DOE, December 17, 1997
ADDITIONAL FEE FOR INCLUSION IN THE DOE REVISED SCHEDULE OF FEES AND CHARGES UNDER THE ENERGY RESEARCH LABORATORY (ERL)
National Administrative Register December 17, 1997
Costing for Mineral Analysis Using X-ray Flourescent Spectrometer 10 Elements/Sample (SiO2, Fe2O3, Al2O3 TiO2, CaO, MgO, Na2O, K2O, MnO2, and P2O5)
| 1. Equipment: | |
| Depreciation: ($199,686) (P 30/$) | |
| (1 year/1,825 days) (1 day/8 samples) | = 410.31 |
| Maintenance: ($6,000) (P 35/$) | |
| (1 year/264 days) (1 day/8 samples) | = 99.43 |
| Electricity: (13.86/kw-hr) (3 Kw) | |
| (0.80) (0.5 hr/sample) | = 16.63 |
| ———— | |
| P 526.37/sample | |
| 2. Calibration: | |
| Standards : ($4,000) (P 30/$)(1/264 days) | |
| (1 day/8 samples) | = 56.82 |
| Manpower : (P 881.86/day) (10 days/yr) | |
| (1 yr/264 days) (1 day/8 samples) | = 4.18 |
| ———— | |
| P 61.00/sample | |
| 3. Analysis: | |
| Manpower: (P 881.86/day) | |
| (1 day/8 samples) | = 110.00 |
| Gases: (P 17,803) (1/264 days) | |
| (1/8 samples) | = 8.43 |
| ———— | |
| P 118.43/sample | |
| 4. Sample Preparation: | |
| Equipment: ($11,800) (P30/$) (1/1825 days) | |
| (1/8 samples) | = P 24.25 |
| Electricity : (P 13.86/kw-hr) (1/3 hp) (0.746 kw) | |
| (0.17 hr/sample) | = P 0.58 |
| Manpower: (P 477.27/day) | |
| (1 day/8 samples) | = P 59.66 |
| Petri dish: (P 22/pc) (3 pcs/sample) | = P 66.00 |
| Caps: (P 11.40/pc) (3 pcs/sample) | = P 34.20 |
| Boric Acid: (P 1.016/g) (15g/sample) | = P 15.20 |
| ————— | |
| P 199.93/sample | |
| 5. Ashing | |
| Manpower: (P 75/hr) (5 hrs/5 sample) | = P 75.00 |
| Equipment Depreciation: | |
| (DM12,967) (P 18.5/DM) (1/5 yrs) | |
| (1/1320 samples) | = P 36.35 |
| Electricity: (P 13.86/kw-hr) (5kw) | |
| (0.80) (5 hrs) | = P 277.20 |
| Consumables: (540/crucible & disk liner) | |
| (1 c & dl/10 samples) | = P 54.00 |
| ————— | |
| P 442.55/sample | |
| Total | = P 1,348.00/sample |
| +10% Incidentals | = P 1,500.00/sample |
Adopted: 17 Dec. 1997
(SGD.) CESAR V. RAMIREZ
OIC-Assistant Secretary