petitioners for violation of R.A. No. 3019 as follows:
  1. Violating the simplified bidding rules because they shortlisted bidders not based on the PCAB master list;
  2. Conducting the bidding and recommending the award to accused
    Legaspi without detailed engineering in violation of P.D. 1594 and
    without the required appropriation and actual availability of funds for
    the total contract price;

  3. Creating and confirming the artificial phases in the Construction
    Agreement and dividing the contract into Phase I and Phase II just to
    enable PEA to circumvent the requirement under P.D. No. 1445 about
    funding requirements. In the case of Mortel. . .

  4. In the case of accused Beriña[, Jr.] and Millan, recommending the
    approval of Variation Order No. 2 and the contract price adjustment, and
    the payment thereof without the required presidential approval and in
    violation of P.D. No. 1594;

  5. In the case of San Juan, Chan, Dayan, Malbarosa, Padilla and
    Damaso, for approving and confirming the Legaspi contract without
    sufficient funding and the Seaside Drive Extension without public
    bidding;

  6. In the case of Legaspi, for conspiring with Beriña[, Jr.] and
    Millan in having the Seaside Drive Extension contract awarded to him
    under a negotiated contract.[175]

At the outset, it must be clarified that a violation of the law and
rules of procurement does not automatically equate to a violation of
R.A. No. 3019. As explained in Sabaldan v. Office of the Ombudsman:[176]

[E]ven granting that there may be violations of the applicable
procurement laws, the same does not mean that the elements of violation
of Section 3(e) of R.A. No. 3019 are already present as a matter of
course. For there to be a violation under Section 3(c) of R.A. No. 3019
based on a breach of applicable procurement laws, one cannot solely rely
on the mere fact that a violation of procurement laws has been
committed. It must be shown that (1) the violation of procurement laws
caused undue injury to any party or gave any private patty unwarranted
benefits, advantage or preference; and (2) the accused acted with
evident bad faith, manifest partiality, or gross inexcusable negligence.[177]

Thus, despite findings for violation of the procurement law, it is
the elements comprising R.A. No. 3019 that must be materially proven,
especially that an information charges a criminal offense, as defined by
R.A. No. 3019, and not by P.D. No. 1594 or R.A. No. 9184.[178] These elements were further elaborated in Chung v. Ombudsman[179] as follows:

By the very language of Section 3, paragraph (e) of RA 3019, which
defines “corrupt practices of public officers,” the elements of
manifest partiality, evident bad faith, and gross inexcusable negligence
and of giving unwarranted benefit, advantage or preference to another
must go hand in hand with a showing of fraudulent intent and corrupt
motives.

Evident bad faith “does not simply connote bad judgment or
negligence” but of having a “palpably and patently fraudulent and
dishonest purpose to do moral obliquity or conscious wrongdoing for some
perverse motive or ill will. It contemplates a state of mind
affirmatively operating with furtive design or with some motive or
self-interest or ill will or for ulterior purposes.”

Manifest partiality, on the other hand, is defined as a clear,
notorious, or plain inclination or predilection to favor one side or
person rather than another, while gross inexcusable negligence is
defined as negligence characterized by the want of even the slightest
care. It presupposes acting or omitting to act in a situation where
there is a duty to act, not inadvertently but willfully and
intentionally, with conscious indifference to consequences insofar as
other persons may be affected.[180] (Citations omitted)

Guided by the foregoing, the acts found by the Sandiganbayan that led to the conviction of petitioners must be re-examined.

DPWH list versus PCAB Masterlist

In holding that petitioners violated the rules on simplified public
bidding, the Sandiganbayan relied on the IRR of P.D. No. 1594 as
amended,[181] stating that
there is an obligation on the part of the PEA to consult the separate
list of the PCAB before the negotiated bidding of the PDMB Project could
proceed. The provision reads:

a. Participation in simplified public bidding for a project shall be limited to bona fide
contractors duly accredited and classified for the project category and
size and who are included in a separate master list to be prepared by
the Philippine Contractors Accreditation Board (PCAB) pursuant to
the uniform guidelines promulgated by the PCAB. The guidelines shall
put emphasis on strict requirements of good track record performance
and/or capability requirements, among others.

On his part, Lacson, a member of the Ad Hoc Committee,
explained that Atty. Enriquez had reported that the “separate
masterlist” that was supposed to be prepared by the PCAB was not yet
available then. Instead, he was furnished by the PCAB with a copy of a
general masterlist in the NCR containing hundreds of listed contractors
with their respective PCAB category/license.[182]
The problem then became how to narrow down the list of pre-qualified
bidders to achieve the objective of conducting a “simplified bidding” as
approved by the Office of the President. To use the general masterlist
obtained by Atty. Enriquez could be unwieldy and militate against the
presidential instructions to immediately have the PDMB Project available
to the public. Hence, the Chairman of the Ad Hoc Committee
decided to seek the help of the DPWH for a list of PCAB contractors with
large “B,” triple “AAA” category/license for roads and bridges since
this is the nature of the PDMB Project.[183]

On this issue, we rule in favor of petitioners.

Notably, the prosecution did not present evidence showing that a
separate masterlist, from which contractors of projects for simplified
public bidding must be chosen from, is available. To continuously
require PEA to rely on a separate masterlist that is not yet in
existence would be to punish petitioners for an inherently impossible
task, which cannot even be attributed as their fault. It was not the
obligation of PEA to produce the masterlist; rather, the responsibility
fell upon the PCAB to do so. Before PEA may be accused of its failure to
comply with an obligation imposed by law, it must first be shown that
such an obligation is capable of being performed. This is especially
true in this case where the obligation of PEA is conditioned upon the
fulfillment of the obligation of PCAB. As such, it is not simply the
obligation imposed by law that must be examined; the corresponding
obligation upon which its performance is made dependent, should also be
taken into consideration. It is thus necessary to first establish that a
separate masterlist of bona fide contractors duly accredited and
classified for the project category, indeed exists. This is in line
with the rule on burden of proof, which imposes upon the prosecution the
burden of proving its allegations. A negative fact such as the absence
of the masterlist, cannot serve as a basis for a wrongdoing, when the
prosecution itself has not first presented proof of its existence. This
flows from the maxim “semper necessitas probandi incumbit illi qui agit,” or the necessity of proof always lies with the person who lays the charges.

In the absence of a separate masterlist, PEA was left with an
alternative to consult the list of DPWH with large “B” and triple “AAA”
category/license for roads and bridges. For sure, these are the largest
in the categorization of the DPWH and among the top tier in the
classification of contractors. These are the lists of contractors with
experience to build roads and bridges.

As of November 22, 2017,
in the Board Resolution No. 201 Series of 2017 issued by PCAB, Category
AAA was defined as those contractors with minimum financial capacity of
PHP 180 million, while Category AAAA are those with minimum financial
capacity of PHP 1 billion. Those with a size range of Large B with
License Category AAA and AAAA are those with single largest project of
above PHP 225 million and allowable range of contract costs of less than
or above PHP 450 million. Notably, the amount allotted for the PDMB
Project, which is PHP 584,365,885.00, falls within the range of Category
AAA and Large B contractor. The actions taken by the PEA must thus be
treated as substantial compliance with the requirement of the law
considering the absence of the separate masterlist and taking into
consideration Section 3(b) of P.D. No. 1594, which reads:

(b) Technical Requirements. The prospective contractor must meet
the following technical requirements to be established in accordance
with the rules and regulations to be promulgated pursuant to Section 12
of this Decree, to enable him to satisfactorily prosecute the subject
project:

1) Competence and experience of the contractor in managing projects similar to the subject project.

2) Competence and experience of the contractor’s key personnel to be assigned to the subject project.

3) Availability and commitment of the contractor’s equipment to be used for the subject project.

Nowhere from the evidence presented by the prosecution was it shown
that JD Legaspi or any of the bidders was unqualified or had no
competence to undertake the PDMB Project because the PEA relied on the
DPWH list. On the contrary, the winning bidder, JD Legaspi, was able to
perform his part of the contract. As PEA was merely performing its
mandate, it cannot take the blame for the shortcoming committed by
another agency. The circumstances that led to PEA’s action in utilizing
the DPWH therefore negates the presence of manifest partiality, evident
bad faith or gross inexcusable negligence under Section 3(e) of R.A. No.
3019.

In the same manner, as there was no list prepared by
PCAB, there were also no guidelines as to how the project could be bid
out. While the Sandiganbayan found that when PEA divided the PDMB
Project into Phase I and Phase II, and respectively divided the ten
contractors under these two phases, those under Phase II were
disadvantaged because of the option given to the SM group and R1
Consortium to build on the land they were awarded, which was covered by
the Phase II, there was no sufficient proof to show that the PEA made
this to accommodate any of the contractors listed for Phase I. It was
not even shown by the prosecution that the bid of the contractors under
Phase II could match the lowest complying bid of JD Legaspi under Phase
I. A bidding was still conducted by the PEA for the Phase I Project,
which included different participants. Thus, it could not be said that
JD Legaspi was given an unwarranted preference in the award of the
project.

Detailed engineering

The Sandiganbayan also found
that the absence of a detailed engineering affected the cost estimate
of the project. With this, the cost adjustments that had to be done in
order to pursue the project became bloated.

A reading of the
pleadings made available before this Court would show that petitioners
did not deny the absence of a detailed engineering for the PDMB Project.
Rather, what was taken into consideration was the condition of the
adjacent land, which was awarded to the other contractors as part of the
PDMB Project.

This contravenes Section 2 of P.D. No. 1594, which reads:

Section 2. Detailed Engineering. No bidding and/or
award of contract for a construction project shall be made unless the
detailed engineering investigations, surveys, and designs for the
project have been sufficiently carried out in accordance with the
standards and specifications to be established under the rules and
regulations to be promulgated pursuant to Section 12 of this Decree so
as to minimize quantity and cost overruns and underruns, change orders
and extra work orders, and unless the detailed engineering documents
have been approved by the Minister of Public Works, Transportation and
Communications, the Minister of Public Highways, or the Minister of
Energy, as the case may be. (Emphasis in the original)

Section 2 of P.D. No. 1594 requires that a detailed engineering be
carried out before any bidding or contract is awarded for a construction
project. Obviously, this requirement is addressed to the agency
concerned, not to a bidder. It is from this detailed engineering that
the concerned agency can get an estimate of the project, which it will
then use as basis in the evaluation of the bids.[184]

As mentioned, the PEA, in coming up with its Agency Budget Estimate,
merely relied on the conditions of the adjacent land, which should not
be the case. The responsibility on the preparation of the bid documents
falls upon the members of the Ad Hoc Committee, who was tasked to evaluate the condition of the road before the same could be bid out.

