Movertrade versus Commission on Audit

The Case

This is a petition for certiorari filed by Movertrade Corporation against the Commission on Audit and the Department of Public Works and Highways, assailing the decision of the Commission on Audit Commission Proper that denied its money claim of 43,725,016.23 pesos for additional dredging works undertaken in connection with the Mount Pinatubo Rehabilitation Program. The case matters because it gathers into one ruling the procedural discipline required of money claims against the government and the substantive rule that a contractor bound by a written contract, who breaches it, cannot fall back on quantum meruit, which means payment for services according to what is deserved absent a contract.

Procedural History

Movertrade filed its money claim directly before the Commission on Audit Commission Proper, which has original jurisdiction over money claims against the government. In its decision, the Commission Proper denied the claim. Instead of moving for reconsideration, Movertrade went straight to the Supreme Court by petition for certiorari. The Court treated the petition as one filed under Rule 64, it having been filed within the thirty-day period, and resolved it on the merits of the procedural and substantive objections.

Facts

Under an agreement dated February 7, 1996, the Department of Public Works and Highways contracted Movertrade to undertake dredging and related works in the Pampanga Bay and the Pasac-Guagua-San Fernando waterways affected by the Mount Pinatubo eruptions and mudflows, for a total contract amount of 188,698,000 pesos. Paragraph 19 of the agreement provided that the contract price shall be adjusted on a no loss, no gain basis if, during the effectivity of the contract, the cost of labor, equipment, materials and supplies should increase due to the direct costs of the Government.

During implementation, Movertrade undertook additional dredging work, which it said was an extreme measure to counter fast siltation of the river system. The additional work yielded a total volume of 984,354.26 cubic meters, equivalent to 43,725,016.23 pesos. Through letters in July and August 1998, Movertrade asked that its justification for the additional expenditures be studied by the Price Escalation Committee and the Arbitration Committee of the Department. It later demanded payment, and in 2007 the Officer-in-Charge of the Department's Legal Service opined that although the additional dredging works were not covered by a valid contract, recovery may be allowed on the basis of quantum meruit, but the approval portion of that memorandum was left unsigned by the Secretary. In 2010, Movertrade was informed that its claim, being a money claim against the government, should be filed before the Commission on Audit.

Movertrade then filed its money claim before the Commission Proper, anchoring it on the no loss, no gain provision, on the Legal Service memorandum invoking quantum meruit, and on a memorandum of the Project Director recommending payment. The Department countered that the claim had no factual basis, that the Conditions of Contract provide that contract prices are deemed inclusive of works associated with delays, and that under the Bid Book Form, work performed in excess of what is specified or shown in the drawings, unless ordered by the Department, will not be paid for.

Issues

  • Whether or not Movertrade's immediate resort to certiorari without first filing a motion for reconsideration before the Commission on Audit Commission Proper rendered the petition defective.
  • Whether or not the Commission on Audit Commission Proper committed grave abuse of discretion in denying the money claim.

Applicable Provisions

Paragraph 6 of the Agreement provides:

The CONTRACTOR shall strictly follow and adhere to the plans and specifications provided by the Department of Public Works and Highways including the direction of the Department of Public Works and Highways' Project Engineer or his Assistants assigned to supervise the works.

This clause bound Movertrade to the plans and specifications and to the direction of the Project Engineer, so that work outside them required prior approval.

Item III of the Bid Book Form, which Movertrade acknowledged, provides:

Any work which we performed in excess of what is specified or shown in the drawings, unless ordered by the Department of Public Works and Highways, will not be paid for.

This is the contractual bar on compensation for unauthorized excess work, and it defeats the claim on quantum meruit.

Ruling

On the first issue, the Court held that the petition must be dismissed for failure to move for reconsideration before the Commission Proper. The general rule requires the aggrieved party to first seek reconsideration from the tribunal that rendered the questioned judgment before resorting to certiorari, and the higher court may decline cognizance when the lower tribunal was deprived of the opportunity to correct its errors. This is especially crucial in a money claim against the government, because such actions are litigated for the first time before the Commission Proper. Movertrade pleaded no exception, and when the Solicitor General raised the defect, Movertrade did not address it in its reply.

On the second issue, the Court held that Movertrade's arguments were not bona fide imputations of grave abuse of discretion. At best, the complaint that the Commission Proper did not appreciate quantum meruit was a mere error of judgment, which cannot be corrected by certiorari, since the petitioner bears the burden of proving not merely reversible error but such a capricious and whimsical exercise of judgment as is equivalent to lack of jurisdiction.

Even setting the flaws aside, the Court held the petition unmeritorious. It recalled that Movertrade had earlier charged the Department for side dumping costs, and that the Court had affirmed the denial of that claim, ruling that contracts have the force of law between the parties and that a contractor cannot unilaterally change the manner of performance without amending the contract or obtaining the express consent or approval of the Department. The Court found that ruling applied squarely: the additional dredging works were undertaken without prior approval and in breach of the Agreement. Movertrade failed to establish that it obtained the requisite approval, or that the Department authorized the additional works. A contractor cannot recover compensation based on quantum meruit where he had been bound by a written agreement and then found guilty of breach thereof.

Doctrine

First, a motion for reconsideration is a prerequisite to certiorari; immediate resort without it renders the petition defective, especially in money claims against the government, which are litigated for the first time before the Commission on Audit Commission Proper. Second, grave abuse of discretion means capricious and whimsical exercise of judgment equivalent to lack of jurisdiction, not mere error of judgment. Third, quantum meruit does not apply where the parties are bound by a written agreement and the contractor is guilty of breach; under Paragraph 6 of the Agreement and Item III of the Bid Book Form, work done in excess of the specifications without the Department's order is not paid for.

Disposition

The petition was dismissed, and the denial of Movertrade's money claim by the Commission on Audit Commission Proper stood.

Remember This

Memorize this line: a contractor bound by a written contract and guilty of breach cannot recover on quantum meruit. Examiners use this case to test the reconsideration requirement before certiorari against the Commission on Audit and the limits of quantum meruit in government contracts.