SCHEDULE OF ERC FEES AND CHARGES, August 22, 2002
SCHEDULE OF ERC FEES AND CHARGES
Pursuant to the provisions of
Section 54 Chapter 12, Book IV of Executive Orders Nos. 292
(Administrative Code of 1987), 218 and 197 and DOF-DBM Joint Circular
No. 2000-2, the following revised schedule of fees and charges for
service rendered, which was approved by the Commission at its meeting
held on August 22, 2002, is hereby adopted for the Energy Regulatory Commission:
|
NATURE/NAME OF FEES |
LEGAL BASIS |
WITH SUPERVISION |
FEES |
WITHOUT SUPERVISION |
FEES |
||
|
|
|
|
|
|
|
||
|
I. |
|
|
|
|
|
||
|
|
|
|
|
|
|
||
|
1. |
Section 40(a), 16(a) Public service Act (C.A. No. 146 as amended); Section 43(p), R.A. No. 9136 |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
2. For approval or modification of Certificate of Public Convenience and/or Necessity of franchised electric utilities in accordance with law |
Section 43(p), R.A. No. 9136 |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
3. For modification of license of suppliers of electricity to the contestable market in accordance with law |
Section 29, R.A. No. 9136 |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
4. For authority to recover stranded costs by distribution utility |
Section 33,R.A. No. 9136 |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
5. For authority to recover cost and return on demand side management projects: |
Section 43(q), R.A. No. 9136 |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
6. For approval of any changes on the terms and conditions of service of the: |
Section 43(h), R.A. No. 9136 |
|
|
|
|
||
|
|
|
|
|
|
|
||
|
(a) TRANSCO or |
|
(a)700 |
00 |
— |
— |
||
|
(b) any distribution utility |
|
(b)700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
7. For approval of reappraisal of the elegible assets of: |
Section 43(i), R.A. No. 9136; Section 17(c), Public Service Law (C.A. No. 146) |
|
|
|
|
||
|
|
|
|
|
|
|
||
|
(a) TRANSCO or |
|
(a)700 |
00 |
— |
— |
||
|
(b) any distribution utility by an independent appraisal company |
|
(b)700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
8. For authority to improve or expand TRNSCO’s transmission facilities with the Grid Code and the Transmission Development Plan(TDP) |
Section 9(d), R.A. No. 9136; Section 20(b),Public Service Law (C.A. No. 146) |
700 |
00 |
— |
— |
||
|
|
|
|
|
|
|
||
|
9. |
Section 40(g),Public Service Law (C.A. No. 146) |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
10. |
Section 19, 24 25, 36 and 43 (u), R.A. No. 9136; Section 16(c) 20(a),Public Service Law (C.A. No. 146) |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
11. |
Section 20(g), C.A. No. 146 as amended; Section 43(p), R.A. No. 9136 |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
12. Authority to issue or increase capital stock |
Section 20(e), 40(f), C.A. No. 146 |
700 |
00 |
3,000 |
00 |
||
|
|
|
|
|
|
|
||
|
II. APPLICATION FOR THE PROVINCIONAL APPROVAL OF THE ABOVE-MENTIONED APPLICATIONS/PETITIONS, IF FILED SEPERATELY |
Section 8, E.O. No. 172; Section 44, R.A. No. 9136; Section 16©, C.A. No. 146 as amended |
500 |
00 |
2,100 |
00 |
||
|
|
|
|
|
|
|
||
|
III. |
|
500 |
00 |
1,500 |
00 |
||
|
|
|
|
|
|
|
||
|
IV. ANY APPLICATION OTHER THAN THE ABOVE |
|
500 |
00 |
1,500 |
00 |
||
In the above-mentioned applications under Items I, II, III, and IV:
a) UTILITIES that are paying Supervision Fees,
are charged only the Supply Material Expenses component of the fees but
not the Salary Expense component of the fees which is already included
in the Supervision Fee.
b) UTILITIES that are not paying the Supervision Fees,
are charged the full costs of the services rendered. The fees and
charges are user charges which are commensurate with the benefits
received from services rendered.
ITEM IV-A — Application for Certificate of Compliance (COC)
ITEM V — Supervision/Regulation Fee
ITEM VI — Certificate of Compliance/License Fee
ITEM VII — Issuance or Increase of Capital Stock
ITEM VIII — Increase of Equipment etc.