Nevertheless, violation of this provision alone, without clear showing
of bad faith, malice, or gross negligence should not be automatically
equated to a violation of Section 3(e) of R.A. No. 3019. There must be
proof amounting to a corrupt motive in doing so, for as explained in Martel v. People:[185]

At this juncture, the Court emphasizes the spirit that animates
R.A. 3019. As its title implies, and as what can be gleaned from the
deliberations of Congress, R.A. 3019 was crafted as an anti-graft and
corruption measure. At the heart of the acts punishable under R.A. 3019
is corruption. As explained by one of the sponsors of the law,
Senator Arturo M. Tolentino, “while we are trying to penalize, the main
idea of the bill is graft and corrupt practices. x x x Well, the idea of
graft is the one emphasized.” Graft entails the acquisition of gain in dishonest ways.[186] (Emphasis in the original; citations omitted)

At the most, the absence of a detailed engineering could affect the
budget or cost for which government must spend for the completion of the
project. Overpricing should however be proven to have been committed
with deliberate corrupt ways before one can be indicted for violation of
R.A. No. 3019. As held in Macairan v. People:[187]

Jurisprudence teaches that in assessing whether there was
overpricing, a specific comparison with the same brand, features and
specifications as those purchased in the questioned transaction should
be made. Further, the report upon which the proof of overpricing is
based should include a canvass of the different suppliers of the
identical product with their corresponding prices. Absent this evidence,
the Court cannot reasonably conclude that the price of the goods
subject of the questioned transaction was actually exorbitant.[188] (Citations omitted)

In this case, the Special Audit Report of the COA found that there
was no overpricing in the portion of the contract awarded to Legaspi.
Its findings stated the following:

Source of Fund

The contract with J.D. Legaspi Construction amounting to
P584,365,885.00 was further increased to P837,317,343.77 due to contract
price adjustments, variation orders, overrun/underrun and supplemental
agreement. The funding source was the P300 Million loan with Land Bank
of the Philippines, which was released on April 7, 2000, and the P1
Billion loan from the Government Service Insurance System of which the
initial drawdown amounting to P600 Million was released on August 15,
2002.

. . . .

Summary of Audit Findings

Finding No. 1

The technical evaluation of the project shows that the total
project cost, including the price adjustment was found to be reasonable
and, therefore, not overpriced. The project was constructed in
accordance with the approved design, scope of work and as-built plans
and specifications.

The allegation of overpricing raised in the complaint of Mr.
Sulpicio Tagud, Director, Public Estates Authority (PEA), based on the
cost comparison per linear meter of road and bridge constructed by three
(3) developers/contractors, appears to be untenable. The road networks
undertaken by the three (3) developers/contractors are not comparable
considering that Central Business Park (CBP) I-A, CBP I-B & C
(reclaimed by SM/R-1 Consortium) were reclaimed by
pre-loading/surcharging method to attain the required soil consolidation
and stability. On the other hand, Financial Center Area (FCA), CBP-2
and Asiaworld area are existing reclaimed areas prior to the 1988 Manila
Cavite Coastal Road and Reclamation Project (MCCRRP) Master Development
which have poor subgrade materials as confirmed by the Bureau of
Research and Standards (BRS) and the R.R. Ignacio Construction as shown
in the results of the Borehole tests conducted in November of 1999.
Logically, the actual cost per linear meter incurred by the SM Group and
R1 Construction as against the cost incurred by J.D. Legaspi
Construction cannot be compared because the areas assigned for each of
these contractors are with different soil conditions requiring different
design for each project.

The technical evaluation conducted has clearly established the
reasonableness of the project cost. The audit team, therefore, finds no
sufficient basis to support the allegation of overpricing.[189]

Considering that the COA, the constitutionally bound auditor of
government funds, declared that no overpricing occurred, such findings
should be given considerable weight. This further shows that no injury
was proven to have been caused to the government; neither any manifest
partiality in favor of a party was given. As part of the elements of
violation of R.A. No. 3019, failure to prove these would be tantamount
to a failure to prove violation of the law, beyond reasonable doubt.

The requirement of availability of funds

With respect to the availability of funds, Section 86 of P.D. No. 1445 provides:

SECTION 86. Certificate Showing Appropriation to Meet Contract.
— Except in the case of a contract. for personal service, for supplies
for current consumption or to be carried in stock not exceeding the
estimated consumption for three months, or banking transactions of
government-owned or controlled banks no contract involving the
expenditure of public funds by any government agency shall be entered
into or authorized unless the proper accounting official of the agency
concerned shall have certified to the officer entering into the
obligation that funds have been duly appropriated for the purpose and
that the amount necessary to cover the proposed contract for the current fiscal year is available for expenditure on account thereof,
subject to verification by the auditor concerned. The certificate
signed by the proper accounting official and the auditor who verified
it, shall be attached to and become an integral part of the proposed
contract, and the sum so certified shall not thereafter be available for
expenditure for any other purpose until the obligation of the
government agency concerned under the contract is fully extinguished.
(Emphasis supplied)

The foregoing provision requires that the appropriation necessary
in order to consider a contract as sufficiently funded must cover that
portion of the needed expenditures for the particular current year.
Necessarily, when a contract transcends beyond a period of one year, and
must be completed within a multi-year period, the availability of
appropriations must be examined for each of the current fiscal year that
arrives. This does not however mean that the implementing agency should
look for funds only when the current fiscal year arrives. Rather, the
source from which the funding for the entire project must already be
determined, for while the actual release of funds may be made on a
yearly basis, continuous payment to a contractor on a multi-year project
could only be made if the source of funds has already been determined.
This is supported by R.A. No. 9184 which requires that the invitation to
bid identify the source of fund of the project, thus:

SEC. 21. Advertising and Contents of the Invitation to Bid.
– In line with the principle of transparency and competitiveness, all
Invitations to Bid for contracts under competitive bidding shall be
advertised by the Procuring Entity in such manner and for such length of
time as may be necessary under the circumstances, in order to ensure
the widest possible dissemination thereof, such as, but not limited to,
posting in the Procuring Entity’s premises, in newspapers of general
circulation, the G-EPS and the website of the Procuring Entity, if
available. The details and mechanics of implementation shall be provided
in the IRR to be promulgated under this Act.

The Invitation to Bid shall contain, among others:

(a) A brief description of the subject matter of the Procurement;
(b) A general statement on the criteria to be used by the
Procuring Entity for the eligibility check, the short listing of
prospective bidders, in the case of the Procurement of Consulting
Services, the examination and evaluation of Bids, and
post-qualification;

(c) The date, time and place of the deadline for the submission
and receipt of the eligibility requirements, the pre-bid conference if
any, the submission and receipt of bids, and the opening of bids;

(d) The Approved Budget for the Contract to be bid;

(e) The source of funds;

(f) The period of availability of the Bidding Documents, and the place where these may be secured;
(g) The contract duration; and,
(h) Such other necessary information deemed relevant by the Procuring Entity. (Emphasis supplied)

In the case of projects funded by the national budget, it is even
required for the agency to secure a multi-year obligational authority to
secure its commitment of paying the multi-year project and ultimately
complete the project. This was explained in Jacomille v. Abaya[190] as follows:

MYOA or Multi-Year Obligational Authority is an authorization
document issued by the DBM to government agencies that undertake MYP
with funding requirements spread over two (2) years or more. Such
projects are evidenced by MYC entered into by the parties. In GAA 2013,
the requirement of MYOA is stated as follows:

Sec. 21. Contracting Multi-Year Projects. In the
implementation of multi-year projects where the total cost is not
provided in this Act, department, bureaus and offices shall request the
DBM for the issuance of a Multi-Year Obligational Authority following
the guidelines under DBM Circular Letter No. 2004-12 dated October 27,
2004. Notwithstanding the issuance of a Multi-Year Obligation Authority,
the obligation to be incurred in any given year, shall in no case
exceed the allotment released for the purpose during the year.

As early as October 27, 2004, the DBM issued the DBM Circular No.
2004-12 to prescribe the guidelines and procedure to implement the MYOA
requirement. The circular defines the different terms affecting MYOA,
such as:

3.1 Multi-Year Obligational Authority (MYOA) – refers to
an authority issued by the Department of Budget and Management (DBM) to
enable an agency to enter into a multi-year contract whether for locally
funded projects (LFPs) or foreign assisted projects (FAPs).

. . . .

The DBM explained the nature of MYOA. When the government entered
into MYC, it was committed to annually pay a given amount to the
contractor/supplier of the project, even without the government planning
for its payment. Thus, the imperative for MYOA arose, which gave an
assurance that the financial commitments included in MYC are considered
in the succeeding proposed budget submitted to Congress. With the
issuance of MYOA, the DBM commits to recommend to Congress the funding
of the MYP until its completion. Evidently, without MYOA, the government
runs the risk of breach of contractual obligations if its financial
commitments are not met for lack of funding.[191] (Emphasis in the original)

The absence of a multi-year obligational authority would ultimately result in a void contract, as applied in COMELEC v. Quijano-Padilla,[192] as follows:

Extant on the record is the fact that the VRIS Project was awarded
to PHOTOKINA on account of its bid in the amount of P6.588 Billion
Pesos. However, under Republic Act No. 8760, the only fund appropriated
for the project was P1 Billion Pesos and under the Certification of
Available Funds (CAF) only P1.2 Billion Pesos was available. Clearly,
the amount appropriated is insufficient to cover the cost of the entire
VRIS Project. There is no way that the COMELEC could enter into a
contract with PHOTOKINA whose accepted bid was way beyond the amount
appropriated by law for the project. This being the case, the BAC should
have rejected the bid for being excessive or should have withdrawn the
Notice of Award on the ground that in the eyes of the law, the same is
null and void.

The objections of then Chairman Demetriou to the implementation of
the VRIS Project, ardently carried on by her successor Chairman
Benipayo, are therefore in order.

Even the draft contract submitted by Commissioner Sadain, that
provides for a contract price in the amount of P1.2 Billion Pesos is
unacceptable. Indeed, we share the observation of former Chairman
Demetriou that it circumvents the statutory requirements on government
contracts. While the contract price under the draft contract is only
P1.2 Billion and, thus, within the certified available funds, the same
covers only Phase 1 of the VRIS Project, i.e., the issuance of
identification cards for only 1,000,000 voters in specified areas. In
effect, the implementation of the VRIS Project will be “segmented” or
“chopped” into several phases. Not only is such arrangement disallowed
by our budgetary laws and practices, it is also disadvantageous to the
COMELEC because of the uncertainty that will loom over its modernization
project for an indefinite period of time. Should Congress fail to
appropriate the amount necessary for the completion of the entire
project, what good will the accomplished Phase I serve? As expected, the
project failed “to sell” with the Department of Budget and Management.
Thus, Secretary Benjamin Diokno, per his letter of December 1, 2000,
declined the COMELEC’s request for the issuance of the Notice of Cash
Availability (NCA) and a multi-year obligational authority to assume
payment of the total VRIS Project for lack of legal basis. Corollarily,
under Section 33 of R.A. No. 8760, no agency shall enter into a
multi-year contract without a multi-year obligational authority, thus:

“SECTION 33. Contracting Multi-Year Projects. – In the
implementation of multi-year projects, no agency shall enter into a
multi-year contract without a multi-year Obligational Authority issued
by the Department of Budget and Management for the purpose.
Notwithstanding the issuance of the multi-year Obligational Authority,
the obligation to be incurred in any given calendar year, shall in no
case exceed the amount programmed for implementation during said
calendar year.”

