AMENDMENT TO D.O NO. 10, SERIES OF 2009 ON THE ALLOCATION OF THE AUTHORIZED 3% DEDUCTIONS FROM PROJECT FUNDS FOR ENGINEERING AND ADMINISTRATIVE OVERHEAD (EAO) EXPENSES
For Foreign-Assisted Projects:
Percentage of Deductions/Retentions from Project Fund TOTAL Central Office (CO)/PMO Equipment Reg. Office (RO) District Engineering Office (DEO) 2.25% 0.25% 0.25% 0.25% 3.00%
For Locally-Funded Projects (Directly Released to the Central Office):
Implementing Office Percentage of Deductions/Retentions from Project Fund TOTAL Central Office (CO) Regional Office (RO)District Engineering Office (DEO)
Central Office/ PMO-lmplemented 2.50%
0.25% 0.25% 3.00%RO-lmplemented 1.0% 1.75% 0.25% 3.00%DEO-lmplemented 1.0% 0.25% 1.75% 3.00%
For those directly released to the Regional Offices and District Offices, which are authorized to deduct not more than 2.5% and 2.00%, respectively, of project cost for EAO expenses, the breakdown of allocation which shall apply only to locally-funded projects, shall be as follows:
Implementing Office Percentage of Deductions/Retentions from Project Fund TOTAL Regional Office (RO)District Engineering Office (DEO)
RO-lmplemented 2.00% 0.50% 2.50%DEO-lmplemented 2.0% 2.0%
It is provided further that the engineering and administrative overhead expenses shall not be authorized for infrastructure projects costing Five Million Pesos (P5,000,000) and below.
This Order supersedes all previous issuances to the contrary and shall take effect immediately.
Adopted: 26 July 2011