AMENDMENT TO THE SCHEDULE OF ERC FEES AND CHARGES

National Administrative Register [ ERC, December 15, 2003 ]



This revised schedule of rates which was approved by the Commission at its meeting held on 03 December 2003 amends Item IV-A of the Schedule of ERC Fees and Charges to read as follows:

NATURE OF FEES

LEGAL BASIS
AMOUNT OF FEES
     
IV-A For the issuance of Certificate of Compliance (COC) to Independent Power Producer (for 5 years duration) pursuant to the standards set for the generation of electric power.
Section 6 R.A. No. 9136
Php 10,000.00 (exclusive of actual cost a technical audit/evaluation)
 
 
IV-B For the issuance of Certificate of Compliance (COC) to the owner of a Self Generation Facilities with the following aggregate installed capacity (for 5 years duration) pursuant to the standards set for the generation of electric power:
Section 6 R.A. No. 9136
 
     
100 KW and below

  Php 1,500.00 (exclusive of actual cost for a technical audit/evaluation)
     
101 – 500 KW   Php 5,000.00 (exclu- of actual cost for a technical audit/evaluation)
     
501 – 999 KW   Php 7,500.00 (exclusive of actual cost for a technical audit/evaluation)
     
1 MW and above   Php 10,000.00 (exclusive of actual cost for a technical audit/evaluation)

This amendment to the Schedule of ERC Fees and Charges shall become effective fifteen (15) days following its publication in a newspaper of general circulation.

Adopted: 15 Dec. 2003

 

(SGD.) MANUEL R. SANCHEZ

Chairman
(SGD.) OLIVER B. BUTALID
(SGD.) CARLOS R. ALINDADA
Commissioner
Commissioner
(SGD.) LETICIA V. IBAY
(SGD.) JESUS N. ALCORDO
Commissioner
Commissioner