Petitioners are justified in refusing to formalize the contract
with PHOTOKINA. Prudence dictated them not to enter into a contract not
backed up by sufficient appropriation and available funds. Definitely,
to act otherwise would be a futile exercise for the contract would
inevitably suffer the vice of nullity. In [Osmeña vs. Commission on Audit,] this Court held:

“The Auditing Code of the Philippines (P.D. 1445) further
provides that no contract involving the expenditure of public funds
shall be entered into unless there is an appropriation therefor and the
proper accounting official of the agency concerned shall have certified
to the officer entering into the obligation that funds have been
duly appropriated for the purpose and the amount necessary to cover the
proposed contract for the current fiscal year is available for
expenditure on account thereof.
Any contract entered into contrary to the foregoing requirements shall be VOID.

“Clearly then, the contract entered into by the former Mayor
Duterte was void from the very beginning since the agreed cost for the
project (P8,368,920.00) was way beyond the appropriated amount
(P5,419,180.00) as certified by the City Treasurer. Hence, the contract
was properly declared void and unenforceable in COA’s 2nd Indorsement,
dated September 4, 1986. The COA declared and we agree, that:

‘The prohibition contained in Sec. 85 of PD 1445 (Government
Auditing Code) is explicit and mandatory. Fund availability is, as it
has always been, an indispensable prerequisite to the execution of any
government contract involving the expenditure of public funds by all
government agencies at all levels. Such contracts are not to be
considered as final or binding unless such a certification as to funds
availability is issued (Letter of Instruction No. 767, s. 1978).
Antecedent of advance appropriation is thus essential to government
liability on contracts ([Zobel vs. City of Manila,] 47 Phil.
169). This contract being violative of the legal requirements
aforequoted, the same contravenes Sec. 85 of PD 1445 and is null and
void by virtue of Sec. 87.”‘[193] (Emphasis in the original, citations omitted)

It is thus important to have an assurance that the funding of the
project will continue. This assumes more significance when the budget is
part of the national budget every year.

In this case however,
the PDMB Project was not funded by the national budget. Rather, it was
funded by a loan to be obtained, which was authorized by the PEA Board
as early as October 4, 1999, when Resolution No. 2017 was issued
approving the One Billion Loan Facility in the Form of Convertible Notes
to Finance the Construction and Development of portions of the Central
Boulevard,[194] pertinent portion of which reads as follows:

RESOLVED FURTHER, that the following items are likewise approved, to wit:

  1. The Term Sheet covering One Billion Pesos Loan Facility which
    will be in the form of Convertible Notes herein attached as Annex “A”
  2. The appointment of Land Bank of the Philippines (LBP) as
    Trustee of the Mortgage Trust Indenture under the terms and conditions
    as contained in their proposal herein attached as Annex “B”
  3. The appointment of the law firm Picazo Buyco Tan Fider and
    Santos as legal counsel for this undertaking under the terms of their
    proposal herein attached as Annex “C”
  4. The extension of the mandate of Land Bank and All Asia Capital
    with regards to this undertaking for a period of six months; and
  5. The interim loan of Three Hundred Million Pesos to be sourced
    from Land Bank against the One Billion Facility under such terms and
    conditions as may be agreed upon.[195]

The authority to contract loan is authorized under the charter of PEA, being a government instrumentality. In Republic v. City of Parañaque,[196] the nature of PEA, later renamed as PRA, was described as follows:

In the case at bench, PRA is not a GOCC because it is neither a
stock nor a non-stock corporation. It cannot be considered as a stock
corporation because although it has a capital stock divided into no par
value shares as provided in Section 7 of P.D. No. 1084, it is not
authorized to distribute dividends, surplus allotments or profits to
stockholders. There is no provision whatsoever in P.D. No. 1084 or in
any of the subsequent executive issuances pertaining to PRA,
particularly, E.O. No. 525, E.O. No. 654 and EO No. 798 that authorizes
PRA to distribute dividends, surplus allotments or profits to its
stockholders.

PRA cannot be considered a non-stock corporation either because it
does not have members. A non-stock corporation must have members.
Moreover, it was not organized for any of the purposes mentioned in
Section 88 of the Corporation Code. Specifically, it was created to
manage all government reclamation projects.

Furthermore, there is another reason why the PRA cannot be
classified as a GOCC. Section 16, Article XII of the 1987 Constitution
provides as follows:

Section 16. The Congress shall not, except by general
law, provide for the formation, organization, or regulation of private
corporations. Government-owned or controlled corporations may be created
or established by special charters in the interest of the common good
and subject to the test of economic viability.

The fundamental provision above authorizes Congress to create
GOCCs through special charters on two conditions: 1) the GOCC must be
established for the common good; and 2) the GOCC must meet the test of
economic viability. In this case, PRA may have passed the first
condition of common good but failed the second one — economic viability.
Undoubtedly, the purpose behind the creation of PRA was not for
economic or commercial activities. Neither was it created to compete in
the market place considering that there were no other competing
reclamation companies being operated by the private sector. As mentioned
earlier, PRA was created essentially to perform a public service
considering that it was Primarily responsible for a coordinated,
economical and efficient reclamation, administration and operation of
lands belonging to the government with the object of maximizing their
utilization and hastening their development consistent with the public
interest.[197] (Emphasis in the original, citations omitted)

Being a government instrumentality, PEA is authorized by its charter
to contract loans to be able to carry into effect the mandate it was
given under P.D. No. 1084. Section 5 thereof reads:

Section 5. Powers and functions of the Authority. The Authority shall, in carrying out the purposes for which it is created, have the following powers and functions:

. . . .

(m) To enter into, make, perform and carry out contracts of every
class and description, including loan agreements, mortgages and other
types of security arrangements, necessary or incidental to the
realization of its purposes with any person, firm or corporation,
private or public, and with any foreign government or entity. (Emphasis
in the original)

Section 12 of P.D. No. 1084 likewise provides:

Section 12. Loans. The Authority, as
well as any affiliate corporation in which it holds, owns and/or
controls by itself or jointly with one or more government-owned or
controlled corporations at least seventy-five per cent (75%) of the
issued and outstanding shares of stock entitled to vote, when
specifically authorized by the President of the Philippines, is hereby
authorized to contract loans, credits, in any convertible foreign
currency or capital goods, and indebtedness from time to time from
foreign governments, or any international financial institutions or fund
sources, or any entities, on such terms and conditions as it shall deem
appropriate for the accomplishment of its purposes and to enter into
and execute agreements and other documents specifying such terms and
conditions. (Emphasis in the original)

The PDMB Project, as funded by loan obtained by the PEA, was thus
authorized by its charter, and whatever fond it may obtain therefrom
could be utilized for the current fiscal year. While the Sandiganbayan
found that dividing the project to Package 1 and Package 2 was a
subterfuge to do away with the requirement of funding, pertinent laws
only require that the funding of a project be viewed on a yearly basis.
The requirement of the law is funding for the current fiscal year. Be it
divided into several phases, as long as the project could be
implemented within the end of the year with the corresponding amount for
such project, the same could not be said to have violated the law.

The need to secure funding for the project covering the current fiscal
year is understandable. Under Section 47 of the Administrative Code, the
contract for the expenditure of public funds shall be for that amount
necessary to cover the proposed contract for the current calendar year,
thus:

SECTION 47. Certificate Showing Appropriation to Meet Contract.
— Except in the case of a contract for personal service, for supplies
for current consumption or to be carried in stock not exceeding the
estimated consumption for three (3) months, or banking transactions of
government-owned or controlled banks, no contract involving the
expenditure of public funds by any government agency shall be entered
into or authorized unless the proper accounting official of the agency
concerned shall have certified to the officer entering into the
obligation that funds have been duly appropriated for the purpose and
that the amount necessary to cover the proposed contract for the current
calendar year is available for expenditure on account thereat: subject
to verification by the auditor concerned. The certificate signed by the
proper accounting official and the auditor who verified it, shall be
attached to and become an integral part of the proposed contract, and
the sum so certified shall not thereafter be available for expenditure
for any other purpose until the obligation of the government agency
concerned under the contract is fully extinguished. (Emphasis supplied)

Considering that the amount of PHP 300 million was identified as the
budget to cover the expenses for the current year when the PDMB Project
was to be implemented the same should already suffice as compliance
with the requirement of the law.

Presidential approval

Another ground relied upon by the Sandiganbayan in convicting petitioners is the failure to secure presidential approval.

A reading of the Memorandum dated January 29, 2000 from the Executive Secretary[198]
would show that it was an approval of the Construction Agreement with
PEA for the construction of the Central Boulevard Road Project in the
amount of PHP 584,365,885.05 subject to certain conditions, foremost of
which are the inclusion of a provision in the Agreement that all extra
works and price adjustments should first be submitted to the President
for approval and that the final approval and actual release of the loan
proceeds from the LandBank/All Asia Capital must be secured.

It
must nonetheless be clarified that the additional condition for
presidential approval concerning extra works and price adjustments were
imposed by the Office of the President. In the same manner, the various
executive orders issued by the President are directives of the
executive, which does not necessarily amount to a violation of R.A. No.
3019.

Insofar as the contract itself was concerned, the approval
of the President was already given, subject to certain conditions,
which are in the nature of resolutory conditions. In an obligation with a
resolutory condition, the obligation is already effective, subject to
the happening of the condition. Thus, the approval of the president
should already be considered as given, subject to the happening of the
conditions it imposed, non-fulfillment of which could be a ground for
appropriate action between entities that imposed the same and those
required to fulfill the condition.

With respect to the
determination as to whether a violation of R.A. No. 3019 occurred, such
an infraction should first be proven to have been committed with
manifest partiality, evident bad faith, or gross inexcusable negligence
that resulted into undue injury to the government or any party, or any
unwarranted benefit to a private party. In the absence of proof of the
elements constituting violation of R.A. No. 3019, mere failure to comply
with a directive of the president cannot be considered a violation of
said criminal law.

Award of the Seaside Drive Extension

As found by the Sandiganbayan, Variation Order No. 2 comprised of the
Inland Bridge Channel and the Seaside Drive Extension. Considering that
it found the construction of the inland bridge channel under this
variation order as legal and necessary for the construction of the PDMB
Project, the same would no longer be disturbed on appeal. Rather, it is
the award of the Seaside Drive Extension under Variation Order No. 2
that will have to be examined.