|
NAME/NATURE OF FEES |
Legal basis |
Amount of Fees |
|
|
|
|
|
IV-A, |
Section 6, R.A. No. 9136 |
P 10,000 (exclusive of actual cost of a technical audit/evaluation) |
|
|
|
|
|
V. Supervision and Regulation Fee: |
Section 40(e) C.A. No. 146 as amended; Section 43 (b) (f) (k) and (s) R.A. No. 9136 |
|
|
|
|
|
|
For |
|
|
|
|
|
|
|
For |
|
|
|
|
|
|
|
The said fees shall be paid on or before September 30th |
|
|
|
|
|
|
|
VI. License Fee: |
Section 6, 29 and 43(p), R.A. No. 9136 |
|
|
|
|
|
|
Supplies shall pay license fee on an annual basis and payable in four equal installments each year, computed as follows: |
|
|
|
|
|
|
|
For |
|
|
|
|
|
|
|
VII. For the issue or increase of capital stock |
Section 40(f) 20(e), C.A. No. 146 |
|
|
or |
|
|
|
|
|
|
|
VIII. |
Section 40(g) C.A. No.146; Section 43(p) R.A. No. 9136 |
|
|
|
|
|
|
For each one hundred pesos or fraction thereof the increased capital |
|
0.75 |
|
|
|
|
|
IX. LABORATORY FEES, for the inspection and certification of watthour |
||
|
|
WITH SUPERVISION ANS REGUALTION FEE |
WITHOUT SUPERVISION AND REGUALTION FEE |
WHOLESALER/ RETAILER/ DEALER FEE |
LIFELINE RATE FOR RESIDENTIAL CONSUMERS |
|
|
|
|
|
|
|
1. For Single Phase Meter |
|
|
|
|
|
|
|
|
|
|
|
a) Single Phase |
20 00 |
60 00 |
60 00 |
20 0 |
|
b) Single Phase with Demand |
30 00 |
90 00 |
90 00 |
– – |
|
c) Single Phase with Electronic Demand |
190 00 |
270 00 |
270 00 |
|
|
|
|
|
|
|
|
2. Polyphase Meter |
|
|
|
|
|
|
|
|
|
|
|
-Electro Mechanical/Panel Board (2 Stator) |
|
|
|
|
|
|
|
|
|
|
|
a) Without Demand |
60 00 |
170 00 |
170 00 |
– – |
|
b) With Demand |
70 00 |
200 00 |
200 00 |
– – |
|
c) With Electronic |
235 00 |
380 00 |
380 00 |
– – |
|
|
|
|
|
|
|
-Electro Mechanical/Panel Board (2 Stator) |
|
|
|
|
|
|
|
|
|
|
|
a) Without Demand |
80 00 |
|
220 00 |
220 00 |
|
|
|
|
|
|
|
b) With Demand |
90 00 |
|
250 00 |
250 00 |
|
|
|
|
|
|
|
c) With Electronic |
255 00 |
|
430 00 |
430 00 |
|
|
|
|
|
|
|
3. Electronic meter |
455 00 |
|
630 00 |
630 00 |
|
|
|
|
|
|
|
4. Integrating Pulse Meter |
765 00 |
|
1,480 00 |
1,480 00 |
|
|
|
|
|
|
|
5. Watt-hour Meter Standard |
|
|
|
|
|
|
|
|
|
|
|
a) Mechanical |
105 00 |
|
280 00 |
280 00 |
|
|
|
|
|
|
|
b) Electronic |
455 00 |
|
630 00 |
630 00 |
|
|
|
|
|
|
|
6. Other Metering Instrument |
455 00 |
|
630 00 |
630 00 |
UTILITIES that are paying Supervision Fees,
will be charged only the OPERATING EXPENSES component of fee in the
testing and calibration of single phase meters, electronic meters
(single phase and polyphase) and other electronic standard or equipment. But
when Special Testing Equipment (STE) will be used in the process, the
ADDITIONAL cost component of the fee will likewise be charged.
UTILITIES that are not paying the Supervision Fees, will be charged with the full cost of the testing and calibration of single phase meters, electronic meters (single phase and polyphase) and other electronic standard or equipment.
LIFELINE RATE
consisting of the OPERATING EXPENSE component of the testing fee will be
applied to single phase meters used by residential consumers. Applicable to meters brought into the laboratory by walk-in residential consumers.
WHOLESALERS/RETAILERS/DEALERS, who are engaged in the business of selling kilowatt-hour meters
will be charged the full costs of service rendered in testing and
calibration of meters, namely: Salary Expense, Operating Expense and
Additional cost expense for the use of Special Testing Equipment (STE)
in the process.
7. SPOT TEST — Inspection or certification made outside the meter laboratory of the Commission [Section 40(h), C.A. No. 146].
a) SPOT TEST OUTSIDE METRO MANILA
Laboratory fee per meter plus Field
Testing Charge equivalent to actual expenses incurred by the Engineer
assigned in the spot test of meters for those utilities without
supervision fees and for the wholesalers, retailers and dealers.
b) SPOT TEST WITHIN METRO MANILA
Laboratory fee
per meter plus additional two pesos (P2.00) per meter to cover the
expenses of the assigned Engineer in the spot test of meters for those
utilities without supervision fee and for the wholesalers, retailers and
dealers.
|
X. CERTIFICATION ISSUED |
Section 40(i), C.A. No. 146 as amended; |
P25.00 |
|
|
Section 44 and 80, R.A. 9136 |
|
|
|
|
|
|
XI. CERTIFIED copies of official documents in the files of the Commission |
Section 40(i), C.A. 146 as amended; Sections 44 and 80, R.A. 9136 |
P5.00 |
This new schedule of revised rates,
which supersedes the 1985 ERB Schedule of Fees and Charges, shall become
effective 15 days following the publication in a newspaper of general
circulation in the Philippines.
Adopted: 22 Aug. 2002
|
(SGD.) FE B. BARIN |
|
|
Chairman |
|
|
|
|
|
(SGD.) MARY ANNE B. COLAYCO |
(SGD.) OLIVER B. BUTALID |
|
Commissioner |
Commissioner |
|
(SGD.) CARLOS R. ALINDADA |
(SGD). LETICIA V. IBAY |
|
Commissioner |
Commissioner |