DPWH DEPARTMENT ORDER NO. 27, S. OF 2010, May 11, 2010
CREATION OF THE DPWH INVESTMENT COORDINATION COMMITTEE (DPWH ICC) TO RATIONALIZE PROJECT INVESTMENTS
projects, whether locally-funded or foreign-assisted, and confirm their
consistency in terms of technical, financial, economic, social and
institutional development with the thematic and sectoral plans and
priorities of the Government, the DPWH Investment Coordination Committee
(DPWH ICC) is hereby created to be headed by the Assistant Secretary
for Planning.
Mainly, the DPWH ICC shall review the fiscal and economic
implications of an on- going or proposed project vis-Ã -vis the current
and future budgets of the Department. Recommendation/s for policy action
or direction when necessary shall be submitted by the DPWH ICC to the
Secretary through the Management Committee.
The scope of the DPWH ICC review shall cover new and on-going
programs and projects costing P300 million and above regardless of
funding source, and shall also include the following:
1. BOT or PPP projects;
2. Feasibility and Detailed Engineering Studies of projects for
funding allocation; and
3. Programs and projects involving change in scope, change in cost
above established sensitivity parameters and budget allocation relative
to original project cost and extension in implementation period or loan
validity,
In the course of its review, the DPWH ICC shall also check the
compliance or non-compliance of the project with regards to the
following parameters:
1. Technical readiness filters
2. Budget cover (e.g. funding strategy, forward obligational
authority, multi year obligational authority) both for loan proceeds and
local counterparts including taxes and duties
3. Value for money considerations
4. Reasonableness of cost vis-a-vis agency benchmarks
5. Consistency with DBM and NEDA policies;
6. Availability of ROW and/or ROW acquisition plan
7. Definitive commitment of participating LGUs, when and where
necessary, especially for ROW
8. Other required documentation (e.g. feasibility study,
implementation plan, required forms and internal/external project
approvals, RDC endorsement, Environmental Clearance
Certification/Certificate of Non-Coverage).
The DPWH ICC shall be supported by a Technical Working Group (TWG)
and assisted by a Secretariat. The composition of the DPWH ICC, TWG and
Secretariat shall be established under a separate Special Order.
The DPWH ICC can call upon any DPWH staff or official in the course
of its review in order to fulfill its mandate.
This Order shall take effect immediately.
Adopted: 11 May 2010
(SGD.) VICTOR A. DOMINGO
Acting Secretary