Variation Orders are classified under the IRR of P.D. No. 1594 as follows:

CI 1 – VARIATION ORDERS – CHANGE ORDER/EXTRA WORK ORDER/SUPPLEMENTAL AGREEMENT

1. Variation orders may be issued by the concerned
agency/office/corporation to cover any increase/decrease in quantities,
including the introduction of new work items that are not included in
the original contract or reclassification of work items that are either
due to change of plans, design or alignment to suit actual field
conditions resulting in disparity between the preconstruction plans used
for purposes of bidding and the “as staked plans” or construction
drawings prepared after a joint survey by the contractor and the
government after award of the contract. The addition/deletion of works
should be within the general scope of the project as bid and awarded. A variation order may either be in the form of a change order, extra work order or a supplemental agreement. (Emphasis supplied)

No substantial change was introduced by the IRR of R.A. No. 9184[199], which defined variation order as follows:

1. Variation Orders – Change Order/Extra Work Order

1.1 Variation Orders may be issued by the procuring entity to
cover any increase/decrease in quantities, including the introduction of
new work items that are not included in the original contract or
reclassification of work items that are either due to change of plans,
design or alignment to suit actual field conditions resulting in
disparity between the preconstruction plans used for purposes of bidding
and the “as staked plans” or construction drawings prepared after a
joint survey by the contractor and the Government after award of the
contract, provided that the cumulative amount of the positive or
additive Variation Order does not exceed ten percent (10%) of the
original contract price. The addition/deletion of works under Variation
Orders should be within the general scope of the project as bid and
awarded. The scope of works shall not be reduced so as to accommodate a
positive Variation Order. A Variation Order may either be in the form of either a change order or extra work order.[200] (Emphasis supplied)

Clearly, a change order or extra work order is considered as a form
of variation order. Petitioners’ claim that the award of the Seaside
Drive Extension does not need the approval of the president is therefore
erroneous. When the Memorandum and the Contract with JD Legaspi
specified as a condition, the approval of the President before any extra
works may be performed on the project, this includes variation orders,
for an extra work is in reality, a form of a variation order. Suffice it
to state, the approval of the President should have been secured before
additional expenses on additional works, irrespective of their
nomenclature, may be awarded to the contractor. This is a condition
imposed by then Executive Secretary Zamora as early as the award of the
contract itself and made a condition in the various PEA Board
Resolutions, and the contract itself.

While Executive Order No.
109 expressly repealed Memorandum Circular No. 25, the same was issued
only on May 27, 2002 after the presidential approval was already given.
The Office of the President’s Memorandum dated January 29, 2000, which
approved the Construction Agreement, carried a condition that all extra
works and price adjustments should first be submitted to the president
for approval. Failure to secure presidential approval on the award of
the Seaside Drive Extension thus raises a circumstance that should be
considered in assessing whether a violation of R.A. No. 3019 occurred.
Nevertheless, this circumstance must be examined vis a vis the elements of the law alleged to have been violated.

Further, a variation order must still fall within the general
scope of the project as bid and awarded. In this case, the Seaside Drive
Extension was characterized by the Sandiganbayan as follows:

With respect, however, to the Seaside Drive Extension under
Variation Order No. 2, it appears that the same cannot legally qualify
to be covered by a Variation Order. This is because it is a road outside
of the PDMB project and nowhere along the original PDMB roadway plan.
It is, in fact, a roadway connecting PDMB and Roxas Boulevard. As
recommended by accused Beriña[, Jr.], the Seaside Extension Drive had to
be constructed to ease up traffic flow to and from Roxas Boulevard.
However, this road was never within the general scope of the PDMB
Project as bid and awarded. Accused Millan admitted this when he
testified that it was part of another project that was supposed to be
implemented but fell through. The Construction Agreement only defines
the Project as the Central Boulevard Road Project, without any mention
of any arterial roads or any additional roadway such as the Seaside
Drive Extension. No documents, whether it be the original action plan of
the Boulevard Project, the Construction Agreement signed between PEA
and accused Legaspi or the Bid Documents, show that the Seaside Drive
Extension was envisioned to be part of the general scope of the PDMB
Project.[201]

Indeed, nowhere was the Seaside Drive Extension found in any of
the documents bid out for the PDMB Project. It was not even located
along the stretch of President Diosdado Macapagal Boulevard, but a road
to connect the PDMB to the Roxas Boulevard, going to NAIA. A separate
bidding for the award of the Seaside Drive Extension should thus have
been undertaken.

Liability for the award of the Seaside Drive Extension

As discussed, the irregularity involved in this case pertains to the
award of the Seaside Drive Extension and not on the main contract for
the PDMB Project. Thus, it is the surrounding circumstances of the award
of this part of the project that should be examined to determine
whether there is a violation of R.A. No. 3019. In the process of
analysis, it bears pointing out that mere violation of the procurement
law does not automatically make one liable for violation of R.A. No.
3019. As explained in Sabaldan v. Office of the Ombudsman:[202]

More importantly, it must be emphasized that the instant case
involves a finding of probable cause for a criminal case for violation
of Section 3(e) of R.A. No. 3019, and not for violation of R.A. No.
9184. Hence, even granting that there may be violations of the
applicable procurement laws, the same does not mean that the elements of
violation of Section 3(e) of R.A. No. 3019 are already present as a
matter of course. For there to be a violation under Section 3(e) of R.A.
No. 3019 based on a breach of applicable procurement laws, one cannot
solely rely on the mere fact that a violation of procurement laws has
been committed. It must be shown that (1) the violation of procurement
laws caused undue injury to any party or gave any private party
unwarranted benefits, advantage or preference; and (2) the accused acted
with evident bad faith, manifest partiality, or gross inexcusable
negligence.[203]

A perusal of the arguments presented by the parties shows that the
participation of some of the petitioners revolved around the award of
the main contract and not in the introduction of Variation Order No. 2.
Thus, they cannot be held criminally liable therefor.

As regards
the liability of Amposta-Mortel, considering that there was no showing
that the variation order in question was submitted to her for review,
she cannot be held liable. A legal officer cannot be considered to have
facilitated the award of an erroneous contract when the same was not
even forwarded to her office for review. This must be so when the main
contract itself has already undergone the appropriate review and has
been given presidential approval.

On the part of the Old PEA
Board, being the governing body of the PEA tasked to formulate policy
decisions, they had every right to rely on the report and recommendation
of the Ad Hoc Committee as it is the members of the Ad Hoc
Committee who has the first-hand knowledge of the ongoing construction
and the actual location of the roads. In the absence of a clear showing
of bad faith, manifest partiality or gross inexcusable negligence in the
issuance of the Resolutions leading to the award of the Seaside Drive
Extension, they could not have violated R.A. No. 3019.

As
represented by Beriña, Jr., to facilitate the flow of traffic at the
Seaside Drive Extension, it is deemed necessary to complete the
construction of the proposed Seaside Drive Extension (connecting Roxas
Boulevard and Central Boulevard) and that since time is of the essence,
it was recommended that the additional works be awarded to JD Legaspi.[204]
The representation of Beriña, Jr. of the need to complete the
construction of the Seaside Drive Extension to facilitate the flow of
traffic and its necessity, especially when time is of the essence, made
the Board believe of the need to approve the award of the Seaside Drive
Extension, moreso, when the road has to connect the PDMB with other
roads.

As it even appears, Resolution Nos. 3017 and 3102 carried
conditions imposed by the PEA Board, which was supposed to safeguard the
award of the Seaside Drive Extension. The conditions imposed under
Resolution No. 3017 are as follows:

a. Payment will be made only on actual quantities completed based
on the approved detailed plans and applicable unit bid prices and agreed
prices (on new items of works)

b. No time extensions will be associated on these additional works
c. Final approval of the Office of the President as per Memo dated 29 June 2000.
d. Actual release of the loan proceeds from Land Bank of the Philippines.[205]

As to Resolution No. 3102, the Old PEA Board, in addition to the
previous conditions it imposed under Board Resolution No. 3017, further
required that the implementation of Variation Order No. 2 be made
subject to the provisions of P.D. No. 1594 while the appropriation of
the difference resulting from the updated cost thereof must be made
subject to existing accounting and auditing rules and regulations.[206] These safeguards negate bad faith or gross inexcusable negligence on the part of the members of the Old Board of PEA.

It must be added that the subsequent approval of the new Board of
Directors of the cost of the project signify their acquiescence not only
to the project but also a recognition of the safeguards that were
already put in place by the Old Board.

On the part of Beriña,
Jr. and Millan, who issued the request for Variation Order No. 1 (later
renumbered as Variation Order No. 2),[207]
the actions they took negate manifest partiality, evident bad faith, or
gross inexcusable negligence. In proposing the construction of the
Seaside Drive Extension, they have honestly believed that P.D. No. 1594
allows a negotiated contract where a variation order is adjacent or
contiguous to an ongoing project and could be economically prosecuted by
the same contractor. Further, from the ground and aerial sketches, the
Integrated Framework Plan and the present Google image of the President
Diosdado Macapagal Boulevard, the Seaside Drive Extension appears to be
connected to JD Legaspi’s PDMB Project.

Indeed, a negotiated
contract is allowed where the variation order to be introduced is
adjacent or contiguous to an ongoing project. Thus, even if the main
contract as bid out did not include the Seaside Drive Extension, the
same may still be introduced as a variation order as part of a
negotiated contract. The law however requires certain requirements, to
wit:

IB 10.6.2 – By negotiated Contract

. . . .

c. Where the subject project is adjacent or contiguous to an
ongoing project and it could be economically prosecuted by the same
contractor provided that subject project has similar or related scope of
works and is within the contracting capacity of the contractor, in
which case, direct negotiation may be undertaken with the said
contractor at the same unit prices adjusted to price levels prevailing
at the time of negotiation using the parametric formulae herein
prescribed without the 5% deduction and contract conditions, less
mobilization cost, provided that he has no negative slippage and has
demonstrated a satisfactory performance.[208]

Hence, the introduction of the Seaside Drive Extension is not without
legal basis. While it would appear that said road does not fall along
the stretch of the PDMB Project, this fact alone cannot serve as a basis
to hold petitioners liable for violation of R.A. No. 3019. To stress,
the focal point in determining whether there is a violation of R.A. No.
3019 is the elements comprising it, one of which is the existence of
manifest partiality, evident bad faith or gross inexcusable negligence.
These were defined as follows:

Under the third element, the crime may be committed through
“manifest partiality,” “evident bad faith,” or “gross inexcusable
negligence.” As already held by this Court, Section 3(e) of RA 3019 may
be committed either by dolo, as when the accused acted with evident bad
faith or manifest partiality, or by culpa, as when the accused committed
gross inexcusable negligence. There is “manifest partiality” when there
is a clear, notorious, or plain inclination or predilection to favor
one side or person rather than another. “Evident bad faith” connotes not
only bad judgment but also palpably and patently fraudulent and
dishonest purpose to do moral obliquity or conscious wrongdoing for some
perverse motive or ill will. “Evident bad faith” contemplates a state
of mind affirmatively operating with furtive design or with some motive
or self-interest or ill will or for ulterior purposes. “Gross
inexcusable negligence” refers to negligence characterized by the want
of even the slightest care, acting or omitting to act in a situation
where there is a duty to act, not inadvertently but willfully and
intentionally, with conscious indifference to consequences insofar as
other persons may be affected.[209] (Citations omitted)

Here, the Seaside Drive Extension was constructed at a portion of
the PDMB in order to have a road that will connect it to the Roxas
Boulevard. It is not a road construction that is totally alien to the
PDMB Project, for it is still a road that is connected to the main
project, and serves as a link to the other roads going to and from the
President Diosdado Macapagal Boulevard. With a legal basis for which the
actions taken by petitioners were anchored, it cannot be said that
their actions were coupled with a clear inclination to favor another or
that a conscious wrongdoing, ill-will or dishonest purpose was being
committed.

