SUPPLEMENTAL GUIDELINES ON THE DEMOLITION OF SCHOOL BUILDINGS

National Administrative Register April 3, 2000 [ DECS ORDER NO. 48, S. 2000, July 24, 2000 ]



1.         In order to clarify procedures on the condemnation and
demolition of school buildings which are perceived to be hazardous,
these guidelines are hereby formulated, amending DECS Memorandum No.
162, s. 2000 dated April 3, 2000 entitled “Requests for Demolition of
School Buildings”.

2.         As a matter of policy, demolition should be resorted to only when:

a.    the physical structure is beyond reasonable repair;
b.    it poses danger to the safety of school children; and
c.    the school administration can assure continuity of school operations even when the structure is demolished.

3.         The following shall constitute the revised guidelines:

a.      The school head, through the schools superintendent,
requests for an ocular inspection/assessment of the school
building/structure to be condemned/demolished from the Building Official
(Municipal/City Engineer’s Office, whoever is available);

b.      The Building Official conducts an inspection/assessment of
the building and submits a report/recommendation thereof to the school
officials concerned;

c.       The school head requests from the schools superintendent
for authority to demolish the condemned building based on the reports,
findings and recommendation of the Building Official. If the building is
insured, the school head should inform the insurance firm of the plan
to demolish the structure;

d.      Upon approval, the schools superintendent, through the
Regional Director, forwards the request to the Central Office for
further evaluation. The documents shall include, among others, the
following:

1.    report/recommendation of the Building Official;
2.    photographs of the building to be demolished showing damaged sections;
3.    certification issued by the school head that, if the building
is demolished, classes need not be disrupted due to lack of classrooms;
4.    PTCA or Alumni Association’s clearance in case of school
buildings with historical value e.g. Gabaldon type school buildings,
those which are at least 50 years old, etc.; and
5.    Indication of probable funding for replacement.

e.      The Central Office evaluates requests, conducts
inspections, if necessary makes recommendations and issues clearance for
demolition;

f.        The school head applies for Demolition Permit from the Building Official;

g.      The school head informs the Office of the Commission on
Audit/Resident Auditor and requests clearance/relief from responsibility
so that the structure will be dropped from the account of the school
once demolished;

h.       As the Building Official issues the necessary permit, demolition work is conducted; and

i.        upon the completion of the demolition, the Building
Official issues a certification that the building has been dropped from
the account of the school.

4.         Priority should be given to structures already provided
with funds for replacement from various sources and should be ready for
immediate occupancy during the school year.

5.         Immediate dissemination of this Order is directed.

Adopted: 24 July 2000

(SGD.) ANDREW GONZALEZ, FSC
Secretary