O.F. CAMPBELL AND GO-TAUCO, PLAINTIFFS AND APPELLANTS, VS. BEHN, MEYER & CO., DEFENDANTS AND APPELLEES.
Listen, read along, or open presentation mode.
O.F. Campbell and Go-Tauco versus Behn, Meyer and Company
The Case
This is a civil action for the recovery of a sum of money arising from two building and filling contracts. O.F. Campbell and Go-Tauco, the plaintiffs and appellants, sued Behn, Meyer and Company, the defendants and appellees, to collect the unpaid balance due on a contract for the construction of a dwelling house and on a separate contract for filling a lot with earth and sand. The defendants resisted, claiming that the house was defectively built and that they had overpaid for filling that was never delivered, and they set up counterclaims. The case matters because it fixes two enduring rules of contract law: the doctrine of substantial performance where the owner accepts the work, and the doctrine of estoppel against a party who, by his own measurement, receipt, and payment, admits receipt of what he later denies.
Procedural History
The case was tried in the Court of First Instance of Manila. The trial judge found that the plaintiffs had defectively constructed the improvements and denied them any compensation beyond what they had already received, treating the unpaid balance as offset by the defendants' damages. The trial judge further found that the defendants had paid for at least 40,000 cubic meters of sand and dirt that were never placed on the lot, amounting to 52,000 pesos, and ordered that the complaint be dismissed and that the defendants recover that sum from the plaintiffs, with costs. The plaintiffs duly excepted and moved for a new trial. The case then came before the Supreme Court on appeal.
Facts
On June 20, 1901, the plaintiffs contracted with the defendants to fill a lot on the bank of the Pasig River, next to Malacañan Palace, with earth and sand of good quality at the rate of 1.30 pesos, Mexican currency, per cubic meter. The contract stated that the amount to be furnished would be over 15,000 cubic meters, delivered at the rate of 5,000 cubic meters monthly, with weekly payments. On July 20, 1901, the same parties entered into a second contract, under which the plaintiffs were to build a dwelling house on a lot in the city of Manila according to a plan and specifications, for 13,000 pesos payable in three installments, with additional sums for city water installation and for a stable, making a total of 15,000 pesos, the work to be finished within three months.
During the progress of the work the parties agreed to certain alterations and additions, and these were made. The plaintiffs charged 7,750 pesos for the extra materials and labor, making the total cost of the structures 22,750.62 pesos. The defendants paid 13,500 pesos, leaving an unpaid balance claimed by the plaintiffs of 9,250.62 pesos, for which they brought this action. The house was finished early in May 1902, and the defendants accepted it by moving into it at that time. During the work the defendants kept two engineers on the premises, one after the other, whose duty it was to see that the work was done in a workmanlike manner and according to the plans and specifications.
As to the filling, the sand was measured in bancas by an agent selected and paid by the defendants, receipts were given daily, and weekly bills were approved by the defendants' manager and then paid. The defendants paid for 62,690.50 cubic meters. Many months after delivery, the defendants' experts sank holes in the lot, allowed 15 per cent for settlement, and concluded that only about 20,965 cubic meters had been placed there. The plaintiffs' experts, of larger experience, testified that with an allowance for settlement of 31 to 38 per cent, the amount paid for could have been delivered.
Issues
- Whether or not the plaintiffs may recover the unpaid balance on the building contract despite defects in the house, the owner having accepted and occupied it.
- Whether or not the plaintiffs may be held liable in damages for defects traceable to the plans, specifications, and the directions of the owner's inspecting engineer.
- Whether or not the defendants may recover, on the ground of mutual mistake, sums paid for sand and earth measured, receipted, and paid for by their own agents.
Applicable Provisions
The decision does not quote a statutory text; it applies the common-law rule of substantial performance, which the Court states as follows:
Where the owner moves into the building contracted for, the rule of substantial performance should be applied in an action by the contractor.
This rule governs the building contract and defeats the trial court's measure of damages.
The Court also states the consequence of acceptance in these words:
By the very fact of accepting the house and occupying it, the defendants acknowledged that it was constructed substantially as required by the contract, plans, and specifications; and this is the law even when the work is not done according to the contract, but accepted.
This fixes the owner's position once he takes possession and occupies the structure.
On the filling contract, the Court applies the doctrine of estoppel in these words:
This case in the absence of evidence of a mutual mistake is governed by the doctrine of estoppel. The defendants measured the sand, they receipted for it, and they paid for it. They can not now say they did not receive it.
This disposes of the counterclaim for overpayment.
Ruling
On the first issue, the Court held that the plaintiffs are entitled to recover the unpaid balance of 9,250.62 pesos. The Court found that the contract, plans, and specifications were complied with, save for a variation to the advantage of the owner, namely that the principal posts rest upon layers of stone instead of upon the ground as the plan called for. The Court held that the trial court erred in adopting as the measure of damages what it would cost to take the building down and rebuild it, without proof of actual costs. Acceptance and occupation bound the defendants to pay the reasonable worth of what they received.
On the second issue, the Court held that the plaintiffs cannot be held liable for the defects. The foundations were built according to the plans and the pillars placed as the plans required, and the work was done under the eyes of the defendants' engineer without objection. The defects in the wood were due to the inferior grade of timber that the specifications themselves designated, and the plaintiffs cannot be responsible for defects of timber furnished as provided in their agreement and of the group and quality designated by the defendants. The settling of the house was due to the ground, to a defect in the plan, or to the directions of the inspecting engineer.
On the third issue, the Court held that the defendants cannot recover the sums paid for the filling. The burden was on the defendants to show that they did not receive the sand, and on the plaintiffs to show that they delivered the unpaid quantity. The defendants' later estimate was a mere approximation or guess, disputed by equally competent experts, while the original measurement was made by the defendants' own representatives at the time of each delivery, in the manner directed by their manager, and there was no proof of fraud or deceit. In the absence of unmistakable evidence of mutual mistake, estoppel barred the claim.
Doctrine
First, where the owner of a building contracted for moves into and occupies it, the rule of substantial performance applies in an action by the contractor; acceptance is an acknowledgment that the work was substantially done as required, even where it was not done strictly according to the contract.
Second, a contractor who follows the plans and specifications, and who works under the direction of the owner's inspecting engineer without objection from him, is not liable in damages for defects traceable to those plans, to the ground, or to the grade of materials the owner himself designated.
Third, the measure of damages is not the cost of tearing down and rebuilding, estimated without proof of actual costs.
Fourth, a party who measures, receipts for, and pays for goods delivered through his own agents cannot later deny receipt; in the absence of unmistakable evidence of mutual mistake, the doctrine of estoppel governs.
Disposition
The judgment of the court below was reversed: the plaintiffs recovered the unpaid balance of 9,250.62 pesos on the building contract, and the defendants' counterclaim for the filling was denied.
Remember This
Memorize the line that acceptance and occupation equal substantial performance, and that one who measures, receipts, and pays cannot later deny receipt absent unmistakable mutual mistake. Examiners use this case for the substantial performance rule in building contracts and for estoppel arising from a party's own measurements and payments.