The same must also be said as to the absence of
presidential approval for the introduction of Variation Order No. 2.
Such a finding does not automatically equate to a violation of R.A. No.
3019, considering the failure of the prosecution to show that it was
accompanied by manifest partiality, evident bad faith or gross
inexcusable negligence. To stress, the main contract has already been
approved by the president. Likewise, taking into consideration the
nature of a negotiated contract by which the award of the additional
works must necessarily be given to the contractor of the main project
provided the requisites are present, reliance on the provision of
negotiated contracts by Beriña, Jr. and Millan negates the element of
evident bad faith, manifest partiality or gross inexcusable negligence.
Necessarily, if the PDMB Project was awarded to JD Legaspi, any
negotiated contracts related thereto should also be awarded to him by
operation of law. As such, with the passage of P.D. No. 1594, the
requirement of presidential approval for the award of a subsequent
project believed to be qualified as a negotiated contract, would be
rendered unnecessary. Considering however that such an approval for
subsequent works has been required by the Office of the President when
it approved the main project, any infraction thereon would only be
subject to the exercise of discretion of the said Office. With respect
to violation of R.A. No. 3019, the good faith reliance of Beriña, Jr.
and Millan as to the necessity of the Seaside Drive Extension and their
appreciation of the application of P.D. No. 1594 as to negotiated
contracts, would not make them liable for violation thereof on account
merely of the absence of presidential approval of the award of the
Seaside Drive Extension.

The need to prove all the elements of
the crime of R.A. No. 3019, as in all other cases of violation of
criminal laws, springs from the constitutional presumption of innocence.
As elaborated in Villarosa v. People:[210]

The settled rule is that conviction in criminal actions demands
proof beyond reasonable doubt. This rule places upon the prosecution the
task of establishing the guilt of an accused, relying on the strength
of its own evidence, and not banking on the weakness of the defense of
an accused. Indeed, the burden is on the prosecution to prove guilt
beyond reasonable doubt, not on the accused to prove his innocence.
Requiring proof beyond reasonable doubt finds basis not only in the due
process clause of the Constitution, but similarly, in the right of an
accused to be “presumed innocent until the contrary is proved.”
Undoubtedly, it is the constitutional presumption of innocence that lays
such burden upon the prosecution. (Citations omitted)[211]

With respect to Legaspi, the Sandiganbayan also convicted him for
violation of Section 3(e) of R.A. No. 3019 because of its finding of
implied conspiracy, holding that the PEA Management would not have
presented the same to the Board had Legaspi not submitted documents
pertaining to the possibility of constructing the same as a change order
to the original Construction Agreement, thereby violating all the
public bidding rules in place.[212]

In Tan v. People,[213] this Court explained the liability of private individuals charged with violation of R.A. No. 3019, to wit:

Private persons, when acting in conspiracy with public officers,
may be indicted and, if found guilty, held liable for the pertinent
offenses under Section 3 of R.A. 3019, including (e) thereof. This is in
consonance with the avowed policy of the anti-graft law to repress
certain acts of public officers and private persons alike constituting graft or corrupt practices act or which may lead thereto.

Thus, for a private person to be charged with and convicted of
Violation of certain offenses under Section 3 of R.A. 3019, which in
this case (e), it must be satisfactorily proven that he/she has acted in
conspiracy with the public officers in committing the offense;
otherwise, he/she cannot he so charged and convicted thereof.

In conspiracy, the act of one is the act of all; thus, it is never
presumed. Like the physical acts constituting the crime itself, the
elements of conspiracy must be proven beyond reasonable doubt. To
establish conspiracy, direct proof of an agreement concerning the
commission of a felony and the decision to commit it is not necessary.
It may be inferred from the acts of the accused before, during or after
the commission of the crime which, when taken together, would be enough
to reveal a community of criminal design, as the proof of conspiracy is
frequently made by evidence of a chain of circumstances. While
direct proof is not essential to establish conspiracy, it must be
established by positive and conclusive evidence. And conviction must be
founded on facts, not on mere inferences and presumptions.
[214] (Emphasis in the original, citations omitted)

A reading of the assailed Decision and Resolution would however show
that the only basis relied upon by the Sandiganbayan in concluding that
Legaspi had a part in the award of the Seaside Drive Extension was the
Sworn Statement as attached to the Counter-Affidavit of Tagud, which was
taken judicial notice of, stating that it was Legaspi who proposed to
PEA the construction of the Seaside Drive Extension.[215]

It must be noted however that neither the Sworn Statement nor the
Counter Affidavit of Tagud was shown to have been offered as evidence by
the prosecution. The Rules of Court specifically provides that evidence
must be formally offered to be considered by the court. Evidence not
offered is excluded in the determination of the case. Failure to make a
formal offer within a considerable period of time shall be deemed a
waiver to submit it.[216]

The same cannot also be taken judicial notice of because it does not fulfill the condition of notoriety. In State Prosecutors v. Judge Muro,[217] judicial notice was explained as follows:

The doctrine of judicial notice rests on the wisdom and discretion
of the courts. The power to take judicial notice is to be exercised by
courts with caution; care must be taken that the requisite notoriety
exists; and every reasonable doubt on the subject should be promptly
resolved in the negative.

Generally speaking, matters of judicial notice have three material
requisites: (1) the matter must be one of common and general knowledge;
(2) it must be well and authoritatively settled and not doubtful or
uncertain; and (3) it must be known to be within the limits of the
jurisdiction of the court. The provincial guide in determining what
facts may be assumed to be judicially known is that of notoriety. Hence,
it can be said that judicial notice is limited to facts evidenced by
public records and facts of general notoriety.

To say that a court will take judicial notice of a fact is merely
another way of saying that the usual form of evidence will be dispensed
with if knowledge of the fact can be otherwise acquired. This is because
the court assumes that the matter is so notorious that it will not be
disputed. But judicial notice is not judicial knowledge. The mere
personal knowledge of the judge is not the judicial knowledge of the
court, and he is not authorized to make his individual knowledge of a
fact, not generally or professionally known, the basis of his action.
Judicial cognizance is taken only of those matters which are “commonly”
known.

Things of “common knowledge,” of which courts take judicial
notice, may be matters coming to the knowledge of men generally in the
course of the ordinary experiences of life, or they may be matters which
are generally accepted by mankind as true and are capable of ready and
unquestioned demonstration. Thus, facts which are universally known, and
which may be found in encyclopedias, dictionaries or other
publications, are judicially noticed, provided they are of such
universal notoriety and so generally understood that they may be
regarded as forming part of the common knowledge of every person.[218] (Citations omitted)

The affidavit of Tagud cannot be taken judicial notice of because it
is not a product of common experience in the ordinary course of things.
No practice has been established for a contractor to ask for additional
works in a project. Rather, the contents of Tagud’s affidavit requires
the presentation of evidence to prove the actions allegedly taken by
Legaspi to ensure that the Seaside Drive Extension would be awarded to
him. In the absence of such evidence, this Court cannot take at face
value, the allegations in the affidavit of Tagud.

Further, the
Sandiganbayan found that Legaspi proceeded to construct the Seaside
Drive Extension without receiving an approval from the Office of the
President as stated in their Construction Agreement. Suffice it to state
however, that such an obligation does not fall on Legaspi, being the
contractor.

Legaspi cannot therefore be held liable for the award of the Seaside Drive Extension.

With respect to the payments made to JD Legaspi, the same is justified on the basis of quantum meruit as expounded in Melchor v. Commision On Audit,[219] to wit:

Moreover, a variation order (which may take the form of a change
order, extra work or supplemental agreement) is a contract by itself and
involves the expenditure of public funds to cover the cost of the work
called for thereunder. (Fernandez, A Treatise on Government Contracts
under Philippine Law, 115-116 [1985]) As such, it is subject to the
restrictions imposed by Sections 85 and 86 of PD 1445 and LOI 968. COA
Circular No. 80-122, dated January 15, 1980, likewise ensures that an
extra work order is approved only when supported by available funds.
Again, the petitioner has not presented proof of an appropriation to
cover the extra work order.

For a failure to show the approval by the proper authority and to
submit the corresponding appropriation, we declare the contract for
extra works null and void.

Section 87 of PD 1445 states:

“Any contract entered into contrary to the requirements of the two immediately preceding sections shall be void, and the officer
or officers entering into the contract shall be liable to the
government or other contracting party for any consequent damage to the
same extent as if the transaction had been wholly between private
parties
.” (Italics supplied)

This does not mean, however, that the petitioner should be held
personally liable and automatically ordered to return to the government
the full amount of P172,003.26.

As previously discussed, it would be unjust to order the
petitioner to shoulder the expenditure when the government had already
received and accepted benefits from the utilization of the building.

In Royal Trust Construction v. Commission on Audit, supra,
cited by the petitioner, the Court, in the interest of substantial
justice and equity, allowed payment to the contractor on a quantum
meruit basis despite the absence of a written contract and a covering
appropriation.

In a more recent case, Dr. Rufino O. Eslao v. Commission on Audit, G.R. No. 89745, April 8, 1991,
the Court directed payment to the contractor on a quantum meruit basis
despite the petitioner’s failure to undertake a public bidding. In that
case, the Court held that “to deny payment to the contractor of the two
buildings which are almost fully completed and presently occupied by the
university would be to allow the government to unjustly enrich itself
at the expense of another.”

Where payment is based on quantum meruit, the amount of recovery
would only be the reasonable value of the thing or services rendered
regardless of any agreement as to value. (Tantuico, State Audit Code of
the Philippines Annotated, 471 [1982])

Although the two cases mentioned above contemplated a situation
where it is the contractor who is seeking recovery, we find that the
principle of payment by quantum meruit likewise applies to this case
where the contractor had already been paid and the government is seeking
reimbursement from the public official who heads the school. If, after
COA determines the value of the extra works computed on the basis of
quantum meruit, it finds that the petitioner made an excess or improper
payment for these extra works, then petitioner Melchor shall be liable
only for such excess payment.[220]

While the variation orders performed by Legaspi may have been done
in advance, this does not deprive him, moreso, make him liable for
payment of the cost of the project, especially that the public is now
reaping the benefits of the said road construction. The principle of quantum meruit
thus applies, and as the COA found no irregularity in the amount paid
to him by the government, such amount should no longer be returned.
Moreover, the contract price adjustment in the amount of PHP
42,418,493.64 was considered reasonable by the COA.[221]

As to the civil liability of petitioners, Cabrera v. People[222] discussed the basis of civil liability for violation of R.A. No. 3019 as follows:

The first punishable act is that the accused is said to
have caused undue injury to the government or any party when the latter
sustains actual loss or damage, which must exist as a fact and cannot be
based on speculations or conjectures. The loss or damage need not be
proven with actual certainty. However, there must be “some reasonable
basis by which the court can measure it.” Aside from this, the loss or
damage must be substantial. It must be “more than necessary, excessive,
improper or illegal.”

The second punishable act is that the accused is said to
have given unwarranted benefits, advantage, or preference to a private
party. Proof of the extent or quantum of damage is not thus essential. It is sufficient that the accused has given “unjustified favor or benefit to another.”[223] (Citations omitted)

Here, there was no undue injury to the government or any party, or
any unwarranted benefit that was proven by the prosecution. The
government cannot be said to have suffered an actual loss since there
was no showing that it had to perform acts prejudicial to its interest
that would pertain to the loan obtained by PEA, or to the construction
of the President Diosdado Macapagal Boulevard. To the contrary, the
timely completion of the project resulted into a benefit in favor of the
government with the increase in value of the land surrounding the area,
as well as the public who continue to reap the benefits of having
alternate routes that would let them avoid traffic congestion.

