ROBERTO AND JOSE T. FIGUERAS, PLAINTIFFS AND APPELLEES, VS. MANUEL VY-TIEPCO, DEFENDANT AND APPELLANT.
Listen, read along, or open presentation mode.
Figueras versus Vy-Tiepco
The Case
This is the case of Figueras versus Vy-Tiepco, a civil action for damages brought by Roberto Figueras and Jose T. Figueras against Manuel Vy-Tiepco, a building contractor. The plaintiffs sued to recover the sum of 1,544 pesos, which they claimed represented the value of work the defendant failed to complete under a written contract to build a house on Rosario Street in Iloilo. The case matters to a reviewee because it is an early and clean illustration of two enduring rules: the burden of proving a breach of contract rests on the party who alleges it, and a court cannot base its judgment on a document that was never shown to be the very instrument the parties agreed upon, especially where the opposing party seasonably objected to its admission.
Procedural History
The plaintiffs commenced the action in the Court of First Instance of Iloilo in May 1902. The defendant filed a demurrer to the complaint, but after argument the parties agreed that the defendant would withdraw the demurrer and that the plaintiffs would present the original plan according to which the house was to have been built. The defendant then filed his answer. The trial court rendered judgment in favor of the plaintiffs, in accordance with their prayer, upon the supposition that the defendant had failed to complete at least eleven items of the construction work. The defendant excepted to that judgment and prepared a bill of exceptions, which the trial judge allowed. The case was then brought to the Supreme Court for the determination solely of the questions of law raised therein.
Facts
On the twenty-ninth of January 1900, the parties agreed that the defendant would build a house on Rosario Street, Iloilo, in accordance with plans drawn for that purpose, and that construction would be completed within four months in strict conformity with the terms and conditions of the contract signed by the defendant and the plaintiff Jose Figueras. The plaintiffs alleged that the defendant did not build the house in accordance with the agreement, but left many parts uncompleted, diminishing the value of the work by 1,544 pesos, as shown by a statement of uncompleted items attached to the complaint. They demanded performance, the defendant refused, and they sued for damages.
In his answer, the defendant admitted the agreement and the four-month term, but insisted that he had fully performed the contract within the period fixed, with the exception of two arches between the dining room and the sitting room in the lower story. He claimed that these arches were omitted by order of the plaintiff Roberto Figueras, who, in the absence of Jose T. Figueras, had charge of the inspection of the work, and that the omission was directed because the plaintiffs intended to use that part of the premises as a storeroom, which they in fact did after the building was delivered. He further alleged that the plaintiffs paid him the balance of 1,000 pesos without making any claim, and paid an additional 600 pesos for other work not provided for in the agreement. He also asserted that the plan presented by the plaintiffs was not the plan to which the contract referred.
At trial, the plaintiffs presented a copy of a plan, over the defendant's objection that it was not the original plan to which the contract referred. The Supreme Court observed that it did not appear that the plan offered was the original plan forming part of the contract; on the contrary, the plan produced showed details and deficiencies demonstrating conclusively that it was not the one to be followed, that the original plan was never produced, and that the plan presented had been drawn subsequently.
Issues
- Whether or not the plaintiffs established a breach of contract by the defendant, in the absence of the original plan to which the contract referred.
- Whether or not the trial court erred in basing its judgment on a plan that was not shown to be the document agreed upon by the parties, over the defendant's timely objection.
Applicable Provisions
Section 497 of the Code of Civil Procedure governs the review of facts on appeal, and the Court invoked it to explain why it could not examine the evidence:
No motion for a new trial was made in compliance with the provisions of section 497 of the Code of Civil Procedure.
This provision bears on the case because, absent a motion for a new trial, the Supreme Court could not review the evidence or make findings upon the controverted facts, leaving only questions of law for its determination.
Ruling
On the first issue, the Court held that without the original plan it was impossible to hold that there had been any breach of the contract, that the contractor failed to perform the work specified in the statement presented, or that the plaintiffs were entitled to recover the amount claimed as the value of the work alleged to have been omitted. The plaintiffs, who alleged the breach, bore the burden of proving it by the very standard the contract fixed, and that standard was the original plan.
On the second issue, the Court held that the trial court erred in rendering judgment for the plaintiffs upon the ground that construction was not completed in accordance with the plan exhibited by them. The trial judge had taken as the basis of his decision a document which was not the one agreed upon and which was properly objected to by the defendant, since it was not shown to be the original plan referred to in the written contract. The Court put the matter plainly:
Without the original plan, it is impossible to hold that there has been any broach of the contract.
Accordingly, the judgment below was set aside.
Doctrine
First, a party who alleges a breach of contract must prove it by competent evidence, and where the contract fixes a specific standard, such as an original plan, the breach cannot be established without that standard. Second, a court cannot base its judgment on a document that was not shown to be the very instrument agreed upon by the parties, particularly where the opposing party seasonably objected to its admission. Third, and procedurally, the Supreme Court will not review the evidence or make findings upon controverted facts where no motion for a new trial was made in compliance with Section 497 of the Code of Civil Procedure; only questions of law may then be resolved.
Disposition
The Supreme Court set aside the judgment of the trial court and returned the case to the court below for a new trial at the instance of the plaintiffs, with the costs of the instance taxed against the plaintiffs.
Remember This
Memorize this line: without the original plan, it is impossible to hold that there has been any breach of the contract. Examiners use this case to test the burden of proof in actions for breach of contract and the rule that a judgment cannot rest on a document not shown to be the genuine agreement of the parties.