DPWH DEPARTMENT ORDER NO. 47, April 20, 1992
SUSPENSION/BLACKLISTING OF LVM CONSTRUCTION
Since LVM Construction/Luz V. Mercado are liable for the following:
a) the total daily penalty up to and including the day immediately the date the Government effectively took over the Works; and
b) the excess cost incurred by the Government in the completion of the Contract either by administration or reletting the same, over the contract price including the cost of supervision and inspection from the time the Government effectively takes over the Works
pursuant to Clause 100 of the DPWH Standard Specifications 1988 and Section 3 of Presidential Decree 1870, which liabilities can be determined only after the completion and acceptance of the project and the expiration of the maintenance period, all concerned are hereby ordered not to release any sum of money to LVM Construction/Luz V. Mercado without prior clearance from the Secretary.
For strict compliance.
Adopted: 20 Apr. 1992
Secretary