Likewise, no circumstance was shown to favor JD Legaspi in the award of
the main contract and the variation orders that would amount to an
unwarranted benefit in his favor. It is undeniable that the contract for
the main project underwent the necessary procurement procedure. As to
the award of the Seaside Drive Extension, the same was brought about by
the honest belief of petitioners that it fell within the parameters of a
negotiated contract. Under the rules on negotiated contract, a project
may be awarded to the same contractor who was awarded with the ongoing
project. Considering that JD Legaspi was awarded with the main contract,
there is nothing irregular for the petitioners, believing in good faith
as to the applicability of the rules on negotiated contracts, to award
the Seaside Drive Extension to JD Legaspi. Thus, there was no
unwarranted benefit that favored JD Legaspi in the award of the Seaside
Drive Extension.

With the foregoing, the civil liability imposed by the Sandiganbayan upon the petitioners should be deleted.

ACCORDINGLY, the consolidated Petitions are GRANTED. The Decision dated February 5, 2015 and the Joint Resolution dated September 16, 2015 rendered by the Sandiganbayan are REVERSED and SET ASIDE.
Petitioners Cristina Amposta-Mortel, Theron Victor Lacson, Leo Padilla,
Manuel Beriña, Jr., Jaime Millan, Bernardo Viray, Raphael Pocholo
Zorilla, Daniel Dayan, Frisco Francisco San Juan, Elpidio Damaso,
Carmelita D. Chan, and Jesusito Legaspi are ACQUITTED
of violation of Republic Act No. 3019 on the ground of reasonable doubt.
The civil liability imposed by the Sandiganbayan is hereby DELETED.

Let an entry of judgment be issued immediately.

SO ORDERED.

Lazaro-Javier, M. Lopez, and Kho, Jr., JJ., concur.
Leonen, SAJ., dissent. See separate opinion.


[1] Rollo (G.R. No. 220500), vol. I, p. 462; rollo (G.R. No. 220580), vol. I, p. 125; rollo (G.R. No. 220587), vol. II, p. 1121; G.R. No. 220523 was consolidated with these cases on September 27, 2021.

[2] Rollo (G.R. No. 220500),
vol. I, pp. 101-245. The February 5, 2015 Decision in Criminal Case No.
27808 was penned by Associate Justice Rafael R. Lagos, concurred in by
Associate Justices Efren N. De La Cruz and Rodolfo A. Ponferrada, First
Division, Sandiganbayan, Quezon City.

[3] Id. at
328-384. The September 16, 2015 Joint Resolution in Criminal Case No.
27808 was penned by Associate Justice Efren N. De La Cruz, concurred in
by Associate Justices Rodolfo A. Ponferrada and Napoleon E. Inoturan,
First Division, Sandiganbayan, Quezon City.

[4] Id. at 243-244.

[5] Id. at 383-384.

[6] As culled from the Sandiganbayan Decision.

[7] See rollo (G.R. No. 220587), vol. I, pp. 304-306.

[8] Rollo (G.R. No. 220500), vol. I, p. 178.

[9] Id. at 179.

[10] Id.

[11] Id.

[12] Id.

[13] Id.

[14] Id. at 180.

[15] Id.

[16] Id. at 180-181.

[17] Id. at 181.

[18] Id.

[19] Id.

[20] Rollo (G.R. No. 220587), vol. I, pp. 310-311.

[21] Id.

[22] Rollo (G.R. No. 220500), vol. I, p. 182.

[23] Rollo (G.R. No. 220587), vol. I, pp. 312-323.

[24] Id. at 315, 317; See also rollo (G.R. No. 220500), vol. I, p. 183.

[25] Rollo (G.R. No. 220587), vol. I, p. 315.

[26] Id. at 322. See also rollo (G.R. No. 220500), vol. I, p. 183.

[27] Rollo (G.R. No. 220500), vol. I, p. 183.

[28] Id.

[29] Id. at 184. See also rollo (G.R. No. 220587), vol. I, p. 330.

[30] Rollo (G.R. No. 220500), vol. I, p. 184.

[31] Id.

[32] Id. at 184.

[33] Id. at 185. See also rollo (G.R. No. 220587), vol. I, pp. 333, 448.

[34] Rollo (G.R. No. 220500), vol. I, p. 185.

[35] Id. at 186.

[36] Id. at 185.

[37] As amended on May 24 and July 5, 2000.

[38] Prescribing Policies, Guidelines, Rules and Regulations for Government Infrastructure Contracts, July 11, 1978.

[39] Rollo (G.R. No. 220500), vol. I, pp. 185-186.

[40] Id. at 186.

[41] Id.

[42] Id. at 186-187.

[43] Id. at 187.

[44] Id.

[45] Id.

[46] Id. at 187-188.

[47] Id. at 188.

[48] Id at 189.

[49] Id. at 188.

[50] Id. at 189.

[51] Id. at 189-190.

[52] Id.

[53] Rollo (G.R. No. 220587), vol. II, pp. 724-732.

[54] Anti-Graft and Corrupt Practices Act, August 17, 1960.

[55] Id. at 728-731.

[56] Rollo (G.R. No. 220587), vol. I, p. 75.

[57] Id.

[58] Rollo (G.R. No. 220500), vol. I, p. 192.

[59] Id. at 192-193.

[60] Id. at 193.

[61] Id.

[62] Id. at 194.

[63] Id. at 194-197.

[64] Id. at 197-198.

[65] Id. at 199.

[66] Id.

[67] Id.

[68] Id. at 200.

[69] Id.

[70] Id. at 201.

[71] Id. at 202.

[72] Id. at 202-203.

[73] Id. at 203.

[74] Id. at 204.

[75] Id. at 205.

[76] Id. at 223.

[77] Id. See also p. 242.

[78] Id. at 225.

[79] Id. at 226.

[80] Id. at 227.

[81] Id. at 228.

[82] Id.

[83] Id. at 230.

[84] Id. at 231.

[85] Id.

[86] Id. at 233.

[87] Id. at 237.

[88] Id. at 238.

[89] Id.

[90] Id. at 238-239.

[91] Id. at 239.

[92] Id.

[93] Id. at 242.

[94] Id. at 328-384.

[95] Id. at 377.

[96] Id.

[97] Id.

[98] Id.

[99] Id. at 384.

[100] Id. at 377-378.

[101] Id. at 377.

[102] Id. at 378-379.

[103] Id. at 379.

[104] Id. at 384.

[105] Id. at 84.

[106] Id. at 85.

[107] Id.

[108] Id. at 86.

[109] Id.

[110] Id. at 94-95.

[111] Id. at 92, 94-95.

[112] Rollo (G.R. No. 220504), vol. I, p. 26.

[113] Former PEA Chief Corporate Counsel and current PEA Corporate Secretary.

[114] Id. at 27.

[115] Id. at 28-29.

[116] Id. at 30.

[117] Id.

[118] Id. at 34.

[119] Id. at 35.

[120] Id. at 37.

[121] Rollo (G.R. No. 220580), vol. I, pp. 53-54.

[122] Id. at 55.

[123] Id. at 56.

[124] Id.

[125] Id.

[126] Id. at 56-57.

[127] Id. at 57.

[128] Government Auditing Code, June 11, 1978.

[129] Rollo (G.R. No. 220580), vol. I, p. 77.

[130] Id. at 77.

[131] Id. at 83.

[132] Id. at 85.

[133] Rollo (G.R. No. 220532), vol. I, p. 282.

[134] Id. at 284.

[135] Id.

[136] Id. at 292.

[137] Id. at 295.

[138] Id. at 304.

[139] Id. at 338.

[140] Id. at 339-340.

[141] Id. at 344-345.

[142] Rollo (G.R. No. 220587), vol. I, p. 30.

[143] Id. at 31-32.

[144] Id. al 32.

[145] Id.

[146] Id. at 32-33.

[147] Id. at 32-33.

[148] Id. at 39-40.

[149] Id. at 40.

[150] Id.

[151] Id. at 40.

[152] Id. at 42.

[153] Id. at 42-43.

[154] Id.

[155] Id. at 48-49.

[156] Id. at 50.

[157] Rollo (G.R. No. 120568), vol. I, pp. 272-326.

[158] Id. at 294.

[159] Id. at 296.

[160] Id. at 302.

[161] Id.

[162] Id. at 308.

[163] Id. at 308-309.

[164] Id. at 310.

[165] Id. at 311.

[166] Id.

[167] Id. at 312.

[168] Id. at 313.

[169] Id. at 328-340.

[170] See rollo (G.R. No. 210505), vol. I, p. 10.

[171] Rollo (G.R. No. 220568), vol. I, p. 21.

[172] Rollo (G.R. No. 220504), vol. I, p. 11.

[173] Tongohan Holdings and Dev’t. Corp v. Atty. Escano, Jr., 672 Phil. 747, 756 (2011) [Per J. Mendoza, Third Division], citing Rep. of the Phils v. Malabanan, 646 Phil. 631, 637 (2010) [Per J. Villarama, Jr., Third Division].

[174] Macairan v. People, G.R. Nos. 215104, 215120, 215147, 215212, 215354-55, 215377, 215923 & 215541,
March 18, 2021 [Per J. Caguioa, First Division] at 20. This pinpoint
citation refers to the copy of this Decision uploaded to the Supreme
Court website.

[175] Rollo (G.R. No. 220587), vol. I, pp. 212-213.

[176] G.R. No. 238014, June 15, 2020 [Per J. Reyes, J. Jr., First Division].

[177] Id. at 7-8. This pinpoint citation refers to the copy of this Decision uploaded to the Supreme Court website.

[178] Government Procurement Reform Act, July 22, 2002.

[179] G.R. No. 239871, March 18, 2021 [Per J. Caguioa, First Division].

[180] Id. at 10. This pinpoint citation refers to the copy or this Decision uploaded to the Supreme Court website.

[181] Implementing Rules and Regulation of Presidential Decree No. 1594, as amended on May 24 and July 5, 2000, IB 10.4.2.

[182] Rollo (G.R. No. 220504), vol. I, p. 30.

[183] Id.

[184] Albay Accredited Constructors Association, Inc. v. Desierto, 516 Phil. 308, 320 (2006) [Per J. Garcia, Second Division].

[185] G.R. No. 224720-23, February 2, 2021 [Per J. Caguioa, En Banc].

[186] Id. at 29. This pinpoint citation refers to the copy of this Decision uploaded to the Supreme Court website.

[187] G.R. No. 215104, March 18, 2021 [Per J. Caguioa, First Division].

[188] Id. at 29. This pinpoint citation refers to the copy of this Decision uploaded to the Supreme Court website.

[189] Rollo (G.R. No. 220587), vol. I, pp. 542-545.

[190] 759 Phil. 248 (2015) [Per J. Mendoza, Second Division].

[191] Id. at 279, 281.

[192] 438 Phil. 72 (2002) [Per J. Sandoval-Gutierrez, En Banc].

[193] Id. at 94-97.

[194] Rollo (G.R. No. 220505), vol. I, p. 20; rollo (G.R. No. 220552), vol. I, p. 79; rollo (G.R. No. 220568), vol. I, p. 29; rollo (G.R. No. 220580), vol. I, pp. 67-68; rollo (G.R. No. 220592), vol. I, p. 234.

