NIELSON & COMPANY, INC., PLAINTIFF-APPELLANT, VS. LEPANTO CONSOLIDATED MINING COMPANY, DEFENDANT-APPELLEE.

G.R. No. L-21601. December 17, 1966 December 17, 1966

← Read the full text of the decision

Listen, read along, or open presentation mode.

Nielson and Company versus Lepanto Consolidated Mining Company

The Case

This is an action for damages brought by Nielson and Company against Lepanto Consolidated Mining Company, arising from the latter's refusal to honor a pre-war management contract under which Nielson operated and managed Lepanto's mining properties. Nielson claims that the outbreak of the Pacific War suspended the contract, and that the period of suspension extended the life of the agreement, entitling it to resume management and to recover its fees and share of profits. Lepanto resists, invoking prescription and laches. The case matters because it is the leading authority on how a force majeure suspension clause in a management contract is construed, and on the distinction between prescription and laches.

Procedural History

Nielson filed the complaint before the Court of First Instance of Manila, which after trial rendered a decision dismissing the complaint, with costs, and likewise dismissed Lepanto's counterclaim for lack of sufficient evidence. Nielson appealed directly to the Supreme Court in view of the amount involved in the case.

Facts

On January 30, 1937, Nielson and Lepanto entered into an operating agreement whereby Nielson would operate and manage Lepanto's mining properties for a management fee of 2,500 pesos a month and a ten percent participation in net profits. The contract had a term of five years. In the latter part of 1941 the parties agreed to renew it for another five years, but in December 1941 the Pacific War broke out.

In January 1942 operations were disrupted. In February 1942 the mill, power plant, supplies, equipment, concentrates, and mines were destroyed upon orders of the United States Army to prevent their use by the invading Japanese forces. The Japanese thereafter occupied and operated the mines until they were ousted in August 1945. After liberation, Lepanto took possession and undertook rebuilding and reconstruction, which was not completed until 1948. On June 26, 1948 the mines resumed operation under the exclusive management of Lepanto.

Shortly after liberation, a disagreement arose. Nielson held that the war suspended the contract, so its life should be extended by the period of suspension. Lepanto contended that the contract expired in 1947 as originally agreed. No understanding was reached, and Nielson filed suit only on February 6, 1958.

Issues

  • Whether or not the management contract was suspended by reason of the war, and if so, for what period.
  • Whether or not such suspension had the effect of extending the term of the management contract for a period equivalent to the suspension.
  • Whether or not the action is barred by prescription and by laches.

Applicable Provisions

Clause II of the management contract, quoted by the Court, provides:

In the event of inundations, floodings of the mine, typhoon, earthquake or any other force majeure, war, insurrection, civil commotion, organized strike, riot, injury to the machinery or other event or cause reasonably beyond the control of NIELSON and which adversely affects the work of mining and milling; NIELSON shall report such fact to LEPANTO and without liability or breach of the terms of this Agreement, the same shall remain in suspense, wholly or partially during the terms of such inability.

This clause is the textual basis for the Court's finding that the contract was suspended, and for its ruling on the effect of that suspension.

Article 1371 of the Civil Code, cited by the Court, provides:

The intention of the parties is to be ascertained from their contemporaneous and subsequent acts.

The Court used this rule to determine the true meaning of the suspension clause from the parties' own conduct.

Ruling

On the first issue, the Court held that the contract was suspended from February 1942, when the mines ceased operation because of a cause clearly beyond Nielson's control that adversely affected the work of mining and milling. The suspension did not end upon liberation in August 1945, because rehabilitation and reconstruction continued; it ended only on June 26, 1948, when Lepanto officially resumed operations.

On the second issue, the Court held that the suspension extended the contract for a period equivalent to the suspension. It ascertained the parties' intention from their contemporaneous and subsequent acts under Article 1371. The minutes of Lepanto's board meeting of March 10, 1945 recorded its chairman, Attorney DeWitt, as stating that the contract would soon expire unless the obligations were suspended, and that a provision suspended its effects in cases like the present. The Court gave this statement more weight than DeWitt's later letter of October 20, 1945, because it was made against Lepanto's own interest and before its board. The testimony of Nielson's witnesses on the mining custom that suspension meant extension stood uncontradicted. The Court distinguished the cases cited by Lepanto, holding that stare decisis does not apply where the material facts are not analogous.

On the third issue, the Court held that laches does not bar the action. Prescription concerns the fact of delay; laches concerns the effect of delay. Prescription is statutory and fixed; laches is equitable and founded on inequity. Applying the elements of laches from Go Chi Gun versus Go Cho, the Court found the delay justified because Nielson had asserted its rights as early as 1945 and 1946 and had not abandoned them.

Doctrine

A force majeure clause suspends a management contract when two conditions concur: the event is reasonably beyond the contractor's control, and it adversely affects the work of mining and milling. The suspension lasts until operations can actually resume, including the period of rehabilitation. The suspension extends the contract for a period equivalent to the suspension, where the parties' contemporaneous and subsequent acts show that this was their intention under Article 1371. Laches is distinct from prescription: prescription is statutory and based on fixed time, while laches is equitable and based on the inequity of enforcing a stale claim. Stare decisis does not apply where the material facts of the prior case are not analogous.

Disposition

The Supreme Court reversed the trial court's decision, holding that the contract was suspended and extended and that the action was not barred, and remanded the case for further proceedings consistent with its ruling.

Remember This

Memorize this line: suspension under a force majeure clause extends the contract for the period of suspension when the parties' contemporaneous and subsequent acts so show. Examiners use this case to test the Article 1371 rule on ascertaining intent, and the classic distinction between prescription and laches.