[195] Id.

[196] 691 Phil. 476 (2012) [Per J. Mendoza, Third Division].

[197] Id. at 484-486.

[198] Rollo (G.R. No. 220587), vol. I, p. 310.

[199] The 2016 Revised Implementing Rules and Regulations of Republic Act No. 9184, March 31, 2021.

[200] Id. Annex E, 1.1.

[201] Rollo (G.R. No. 220505), vol. I, p. 215.

[202] G.R. No. 238014, June 15, 2020 [Per J. Reyes, J. Jr., First Division].

[203] Id. at 7-8. This pinpoint citation refers to the copy of this Decision uploaded to the Supreme Court website.

[204] Rollo (G.R. No. 220505), vol. II, p. 735.

[205] Rollo (G.R. No. 220580), vol. I, pp. 57-58.

[206] Id. at 57.

[207] Rollo (G.R. No. 220587), vol. I, p. 328.

[208] Implementing Rules and Regulation of Presidential Decree No. 1594, as amended on May 24 and July 5, 2000.

[209] Villarosa v. People, G.R. No. 233155-63, June 23, 2020 [Per C.J. Peralta, En Banc] at 8-9. This pinpoint citation refers to the copy of this Decision uploaded to the Supreme Court website.

[210] Id.

[211] Id. at 7. This pinpoint citation refers to the copy of this Decision uploaded to the Supreme Court website.

[212] Rollo (G.R. No. 220580), vol. I, p. 209.

[213] 797 Phil. 411 (2016) [Per J. Perez, Third Division].

[214] Id. at 428-429.

[215] See rollo (G.R. No. 220587), vol. I, p. 210.

[216] Republic v. Gimenez, 776 Phil. 233, 255 (2016) [Per J. Leonen, Second Division].

[217] 306 Phil. 519 (1994) [Per Curiam, En Banc].

[218] Id. at 537-538.

[219] 277 Phil. 801 (1991) [Per J. Gutierrez, Jr., En Banc].

[220] Id. at 814-815.

[221] Rollo (G.R. No. 220505), vol. II, p. 939.

[222] G.R. No. 191611-14, July 29, 2019 [Per J. Reyes, J. Jr., Second Division].

[223] Id. at 6. This pinpoint citation refers to the copy of this Decision uploaded to the Supreme Court website.



DISSENTING OPINION

LEONEN, SAJ.:

I dissent.

The public bidding process is imbued with
public interest. Individuals involved in the bidding process have an
important responsibility to ensure compliance with the relevant bidding
rules and regulations. I disagree with the majority’s decision to acquit
petitioners and to remove their civil liability.

The
Sandiganbayan convicted petitioners of violation of Republic Act No.
3019, Section 3(e). It found that, taking the totality of petitioners’
conduct, the irregularities in the bidding process resulted in undue and
unwarranted benefits or advantage to petitioner Jesusito Legaspi, with
evident bad faith, manifest partiality, or gross inexcusable negligence.[1] According to the Sandiganbayan, the basis for their conviction are:

  1. Violating the simplified bidding rules because they shortlisted bidders not based on the PCAB master list.
  2. Conducting the bidding and recommending the award to Legaspi
    without [detailed] engineering in violation of P.D. 1594 and without the
    required appropriation and actual availability of funds for the total
    contract price.

  3. Creating and confirming the artificial phases in the Construction
    Agreement and dividing the contract into Phase I and Phase II just to
    enable PEA to circumvent the requirement under P.D. No. 1445 about
    funding requirements.

  4. In the case of Beriña and Millan, recommending the approval of
    Variation Order No. 2 and the contract price adjustment, and the payment
    thereof, without the required presidential approval and in violation of
    P.D. No. 1594.

  5. In the case of San Juan, Chan, Dayan, Malbarosa, Padilla and
    Damaso, for approving and confirming the Legaspi contract without
    sufficient funding and the Seaside Drive Extension without public
    bidding.

  6. In the case of Legaspi, for conspiring with Beriña and Millan in
    having the Seaside Drive Extension contract awarded to him under a
    negotiated contract.[2]

The President Diosdado Macapagal Boulevard was part of a flagship
project (the Project) for the construction of a five-kilometer highway
traversing the reclaimed area from Buendia Avenue to Pacific Avenue.[3]
Due to the project’s importance, the then Chairperson of the Public
Estates Authority (now Philippine Reclamation Authority) requested the
Office of the President for authority to bid and award the project
through simplified bidding. This request was approved through the
Memorandum issued by then Executive Secretary Ronaldo Zamora.[4]

As noted by the Sandiganbayan, under a simplified bidding process, participation was limited to “bona fide
contractors duly accredited and classified for the project category and
size and who are included in a separate list to be prepared by the
Philippine Contractors Accreditation Board.”[5]
Thus, despite the simplified procedure, safeguards were still put in
place with the involvement of the Philippine Contractors Accreditation
Board, the agency which grants, suspends, and revokes licenses to
contractors,[6] to ensure the qualification of the contractors that were to bid in the projects.

Despite this, the Public Estate Authority chose to limit its
bidders to a shortlist of 10 contractors, provided not by the Philippine
Contractors Accreditation Board as expressly required, but a list of 10
contractors given by the Department of Public Works and Highways.[7]

The ponencia,
however, concludes that petitioners were left with no choice but to
consult the list given by the Department of Public Works and Highways
because the Philippine Contractors Accreditation Board list was not yet
existent. In absolving petitioners, the ponencia asserts: “[a]
negative fact, such as the absence of the masterlist, cannot serve as a
basis for a wrongdoing, when the prosecution itself has not first
presented proof of its existence.”[8] I disagree.

The unavailability of the list by the Philippine Contractors
Accreditation Board was not a reason to deviate from the standard
procedure and get a separate list from the Department of Public Works
and Highways. There is no substantial compliance, as the ponencia puts it,[9]
since there was no compliance at all. There is no mechanism or
provision that authorizes the substitution of the Philippine Contractors
Accreditation Board list by another list.

Moreover, as the Sandiganbayan has found, the entire project was
divided into two separate packages for purposes of the simplified
bidding without any rational basis.[10]
Package 1 included part of the Project that was eventually awarded to
petitioner Legaspi, while Package II covered part of the Project where
the Public Estates Authority had a prior joint venture agreement with
SM, Inc. and R1 Consortium. This joint venture agreement allowed the two
developers the option to construct that portion of the Project in
exchange for lands or bonds. Thus, the continuation of Package II of the
Project depended on the decision of SM, Inc. and R1 Consortium of
whether they will pursue the Project themselves or not.[11]
Petitioner Legaspi’s company was put in the list of contractors for
Package I just because it was number two in the list by the Department
of Public Works and Highways. The latter five of the 10 contractors were
assigned as prequalified contractors for Package II, again without
basis. This arbitrary decision led to unwarranted benefits in favor of
petitioner Legaspi.[12] As explained by the graft court:

[T]hose contractors assigned for the Package II bidding were, from
the start, disadvantaged because of the great possibility that Package
II could not be bid out because of the option open to SM and R1
consortium. In turn, those contractors which were assigned for Package
I, were favored by PEA’s arbitrary decision because, just by their
being listed ahead in the DPWH list, they were certain to be able to bid
and in the case of Legaspi, win the award for Package I. This alone
gave undue advantage to the first set of contractors and prejudiced the
second set. Had PEA included all ten (10) of the DPWH listed contractors
for both Package I and II, no such advantage or prejudice would have
resulted. Better still, if PEA followed P.D. 1594 by including ALL
qualified contractors accredited by the PCAB in its master list in the
simplified bidding, then no question of impropriety could arise.

JD Legaspi Construction, which was number 2 in the DPWH list
therefore, gained an advantage or benefit, as it was able to bid and win
Package I, to the disadvantage of those contractors in the second set
of the DPWH list and also those PCAB accredited contractors in the
latter’s master list, who were not included in the DPWH list.

Moreover, PEA’s fear that a contractor could get both Package I
and II of the Boulevard project was not completely averted because
during the course of Legaspi’s implementation of its contract, PEA
approved Variation Order No. 2 in favor of Legaspi. This included the
Inland Channel Bridge which was originally part of Package II but was
later turned down to be built by R1 Consortium. Variation Order No. 2
also included the Seaside Drive Extension connecting PDMB to Roxas
Boulevard… No additional bidding was done for the additional works
under Variation Order No. 2. Legaspi, therefore, was given unwarranted
benefits and/or advantage by PEA.[13]

Moreover, there were no detailed engineering plans when petitioner
Raphael Pocholo Zorilla prepared the Approved Agency Estimate, and the
Public Estates Authority bid out and awarded the Project. The ponencia makes the same observation that this clearly contravenes Section 2 of Presidential Decree No. 1594, which reads:

Section 2. Detailed Engineering. No bidding and/or award of contract for a construction project shall be made unless the detailed engineering investigations, surveys, and designs for the project have been sufficiently carried out
in accordance with the standards and specifications to be established
under the rules and regulations to be promulgated pursuant to Section 12
of this Decree so as to minimize quantity and cost overruns and
underruns, change orders and extra work orders, and unless the detailed engineering documents have been approved
by the Minister of Public Works, Transportation and Communications, the
Minister of Public Highways, or the Minister of Energy, as the case may
be. (Emphasis supplied)

However, the ponencia absolves petitioner for this
violation because it finds that there was no clear showing of bad faith,
malice, or gross negligence.[14]

Further, the Sandiganbayan also found that there was no
appropriation and sufficient funds to finance the project at the time
the Public Estates Authority approved the signed Construction Agreement
with petitioner Legaspi.[15]
All it had was a Board Resolution identifying the source of funds—the
PHP 1 billion loan facility from Land Bank of the Philippines and All
Asia Capital Group—but the loan was not yet existent because it was
still under negotiation at that time.[16]
By the time the Construction Agreement was signed, dated, and
notarized, only PHP 300 Million was actually released as proceeds of the
loan from the Land Bank of the Philippines; this was still below the
actual contract cost of PHP 584,365,855.05.[17]

Additionally, the Sandiganbayan found that splitting the Project into
two phases was only a ploy to circumvent this defect, but this defect
remained as Phase II of the project since it “could be undertaken only
if and when funds are made available again.”[18] And indeed, the Public Estates Authority ran out of funds, and could not pursue the remaining works.[19]

The ponencia,
however, maintains that the law only requires that project funding be
viewed on a yearly basis, irrespective of whether the project is divided
into several phases. As long as a portion of the project could be
implemented by the end of the fiscal year with the corresponding amount
to cover for that portion, there is no violation of the law.[20]

As to the lack of presidential approval for contract price
adjustments as required by the Memorandum by Executive Secretary Zamora,
the ponencia finds that these were violations of directives
from the Executive that do not necessarily amount to violations of the
law. In any case, it claims that such infraction was not “proven to have
been committed with manifest partiality, evident bad faith, or gross
inexcusable negligence… [M]ere failure to comply with a directive of
the president cannot be considered a violation of … criminal law.”[21]

However, as to the award of the Seaside Drive Extension under Variation Order No. 2 of the Construction Agreement, the ponencia
agrees that presidential approval was required because this variation
order constituted a change order or extra work order under the
Implementing Rules of Republic Act No. 9184. This is because the
construction of the Seaside Drive Extension did not fall within the
general scope of the original project; nowhere was the Extension found
in any of the bidding documents for the President Diosdado Macapagal
Boulevard Project, nor was it even located along the stretch of the
Boulevard. Accordingly, a separate award for the Seaside Drive Extension
should have been undertaken.[22]

Despite this, the ponencia absolves petitioners, saying
they had no participation in the award of Variation Order No. 2,
specifically petitioners Cristina Amposta-Mortel and Zorilla.[23]

The ponencia also finds there was no clear showing of
bad faith, manifest partiality, or gross inexcusable negligence in the
bid and award for Variation Order No. 2.[24] Particularly, the ponencia
states that members of the old Board of Directors of the Public Estates
Authority, particularly petitioners Daniel T. Dayan, Frisco F. San
Juan, Elpidio G. Damaso, Legaspi, and Carmelita Chan, “had every right
to rely on the report and recommendation of the Ad Hoc Committee” when it issued the Resolutions leading to the award of the Seaside Drive Extension under Variation Order No. 2.[25]

As to the members of the Ad Hoc Committee, specifically petitioners Manuel Beriña Jr. and Jaime R. Millan, the ponencia
holds that they “honestly believed that P.D. No. 1594 allows a
negotiated contract where a variation order is adjacent or contiguous to
an ongoing project and could be economically prosecuted by the same
contractor.”[26] This also justified the lack of presidential approval.[27]

I disagree with the ponencia‘s finding of clearing petitioners of criminal and civil liability. The Sandiganbayan’s decision should be affirmed.

Petitioner Amposta-Mortel’s position as Manager of the Public
Estates Authority’s Legal Department requires her to review and
recommend the legal instruments that involve her agency. Her signatures
in these instruments precisely signifies her participation, because they
are certifications that she had read and understood these documents. As
head of the Legal Department, her signature therefore meant that she
had reviewed the original Construction Agreement despite being aware of
the lack of funds for the transaction. Her role is not simply to be a
”rubber stamp” to the Agreement, as the Sandiganbayan puts it.[28]
The Sandiganbayan also notes her admissions in her Memorandum, where
she merely relied on the approval of the Office of the Government
Corporate Counsel and the Public. Estates Authority’s Board of Directors
without having an independent assessment of the Agreement. “Even a
cursory reading of the Construction Agreement against the Zamora
Memorandum would yield a finding of inconsistency, which should have
raised red flags in the mind of [Amposta-Mortel].”[29]
Her argument that she merely reviews matters which are brought to her
attention only further reveals her omission to act in instances where
her participation was necessary. She should be found guilty of the
charge.

The conviction of petitioner Zorilla, being the one who
prepared the Approved Agency Estate for the Project despite lack of
detailed engineering, should likewise be upheld. Preparing this despite
the lack of a detailed engineering plan is not simple negligence; this
is a crucial part in formulating an Approved Agency Estimate.[30]

As to petitioners who were part of the old Board of Directors of the
Public Estates Authority, namely petitioners Leo V. Padilla, Dayan, San
Juan, Damaso, Legaspi, and Chan, they should be convicted for their acts
of issuing Resolutions approving (1) the contract to Legaspi despite
the absence of actual loan proceeds, (2) the Variation Order No. 2
despite lack of bidding, and (3) the increase on the cost of Variation
Order No. 2. The Sandiganbayan also found that they failed to question
the Public Estates Authority Management on why the contract was divided
into two phases when what they approved was an “undivided” contract.[31]

Moreover, their reliance on the report and recommendation of the Ad Hoc Committee is misplaced. While Arias v. Sandiganbayan[32]
ruled that “[a]ll heads of offices have to rely to a reasonable extent
on their subordinates and on good faith of those who prepare bids,
purchase supplies, or enter into negotiations,” this is subject to a
qualification. In Abubakar v. People[33]:

The application of the doctrine is subject to the qualification
that the public official has no foreknowledge of any facts or
circumstances that would prompt him or her to investigate or exercise a
greater degree of care. In a number of cases, this Court refused to
apply the Arias doctrine considering that there were circumstances that should have prompted the government official to inquire further.[34] (Citations omitted)

The irregularities attending the bidding process for both the
President Diosdado Macapagal Boulevard Project and the Seaside Drive
Extension under Variation Order No. 2 should have prodded them, at the
very least, to investigate further. Their conviction should be upheld.

Additionally, petitioners Lacson, Beriña, Viray, and Millan were the
persons responsible for the supervision of the Project. They were
directly involved in the planning and execution of the project.

Petitioners Lacson, Beriña, and Viray, as part of the Ad Hoc Committee,
“prepare[d] the bid documents, evaluate[d] the bidders’ qualifications,
evaluate[d] their submitted bids, and recommend[ed] plans,
specifications, invitations to bid, pre-qualifications, and all
pre-construction and construction activities to the Board for approval.”[35]
Meanwhile, petitioner Millan, who acted as Assistant General Manager,
was in charge of the “evaluation, processing, and approval of bids of
contractors, progress billings, and payments.”[36] Having direct participation in the prohibited acts, their convictions should also be affirmed.

Finally, as to petitioner Legaspi, who is a private individual,
the Sandiganbayan found that there was no evidence to show that he
conspired with the other petitioners during the start of the Project. It
was the Public Estates Authority’s management, specifically the Ad Hoc
Committee, that designed the splitting of the Project in to two phases.
Nevertheless, petitioner Legaspi pushed for the recommendation and
approval of Variation Order No. 2, so that his company could be awarded
the construction of the Seaside Drive Extension. He also claimed for
“overruns which made the final bill for the project 43% higher than that
of the original contract price.”[37]
It was his prompting that led the Public Estates Authority’s management
to present Variation Order No. 2 for the Seaside Drive Extension to the
Board as a simple change order to the original contract, thereby
violating the rules on public bidding.[38]

Moreover, petitioner Legaspi proceeded with the construction of the
Seaside Extension Drive despite the lack of a Notice to Proceed and
presidential approval, in contradiction to the requirement under the
original Construction Agreement. These “surrounding circumstances and
legal provisions all yield to the same conclusion that there was implied
conspiracy between [petitioner] Legaspi and the [Public Estates
Authority’s] management.”[39]

Despite these, the ponencia
rules that the prosecution failed to prove they acted with manifest
partiality, evident bad faith, or gross inexcusable negligence, and
acquits petitioners.

For a conviction of violation of Section 3(e), the following elements must be present:

  1. The accused must be a public officer discharging administrative, judicial or official functions;
  2. He [or she] must have acted with manifest partiality, evident bad faith or [gross] inexcusable negligence;
  3. That his [or her] action caused any undue injury to any party,
    including the government, or giving any private party unwarranted
    benefits, advantage or preference in the discharge of his functions.[40]

The ponencia found that the prosecution failed to show
corrupt motives in the irregularities committed during bidding and award
of the President Diosdado Macapagal Boulevard Project, as well as the
Seaside Drive Extension under Variation Order No 2. It assessed this
element as against petitioners’ individual acts. I disagree.

In Abubakar[41]:

The second element provides the modalities by which a violation of
Section 3(e) of Republic Act No. 3019 may he committed.” Manifest
partiality,” “evident bad faith,” or “gross inexcusable negligence” are
not separate offenses, and proof of the existence of any of these three
(3) “in connection with the prohibited acts . . . is enough to convict.”[42]

Thus, independent proof of the second element is not necessary.
Manifest partiality, evident bad faith, or gross inexcusable negligence
can be proven through the manner by which the prohibited acts are
committed. In other words, these “merely describe the mode by which the
offense penalized in Section 3(e) of the statute may be committed.”[43]

The Sandiganbayan was correct in looking at the totality of
petitioners’ conducts to find the presence of manifest partiality,
evident bad faith, or gross inexcusable negligence. After all, corrupt
practices are often done through a series of discrete acts that, when
taken together, reveal ill motives.

The construction of the
President Diosdado Macapagal Boulevard was a flagship infrastructure
project, and this huge undertaking by the national government involved
large sums of money. “The rules on competitive bidding and those
concerning the disbursement of public funds are imbued with public
interest. Government officials whose work relates to these matters are
expected to exercise greater responsibility in ensuring compliance with
the pertinent rules and regulations.”[44]

ACCORDINGLY, I vote to DENY
the Petitions. The Sandiganbayan Decision and Joint Resolution dated
February 5, 2015 and September 16, 2015 finding petitioners Cristina
Amposta-Mortel, Theron Victor V. Lacson, Leo V. Padilla, Manuel Beriña,
Jr., Jaime R. Millan, Bernardo T. Viray, Raphael Pocholo A. Zorilla,
Daniel T. Dayan, Frisco F. San Juan, Elpidio G. Damaso, Carmelita D.
Chan, and Jesusito Legaspi guilty of violation of Republic Act No. 3019
should be AFFIRMED.


[1] Rollo (G.R. No. 220500), p. 242.

[2] Id. at 242-243.

[3] Ponencia, pp. 5-6.

[4] Id. at 6.

[5] Rollo (G.R. No. 220500), p. 92, citing Implementing Rules and Regulations of Presidential Decree No. 1594, as amended, IB 10.4.2.5, July 12, 1995.

[6] See Republic Act No. 4566 (1965), a amended by residential Decree No. 1746 (1980).

[7] Rollo (G.R. No. 220500), pp. 192-193.

[8] Ponencia, pp. 43-44.

[9] Id. at 44.

[10] Rollo (G.R. No. 220500), p. 194.

[11] Id. at 193.

[12] Id. at 192-194.

[13] Id. at 193-194.

[14] Ponencia, p. 46.

[15] Rollo (G.R. No. 220500), p. 199.

[16] Id. at 198-199.

[17] Id. at 199.

[18] Id.

[19] Id. at 200.

[20] Ponencia, pp. 54-55.

[21] Id. at 56.

[22] Id. at 56-58.

[23] Id. at 59.

[24] Id.

[25] Id.

[26] Id. at 60-61.

[27] Id. at 62.

[28] Rollo (G.R. No. 220500), p. 229.

[29] Id. at 229.

[30] Id. at 226.

[31] Id. at 230.

[32] 259 Phil. 794 (1989) [Per J. Gutierrez, Jr., En Banc].

[33] G.R. Nos. 202408, 202409 & 202412, June 27, 2018 [Per J. Leonen, First Division].

[34] Id.

[35] Rollo (G.R. No. 220500), p. 224.

[36] Id. at 224.

[37] Id. at 239.

[38] Id.

[39] Id. at 239-241.

[40] Id. at 242.

[41] G.R. Nos. 202408, 202409 & 202412, June 27, 2018 [Per J. Leonen, First Division].

[42] Id. citing Gallego v. Sandiganbayan, 201 Phil. 379, 383 (1982) [Per J. Relova, En Banc] and Sison v. People, 628 Phil. 573, 583 (2010) [Per J. Corona, Third Division].

[43] See Gallego v. Sandiganbayan, 201 Phil. 379, 383 (1982) [Per J. Relova, En Banc].

[44] Abubakar v. People, G.R. Nos. 202408, 202409 & 202412, June 27, 2018 [Per J. Leonen, First Division].